15111 W LEMAY ST 91406
Certificate Information: 15111 W LEMAY ST 91406
- Application / Permit
- 18010-20000-04551
- Plan Check / Job No.
- B18VN15871
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SFD with attached garage, floor plan Type A'-1. 30 lot small lot subdivision (lot 20/30).
- Permit Issued
- Issued on 6/4/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2018 | APPLICANT |
| Green Plans Picked Up | 10/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2018 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 10/10/2018 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 10/19/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 10/23/2018 | APPLICANT |
| Plan Check Approved | 4/2/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 6/4/2020 | LADBS |
| CofO in Progress | 6/10/2023 | HENRY KIM |
| Permit Finaled | 6/12/2023 | JOHN JANSON |
| CofO Issued | 6/12/2023 | JOHN JANSON |
| Permit Finaled | 6/12/2023 | JOHN JANSON |
Permit Application Clearance Information
| Hold | Cleared | 10/9/2018 | LOURDES RAMIRO |
| Hold | Cleared | 11/19/2018 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 1/3/2019 | MARKOS PEREZ-BRAN |
| ZA Case | Cleared | 3/13/2019 | ANNA VIDAL |
| ZA Case | Cleared | 3/13/2019 | ANNA VIDAL |
| Hydrant and Access approval | Cleared | 4/11/2019 | JOHN DALLAS |
| Address approval | Cleared | 4/18/2019 | HOWARD COOPER |
| Green Code | Cleared | 5/2/2019 | MICHAEL AYERS |
| Low Impact Development | Cleared | 12/18/2019 | ANDRES COVARRUBIAS |
| Miscellaneous | Cleared | 1/13/2020 | ADRIAN CASTRO |
| Permit | Cleared | 1/13/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/13/2020 | ADRIAN CASTRO |
| "Q" conditions | Cleared | 2/21/2020 | VINCENT QUITORIANO |
| Miscellaneous | Cleared | 2/21/2020 | VINCENT QUITORIANO |
| ZI | Cleared | 2/21/2020 | VINCENT QUITORIANO |
Contact Information
| Contractor | G N L Development Inc; Lic. No.: 981677-B | 5939 TOPEKA DRIVE TARZANA, CA 91356 |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
| JOSEPH SAGEN, (818) 774-4353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/6/2020 | Partial Approval | JOSEPH SAGEN |
| Underground Mechanical | 10/21/2020 | Corrections Issued | DONALD SUNSERI |
| Underground Mechanical | 10/23/2020 | Partial Approval | JOSEPH SAGEN |
| Underground Mechanical | 11/2/2020 | Partial Approval | JOSEPH SAGEN |
| Footing/Foundation/Slab | 11/9/2020 | Partial Approval | JOSEPH SAGEN |
| Excavation/Setback/Form/Re-Bar | 11/23/2020 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2021 | Partial Approval | JOSEPH SAGEN |
| Underground Mechanical | 2/26/2021 | Partial Approval | JOSEPH SAGEN |
| Deputy Wood Construction | 3/17/2021 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2021 | Partial Approval | JOSEPH SAGEN |
| Deputy Wood Construction | 4/16/2021 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2021 | Partial Approval | JOSEPH SAGEN |
| Insulation | 5/12/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Partial Approval | JOSEPH SAGEN |
| Insulation | 6/9/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2021 | Partial Approval | JOSEPH SAGEN |
| PLUMBING-Rough | 6/18/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| PLUMBING-Rough | 6/25/2021 | Partial Approval | JOSEPH SAGEN |
| Insulation | 6/30/2021 | Partial Approval | JOSEPH SAGEN |
| Insulation | 7/8/2021 | Partial Approval | JOSEPH SAGEN |
| PLUMBING-Rough | 7/22/2021 | Partial Approval | JOSEPH SAGEN |
| Deputy Wood Construction | 7/30/2021 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2021 | Partial Approval | JOSEPH SAGEN |
| Underground Mechanical | 7/30/2021 | Partial Approval | JOSEPH SAGEN |
| ELECTRICAL-Rough | 8/10/2021 | Partial Approval | JOSEPH SAGEN |
| ELECTRICAL-Rough | 8/18/2021 | Approved | JOSEPH SAGEN |
| PLUMBING-Rough | 8/18/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2021 | Partial Approval | JOSEPH SAGEN |
| PLUMBING-Rough | 8/27/2021 | Approved | JOSEPH SAGEN |
| Shower Pan | 8/27/2021 | Approved | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 8/31/2021 | Approved | JOSEPH SAGEN |
| Green Building Rough | 8/31/2021 | Approved | JOSEPH SAGEN |
| HVAC-Rough | 8/31/2021 | Approved | JOSEPH SAGEN |
| Verify Sprinkler Sign Off | 8/31/2021 | Approved | JOSEPH SAGEN |
| Drywall Nailing | 9/17/2021 | Approved | JOSEPH SAGEN |
| Interior/Exterior Lathing | 9/22/2021 | Partial Approval | JOSEPH SAGEN |
| Underground Mechanical | 1/20/2022 | Approved | SEAN WIRCH |
| Gas Test | 2/15/2022 | Approved | HENRY KIM |
| ELECTRICAL-Final | 12/7/2022 | Approved | JEFFREY PARD |
| HVAC-Final | 12/19/2022 | Approved | HENRY KIM |
| PLUMBING-Final | 1/4/2023 | Approved | HENRY KIM |
| Final | 5/11/2023 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 5/11/2023 | Approved | HENRY KIM |
| Green Building Final | 5/11/2023 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 5/11/2023 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 5/11/2023 | Approved | HENRY KIM |
| Final | 6/9/2023 | OK to Issue CofO | HENRY KIM |