9725 N SUNLAND BLVD 91040
Certificate Information: 9725 N SUNLAND BLVD 91040
- Application / Permit
- 18010-20000-04260
- Plan Check / Job No.
- B18VN15042
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 60' X 28' 8" STATE-APPROVED MANUFACTURED SINGLE FAMILY DWELLING OVER ENGINEERED FOUNDATION.
- Permit Issued
- Issued on 6/2/2020
- Issuing Office
- Current Status
- CofO Issued on 9/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2018 | GURUNATH NESARAJAH |
| Green Plans Picked Up | 10/1/2018 | APPLICANT |
| Corrections Issued | 10/3/2018 | GURUNATH NESARAJAH |
| Quality Review Completed | 10/9/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 10/11/2018 | APPLICANT |
| Plan Check Approved | 5/1/2020 | GURUNATH NESARAJAH |
| Issued | 6/2/2020 | APPLICANT |
| CofO in Progress | 7/19/2021 | MATTHEW NELSON |
| CofO in Progress | 9/3/2021 | MATTHEW NELSON |
| CofO Issued | 9/16/2021 | MICHAEL SMITH |
| Permit Finaled | 9/16/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 12/6/2018 | DAVID MATSON |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 2/4/2019 | JOHN DALLAS |
| ZI | Cleared | 2/4/2019 | STEVEN WECHSLER |
| GPI Written Notices | Cleared | 8/23/2019 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 8/23/2019 | GURUNATH NESARAJAH |
| ZI | Cleared | 8/23/2019 | DAISY BENICIA |
| Low Impact Development | Cleared | 9/3/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/3/2019 | ERIK BEASLEY |
| Specific Plan | Cleared | 10/10/2019 | NOAH MCCOY |
| Sewer availability | Cleared | 12/11/2019 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | William, Farish; Lic. No.: C30123 | 19432 CASTLEWOOD CREEK HUNTINGTON BEACH, CA 92648 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/12/2020 | Corrections Issued | BEAU COLLINS |
| Footing/Foundation/Slab | 11/12/2020 | Not Ready for Inspection | BEAU COLLINS |
| Excavation/Setback/Form/Re-Bar | 11/23/2020 | Approved | BEAU COLLINS |
| Footing/Foundation/Slab | 11/23/2020 | Approved | BEAU COLLINS |
| Structural Steel Frame | 1/14/2021 | Corrections Issued | BEAU COLLINS |
| Excavation/Setback/Form/Re-Bar | 2/18/2021 | Approved | BEAU COLLINS |
| Piling/Pier/Caisson | 2/18/2021 | Corrections Issued | BEAU COLLINS |
| PLUMBING-Rough | 3/19/2021 | Corrections Issued | BEAU COLLINS |
| Gas Test | 4/26/2021 | Approved | BEAU COLLINS |
| Service/Power Release | 4/26/2021 | Not Required | BEAU COLLINS |
| BUILDING-Rough-Frame | 5/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 5/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/4/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 5/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 5/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 5/4/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/13/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Drywall Nailing | 7/13/2021 | Approved | MATTHEW NELSON |
| Final | 7/13/2021 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 7/13/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/13/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/13/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 7/13/2021 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 7/13/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/16/2021 | Approved | MATTHEW NELSON |
| Final | 7/16/2021 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 7/16/2021 | Approved | MATTHEW NELSON |