1316 S LONGWOOD AVE 90019
Certificate Information: 1316 S LONGWOOD AVE 90019
- Application / Permit
- 18010-20000-04522
- Plan Check / Job No.
- B18VN15984
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 31'-0" X 38'-0" IRREGULAR SHAPED THREE STORY SINGLE FAMILY DWELLING WITH ATTACHED CARPORT.
- Permit Issued
- Issued on 1/23/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/15/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | SARKIS HARABEDIAN |
| Corrections Issued | 10/17/2018 | SARKIS HARABEDIAN |
| Quality Review Completed | 10/22/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 10/23/2018 | APPLICANT |
| Green Plans Picked Up | 10/23/2018 | APPLICANT |
| Applicant returned to address corrections | 12/19/2018 | SARKIS HARABEDIAN |
| Plan Check Approved | 1/8/2019 | SARKIS HARABEDIAN |
| Issued | 1/23/2019 | LADBS |
| CofO in Progress | 10/14/2020 | STUART CHAPMAN |
| Permit Finaled | 10/15/2020 | DEROLD HAUFF |
| CofO Issued | 10/15/2020 | DEROLD HAUFF |
| Permit Finaled | 10/15/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2018 | KAYLA PEJI |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2018 | KAYLA PEJI |
| Hydrant and Access approval | Cleared | 12/10/2018 | GILBERT URREA |
| Sewer availability | Cleared | 12/10/2018 | KAYLA PEJI |
| Green Code | Cleared | 12/19/2018 | DAVID MATSON |
| Low Impact Development | Cleared | 1/7/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/7/2019 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , Dean,Almalla; Lic. No.: C58024 | 15053 VENTURA BLVD 205 SHERMAN OAKS, CA 91403 |
| Engineer | Sepich,, John Edward; Lic. No.: C37509 | 5655 LINDERO CANYON RD 106-3 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2019 | Partial Approval | CHARLENE BUSTAMANTE |
| METHANE-Barrier | 5/6/2019 | Not Ready for Inspection | CHARLENE BUSTAMANTE |
| METHANE-Subgrade | 5/6/2019 | Not Ready for Inspection | CHARLENE BUSTAMANTE |
| Excavation/Setback/Form/Re-Bar | 8/16/2019 | Corrections Issued | CHARLENE BUSTAMANTE |
| Footing/Foundation/Slab | 8/16/2019 | Partial Approval | CHARLENE BUSTAMANTE |
| METHANE-Barrier | 8/16/2019 | Not Ready for Inspection | CHARLENE BUSTAMANTE |
| METHANE-Subgrade | 8/16/2019 | Not Ready for Inspection | CHARLENE BUSTAMANTE |
| Underground Mechanical | 8/26/2019 | Approved | CHARLENE BUSTAMANTE |
| Deputy Methane Barrier | 9/9/2019 | Approved | CHARLENE BUSTAMANTE |
| Footing/Foundation/Slab | 9/9/2019 | Approved | CHARLENE BUSTAMANTE |
| METHANE-Barrier | 9/9/2019 | Approved | CHARLENE BUSTAMANTE |
| METHANE-Subgrade | 9/9/2019 | Approved | CHARLENE BUSTAMANTE |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2019 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2019 | Partial Approval | CHARLENE BUSTAMANTE |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2019 | Partial Approval | CHARLENE BUSTAMANTE |
| Structural Steel Frame | 11/12/2019 | Approved | CHARLENE BUSTAMANTE |
| ELECTRICAL-Rough | 1/29/2020 | Corrections Issued | ELMER BLAND |
| Gas Test | 1/29/2020 | Approved | ELMER BLAND |
| HVAC-Rough | 1/29/2020 | Not Ready for Inspection | ELMER BLAND |
| PLUMBING-Rough | 1/29/2020 | Approved | ELMER BLAND |
| ELECTRICAL-Rough | 2/4/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 2/4/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2020 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 2/12/2020 | Not Ready for Inspection | RAUL BARAJAS |
| METHANE-Rough | 2/12/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 2/12/2020 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 2/12/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2020 | Partial Approval | CHARLENE BUSTAMANTE |
| Green Building Rough | 2/21/2020 | Approved | CHARLENE BUSTAMANTE |
| METHANE-Rough | 2/21/2020 | Not Ready for Inspection | CHARLENE BUSTAMANTE |
| Verify Sprinkler Sign Off | 2/21/2020 | Not Ready for Inspection | CHARLENE BUSTAMANTE |
| Insulation | 3/3/2020 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 3/3/2020 | Partial Approval | RUBEN SALAS |
| Drywall Nailing | 3/17/2020 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 5/5/2020 | Partial Approval | THOMAS LOGRASSO |
| Sewer | 6/11/2020 | Corrections Issued | STUART CHAPMAN |
| Sewer | 6/17/2020 | Approved | STUART CHAPMAN |
| Green Building Final | 7/30/2020 | Corrections Issued | STUART CHAPMAN |
| Special/Order Compliance | 7/30/2020 | Partial Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 8/18/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/18/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 8/18/2020 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/18/2020 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Final | 8/18/2020 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Final | 8/18/2020 | Approved | STUART CHAPMAN |
| METHANE-Rough | 8/18/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/18/2020 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2020 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 8/18/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 8/18/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 8/18/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 9/15/2020 | Corrections Issued | STUART CHAPMAN |
| Final | 9/15/2020 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 9/15/2020 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 9/15/2020 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Final | 9/15/2020 | Approved | STUART CHAPMAN |
| Service/Power Release | 9/15/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 9/15/2020 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 9/24/2020 | Approved | STUART CHAPMAN |
| Final | 9/24/2020 | Conditional Approval | STUART CHAPMAN |
| Green Building Final | 9/24/2020 | Approved | STUART CHAPMAN |
| Service/Power Release | 9/24/2020 | Approved | STUART CHAPMAN |
| Smoke Detectors | 9/24/2020 | Approved | STUART CHAPMAN |