13126 W VAN NUYS BLVD 91331

Certificate Information: 13126 W VAN NUYS BLVD 91331

Application / Permit
18010-20000-04301
Plan Check / Job No.
B18VN15250
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
NEW 2 STORY RETAIL/OFF BLDG. Hours of operation will be from 7am to 11pm. - COMPLY WITH DEPARTMENT ORDER effective date 04/12/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
Permit Issued
Issued on 12/31/2020
Issuing Office
Current Status
CofO Issued on 2/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2018 APPLICANT
Assigned to Plan Check Engineer 10/4/2018 RODNEY SAMIIAN
Disabled Access Plans Picked Up 10/5/2018 APPLICANT
Green Plans Picked Up 10/5/2018 APPLICANT
Corrections Issued 10/11/2018 RODNEY SAMIIAN
Quality Review Completed 10/15/2018 ABDUL CHEGENI
Building Plans Picked Up 10/16/2018 APPLICANT
Applicant returned to address corrections 3/13/2019 RODNEY SAMIIAN
Applicant returned to address corrections 3/18/2019 RODNEY SAMIIAN
Applicant returned to address corrections 5/6/2019 RODNEY SAMIIAN
Applicant returned to address corrections 3/3/2020 RODNEY SAMIIAN
Applicant returned to address corrections 4/15/2020 RODNEY SAMIIAN
Applicant returned to address corrections 6/8/2020 RODNEY SAMIIAN
Plan Check Approved 7/29/2020 RODNEY SAMIIAN
Issued 12/31/2020 APPLICANT
CofO in Progress 1/22/2025 DANNY RODRIGUEZ
Permit Finaled 2/6/2025 RICKEY JACKSON
CofO Issued 2/6/2025 RICKEY JACKSON
Permit Finaled 2/6/2025 RICKEY JACKSON

Permit Application Clearance Information

Clean Up Green Up Cleared 10/23/2018 DENNIS CHEW
Eng Process Fee Ord 176,300 Cleared 10/23/2018 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 10/23/2018 DENNIS CHEW
ZI Cleared 10/23/2018 DENNIS CHEW
"Q" conditions Cleared 12/21/2018 DANALYNN DOMINGUEZ
Supp. Use District POD/CDO/TDO Cleared 12/21/2018 DANG NGUYEN
ZI Cleared 12/21/2018 DANG NGUYEN
Comm Cor/Mini-Mall Cleared 1/11/2019 RINA LARA
Address approval Cleared 3/5/2019 HOWARD COOPER
Sewer availability Cleared 3/5/2019 JOHN LIN
Hydrant and Access approval Cleared 8/15/2019 GILBERT URREA
DAS Clearance Cleared 8/19/2019 NORLITO MEDRANO
Green Code Cleared 2/3/2020 DAVID MATSON
Highway dedication Cleared 5/1/2020 JOHN LIN
Permit Cleared 5/1/2020 JOHN LIN
Low Impact Development Cleared 6/25/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/25/2020 ADRIAN CASTRO
Comm Cor/Mini-Mall Cleared 7/24/2020 MAXFIELD VERMY

Contact Information

Contractor Mc Guan Construction & Plumbing; Lic. No.: 862056-B 21109 CROSS CREEK DR      SANTA CLARITA, CA 91350
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 4/30/2021 Corrections Issued ANDREW DORSO
METHANE-Subgrade 5/5/2021 Corrections Issued ANDREW DORSO
Deputy Methane Barrier 5/26/2021 Conditional Approval ANDREW DORSO
Special/Order Compliance 5/26/2021 Corrections Issued ANDREW DORSO
Deputy Grading 5/27/2021 Conditional Approval ANDREW DORSO
Deputy Methane Barrier 5/28/2021 Conditional Approval DANIEL VARNUM
METHANE-Rough 6/4/2021 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 6/16/2021 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 6/16/2021 Partial Approval DAVID BURKHEAD
METHANE-Barrier 6/16/2021 Partial Inspection DAVID BURKHEAD
METHANE-Subgrade 6/16/2021 Partial Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 6/18/2021 Conditional Approval DANNY RODRIGUEZ
Special/Order Compliance 8/13/2021 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/17/2021 Not Ready for Inspection JOHN KITCKO
Deputy Wood Construction 8/18/2021 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Corrections Issued DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/8/2021 Partial Approval CAMERON CHABAN
Deputy Wood Construction 9/23/2021 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 11/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Barrier 11/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Subgrade 11/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/24/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/6/2021 Partial Approval DANNY RODRIGUEZ
METHANE-Barrier 12/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Subgrade 12/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 1/5/2022 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 1/26/2022 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/28/2022 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 3/17/2022 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 3/23/2022 Corrections Issued DANNY RODRIGUEZ
Deputy Drilled-In Anchors 4/4/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Wood Construction 4/4/2022 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 4/5/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 4/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wall Anchors 4/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/13/2022 Partial Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 4/22/2022 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 4/25/2022 Partial Approval DANNY RODRIGUEZ
Pre-Inspection 11/10/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 11/29/2022 Corrections Issued EDWIN GREGORYONA
METHANE-Barrier 11/29/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 11/29/2022 Not Ready for Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 2/2/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 2/2/2023 Not Ready for Inspection STEVEN LEVITT
Insulation 3/28/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/4/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/4/2023 Approved DANNY RODRIGUEZ
Drywall Nailing 4/11/2023 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 5/2/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Final 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Green Building Final 11/29/2023 Not Ready for Inspection JEFFREY DURAN
METHANE-Barrier 11/29/2023 Not Ready for Inspection JEFFREY DURAN
METHANE-Final 11/29/2023 Not Ready for Inspection JEFFREY DURAN
METHANE-Rough 11/29/2023 Not Ready for Inspection JEFFREY DURAN
METHANE-Subgrade 11/29/2023 Not Ready for Inspection JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Not Ready JEFFREY DURAN
Smoke Detectors 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Wood Frame 11/29/2023 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 12/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 12/5/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 12/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Barrier 12/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Final 12/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 12/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Subgrade 12/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/5/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 12/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 4/11/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 11/21/2024 Approved GREGORY POMISH
Final 11/21/2024 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 11/21/2024 Approved GREGORY POMISH
Green Building Final 11/21/2024 Approved GREGORY POMISH
METHANE-Barrier 11/21/2024 Approved GREGORY POMISH
METHANE-Final 11/21/2024 Approved GREGORY POMISH
METHANE-Rough 11/21/2024 Approved GREGORY POMISH
METHANE-Subgrade 11/21/2024 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Approved GREGORY POMISH
Smoke Detectors 11/21/2024 Approved GREGORY POMISH
Special/Order Compliance 11/21/2024 Partial Inspection BRIAN KELLY
Verify Sprinkler Sign Off 11/21/2024 Approved GREGORY POMISH
Wood Frame 11/21/2024 Approved GREGORY POMISH
Final 12/12/2024 Not Ready for Inspection DANNY RODRIGUEZ
Final 12/23/2024 Partial Inspection DANNY RODRIGUEZ
Final 12/30/2024 Partial Inspection DANNY RODRIGUEZ
Final 1/14/2025 OK to Issue CofO DANNY RODRIGUEZ