8756 N BAIRD AVE 91324

Certificate Information: 8756 N BAIRD AVE 91324

Application / Permit
18010-20000-04404
Plan Check / Job No.
B18VN15440
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
NEW (49.33'X 68.67') 1-STORY WAREHOUSE/MFG WITH MEZZANINE INCIDENTAL OFFICE.
Permit Issued
Issued on 7/21/2020
Issuing Office
Current Status
CofO Issued on 8/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2018 APPLICANT
Assigned to Plan Check Engineer 10/4/2018 DANNY MORALES
Green Plans Picked Up 10/5/2018 APPLICANT
Disabled Access Plans Picked Up 10/9/2018 APPLICANT
Corrections Issued 10/11/2018 DANNY MORALES
Quality Review Completed 10/15/2018 OMID HEDAYAT
Building Plans Picked Up 10/19/2018 APPLICANT
Applicant returned to address corrections 12/27/2018 ABDUL CHEGENI
Plan Check Approved 8/26/2019 ABDUL CHEGENI
Issued 7/21/2020 APPLICANT
CofO in Progress 8/25/2022 DANNY RODRIGUEZ
Permit Finaled 8/31/2022 JEFFREY DURAN
CofO Issued 8/31/2022 JEFFREY DURAN
Permit Finaled 8/31/2022 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 11/19/2018 MARKOS PEREZ-BRAN
Bicycle Parking Cleared 11/19/2018 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 11/19/2018 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 11/19/2018 GEORGE SUCHAND
Sewer availability Cleared 11/19/2018 MARKOS PEREZ-BRAN
DAS Clearance Cleared 12/4/2018 NORLITO MEDRANO
Trees in Parkway Cleared 12/11/2018 ADRIAN SANCHEZ
"Q" conditions Cleared 12/19/2018 RINA LARA
Highway dedication Cleared 12/19/2018 JEANETTE VONG
Permit Cleared 12/19/2018 JEANETTE VONG
Low Impact Development Cleared 12/24/2018 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 12/24/2018 JEANETTE VONG
Green Code Cleared 1/11/2019 PARISA ZAHABI
"T" removal Cleared 8/8/2019 RINA LARA

Contact Information

Architect , ; Lic. No.: C24001       ,
Contractor Kash Construction & Management Services; Lic. No.: 948617-B 533 S LOS ANGELES STREET #504      LOS ANGELES, CA 90013
Engineer Wahba,, Wahba Faris; Lic. No.: C33667 10041 SYLVIA AVE      NORTHRIDGE, CA 91324

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 11/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/29/2020 Not Ready for Inspection HAMID PISHEHVAR
Pre-Inspection 1/4/2021 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Concrete 1/8/2021 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 1/26/2021 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 2/2/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/3/2021 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/31/2021 No Access for Inspection DANNY RODRIGUEZ
Green Building Rough 4/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 4/22/2021 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/30/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 5/7/2021 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 5/7/2021 Approved HAMID PISHEHVAR
Pre-Inspection 5/17/2021 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 5/18/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/18/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/19/2021 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 5/19/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/24/2021 Conditional Approval JEFFREY DURAN
Green Building Rough 5/27/2021 Partial Approval HAMID PISHEHVAR
Reinforced Masonry Frame 5/27/2021 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 5/27/2021 Not Ready for Inspection HAMID PISHEHVAR
Deputy Reinf. Masonry 5/28/2021 Conditional Approval JEFFREY DURAN
Green Building Rough 6/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 6/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 6/10/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 6/14/2021 Conditional Approval RICKEY JACKSON
Reinforced Masonry Frame 6/18/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 6/22/2021 Approved HAMID PISHEHVAR
Deputy Steel/Welding 7/16/2021 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 7/20/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/20/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 7/20/2021 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Partial Approval DANNY RODRIGUEZ
Pre-Inspection 7/22/2021 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 8/10/2021 Not Ready for Inspection KENNETH ROBERTS
Verify Sprinkler Sign Off 8/10/2021 Not Ready for Inspection KENNETH ROBERTS
Wood Frame 8/10/2021 Not Ready for Inspection KENNETH ROBERTS
Green Building Rough 10/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 10/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 10/27/2021 Approved DANNY RODRIGUEZ
Insulation 10/27/2021 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/27/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 10/27/2021 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 11/4/2021 Approved KENNETH ROBERTS
Pre-Inspection 11/18/2021 Partial Inspection DANNY RODRIGUEZ
Final 3/29/2022 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 3/29/2022 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 3/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/29/2022 SGSOV No Gas DANNY RODRIGUEZ
Smoke Detectors 3/29/2022 Approved DANNY RODRIGUEZ
Structural Steel Frame 3/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/29/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Final 5/24/2022 OK to Issue CofO DANNY RODRIGUEZ
Footing/Foundation/Slab 5/24/2022 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 5/24/2022 Approved DANNY RODRIGUEZ
Structural Steel Frame 5/24/2022 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/24/2022 Approved DANNY RODRIGUEZ
Wood Frame 5/24/2022 Approved DANNY RODRIGUEZ
Pre-Inspection 6/29/2022 Partial Inspection DANNY RODRIGUEZ