6744 N LOUISE AVE 91406

Certificate Information: 6744 N LOUISE AVE 91406

Application / Permit
18010-20000-04262
Plan Check / Job No.
B18VN15057
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER AB494 & SB229
Permit Issued
Issued on 3/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2018 APPLICANT
Assigned to Plan Check Engineer 9/27/2018 NILOOFAR MEHRAIN
Green Plans Picked Up 10/3/2018 APPLICANT
Corrections Issued 10/10/2018 NILOOFAR MEHRAIN
Quality Review Completed 10/11/2018 CHON CHIO KUO
Building Plans Picked Up 10/12/2018 APPLICANT
Plan Check Approved 2/26/2020 NILOOFAR MEHRAIN
Issued 3/9/2020 LADBS
CofO in Progress 3/11/2021 STEVEN BACK
CofO Issued 3/23/2021 MICHAEL SMITH
Permit Finaled 3/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/15/2018 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/15/2018 LEE GUILBEAUX
Permit Cleared 10/15/2018 LEE GUILBEAUX
Sewer availability Cleared 10/15/2018 LEE GUILBEAUX
ZI Cleared 10/15/2018 DENNIS CHEW
Hydrant and Access approval Cleared 10/17/2018 JOHN DALLAS
Green Code Cleared 10/24/2018 MICHAEL AYERS
Construction near power lines Cleared 4/30/2019 RIDWAN HARDY
Construction within easement Cleared 4/30/2019 RIDWAN HARDY
Low Impact Development Cleared 2/18/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/18/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/10/2020 Corrections Issued STEVEN BACK
PLUMBING-Rough 9/10/2020 Partial Approval STEVEN BACK
Sewer 9/10/2020 Approved STEVEN BACK
Footing/Foundation/Slab 9/16/2020 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 9/25/2020 Approved STEVEN BACK
Footing/Foundation/Slab 9/25/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 10/21/2020 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/21/2020 Corrections Issued STEVEN BACK
Verify Sprinkler Sign Off 10/21/2020 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 11/2/2020 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 11/17/2020 Approved STEVEN BACK
ELECTRICAL-Rough 11/17/2020 Approved STEVEN BACK
Green Building Rough 11/17/2020 Approved STEVEN BACK
HVAC-Rough 11/17/2020 Approved STEVEN BACK
PLUMBING-Rough 11/17/2020 Approved STEVEN BACK
Underground Mechanical 11/17/2020 Approved STEVEN BACK
Verify Sprinkler Sign Off 11/17/2020 Approved STEVEN BACK
Insulation 11/25/2020 Approved STEVEN BACK
Interior/Exterior Lathing 11/25/2020 Partial Approval STEVEN BACK
Drywall Nailing 12/3/2020 Approved STEVEN BACK
Interior/Exterior Lathing 12/3/2020 Approved STEVEN BACK
Final 2/23/2021 Corrections Issued STEVEN BACK
Green Building Final 2/23/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Approved STEVEN BACK
Service/Power Release 2/23/2021 Not Ready for Inspection STEVEN BACK
Smoke Detectors 2/23/2021 Approved STEVEN BACK
Final 3/11/2021 OK to Issue CofO STEVEN BACK
Service/Power Release 3/11/2021 Approved STEVEN BACK