6705 N SEPULVEDA BLVD 91411

Certificate Information: 6705 N SEPULVEDA BLVD 91411

Application / Permit
18010-20000-04546
Plan Check / Job No.
B18VN15871
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SFD with attached garage, floor plan Type A'-1. 30 lot small lot subdivision (lot 15/30).
Permit Issued
Issued on 6/4/2020
Issuing Office
West Los Angeles
Current Status
CofO Corrected on 6/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2018 APPLICANT
Green Plans Picked Up 10/2/2018 APPLICANT
Assigned to Plan Check Engineer 10/4/2018 VLADIMIR ARUTYUNYAN
Corrections Issued 10/10/2018 VLADIMIR ARUTYUNYAN
Quality Review Completed 10/19/2018 CHON CHIO KUO
Building Plans Picked Up 10/23/2018 APPLICANT
Plan Check Approved 4/29/2020 VLADIMIR ARUTYUNYAN
Issued 6/4/2020 LADBS
CofO in Progress 6/13/2023 HENRY KIM
Re-Activate Permit 6/14/2023 JOHN JANSON
CofO Issued-Status Void 6/14/2023 JOHN JANSON
Permit Finaled-Status Void 6/14/2023 JOHN JANSON
Permit Finaled 6/14/2023 JOHN JANSON
CofO Corrected 6/14/2023 JOHN JANSON
Permit Finaled 6/14/2023 JOHN JANSON

Permit Application Clearance Information

Hold Cleared 10/9/2018 LOURDES RAMIRO
Hold Cleared 11/19/2018 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 1/3/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 1/3/2019 MARKOS PEREZ-BRAN
ZA Case Cleared 3/13/2019 ANNA VIDAL
ZA Case Cleared 3/13/2019 ANNA VIDAL
Hydrant and Access approval Cleared 4/11/2019 JOHN DALLAS
Address approval Cleared 4/18/2019 HOWARD COOPER
Green Code Cleared 5/2/2019 MICHAEL AYERS
Low Impact Development Cleared 12/18/2019 ANDRES COVARRUBIAS
Miscellaneous Cleared 1/13/2020 ADRIAN CASTRO
Permit Cleared 1/13/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/13/2020 ADRIAN CASTRO
"Q" conditions Cleared 2/21/2020 VINCENT QUITORIANO
Miscellaneous Cleared 2/21/2020 VINCENT QUITORIANO
ZI Cleared 2/21/2020 VINCENT QUITORIANO

Contact Information

Contractor G N L Development Inc; Lic. No.: 981677-B 5939 TOPEKA DRIVE      TARZANA, CA 91356
Engineer Jitechian,, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2020 Partial Approval JOSEPH SAGEN
Underground Mechanical 6/25/2020 Partial Approval JOSEPH SAGEN
Grounding or Bonding 8/5/2020 Approved JOSEPH SAGEN
Footing/Foundation/Slab 8/7/2020 Not Ready for Inspection JOSEPH SAGEN
Footing/Foundation/Slab 8/10/2020 Partial Approval JOSEPH SAGEN
Underground Mechanical 8/21/2020 Partial Approval JOSEPH SAGEN
Excavation/Setback/Form/Re-Bar 9/1/2020 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Partial Approval JOSEPH SAGEN
Structural Steel Frame 9/30/2020 Partial Approval JOSEPH SAGEN
Deputy Wood Construction 10/6/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 10/7/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 11/5/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Partial Approval JOSEPH SAGEN
Deputy Wood Construction 12/16/2020 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Partial Approval JOSEPH SAGEN
PLUMBING-Rough 12/24/2020 Partial Approval JOSEPH SAGEN
Deputy Wood Construction 1/6/2021 Approved SEAN WIRCH
ELECTRICAL-Rough 1/25/2021 Partial Approval JOSEPH SAGEN
PLUMBING-Rough 2/24/2021 Partial Approval JOSEPH SAGEN
Underground Mechanical 2/24/2021 Partial Approval JOSEPH SAGEN
Deputy Wood Construction 2/25/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Partial Approval JOSEPH SAGEN
BUILDING-Rough-Frame 3/25/2021 Partial Approval JOSEPH SAGEN
ELECTRICAL-Rough 3/25/2021 Approved JOSEPH SAGEN
Green Building Rough 3/25/2021 Approved JOSEPH SAGEN
HVAC-Rough 3/25/2021 Approved JOSEPH SAGEN
PLUMBING-Rough 3/25/2021 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 3/25/2021 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 4/1/2021 Approved JOSEPH SAGEN
Interior/Exterior Lathing 4/9/2021 Partial Approval JOSEPH SAGEN
Shower Pan 4/12/2021 Approved JOSEPH SAGEN
Underground Mechanical 7/14/2021 Partial Approval JOSEPH SAGEN
Underground Mechanical 7/27/2021 Partial Approval JOSEPH SAGEN
Gas Test 10/15/2021 Approved HENRY KIM
ELECTRICAL-Final 11/30/2022 Approved HENRY KIM
HVAC-Final 12/16/2022 Approved HENRY KIM
PLUMBING-Final 12/22/2022 Approved HENRY KIM
Final 3/31/2023 Corrections Issued HENRY KIM
Footing/Foundation/Slab 3/31/2023 Approved HENRY KIM
Green Building Final 3/31/2023 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Approved HENRY KIM
Service/Power Release 3/31/2023 Not Required HENRY KIM
Smoke Detectors 3/31/2023 Approved HENRY KIM
Final 5/11/2023 Corrections Issued HENRY KIM
Final 6/13/2023 OK to Issue CofO HENRY KIM