9725 N SUNLAND BLVD 91040

Certificate Information: 9725 N SUNLAND BLVD 91040

Application / Permit
18010-20000-04260
Plan Check / Job No.
B18VN15042
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 60' X 28' 8" STATE-APPROVED MANUFACTURED SINGLE FAMILY DWELLING OVER ENGINEERED FOUNDATION.
Permit Issued
Issued on 6/2/2020
Issuing Office
Current Status
CofO Issued on 9/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2018 APPLICANT
Assigned to Plan Check Engineer 9/27/2018 GURUNATH NESARAJAH
Green Plans Picked Up 10/1/2018 APPLICANT
Corrections Issued 10/3/2018 GURUNATH NESARAJAH
Quality Review Completed 10/9/2018 OMID HEDAYAT
Building Plans Picked Up 10/11/2018 APPLICANT
Plan Check Approved 5/1/2020 GURUNATH NESARAJAH
Issued 6/2/2020 APPLICANT
CofO in Progress 7/19/2021 MATTHEW NELSON
CofO in Progress 9/3/2021 MATTHEW NELSON
CofO Issued 9/16/2021 MICHAEL SMITH
Permit Finaled 9/16/2021 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 12/6/2018 DAVID MATSON
Eng Process Fee Ord 176,300 Cleared 2/4/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 2/4/2019 JOHN DALLAS
ZI Cleared 2/4/2019 STEVEN WECHSLER
GPI Written Notices Cleared 8/23/2019 GURUNATH NESARAJAH
Grading Pre-Inspection Cleared 8/23/2019 GURUNATH NESARAJAH
ZI Cleared 8/23/2019 DAISY BENICIA
Low Impact Development Cleared 9/3/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/3/2019 ERIK BEASLEY
Specific Plan Cleared 10/10/2019 NOAH MCCOY
Sewer availability Cleared 12/11/2019 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer William, Farish; Lic. No.: C30123 19432 CASTLEWOOD CREEK      HUNTINGTON BEACH, CA 92648

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/12/2020 Corrections Issued BEAU COLLINS
Footing/Foundation/Slab 11/12/2020 Not Ready for Inspection BEAU COLLINS
Excavation/Setback/Form/Re-Bar 11/23/2020 Approved BEAU COLLINS
Footing/Foundation/Slab 11/23/2020 Approved BEAU COLLINS
Structural Steel Frame 1/14/2021 Corrections Issued BEAU COLLINS
Excavation/Setback/Form/Re-Bar 2/18/2021 Approved BEAU COLLINS
Piling/Pier/Caisson 2/18/2021 Corrections Issued BEAU COLLINS
PLUMBING-Rough 3/19/2021 Corrections Issued BEAU COLLINS
Gas Test 4/26/2021 Approved BEAU COLLINS
Service/Power Release 4/26/2021 Not Required BEAU COLLINS
BUILDING-Rough-Frame 5/4/2021 Not Ready for Inspection JOHN HAYES
Drywall Nailing 5/4/2021 Not Ready for Inspection JOHN HAYES
Final 5/4/2021 Corrections Issued JOHN HAYES
Green Building Final 5/4/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 5/4/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/4/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 5/4/2021 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 5/4/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/13/2021 Not Ready for Inspection MATTHEW NELSON
Drywall Nailing 7/13/2021 Approved MATTHEW NELSON
Final 7/13/2021 OK to Issue CofO MATTHEW NELSON
Green Building Final 7/13/2021 Approved MATTHEW NELSON
Green Building Rough 7/13/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/13/2021 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 7/13/2021 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 7/13/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 7/16/2021 Approved MATTHEW NELSON
Final 7/16/2021 OK to Issue CofO MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/16/2021 SGSOV Approved MATTHEW NELSON
Verify Sprinkler Sign Off 7/16/2021 Approved MATTHEW NELSON