10975 N CARTWRIGHT DR 91311
Certificate Information: 10975 N CARTWRIGHT DR 91311
- Application / Permit
- 18010-20000-04142
- Plan Check / Job No.
- B18VN14510
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE TWO STORY SFD WITH ATTACHED GARAGE _ STANDARD PLAN # 645 _ PLAN 7A
- Permit Issued
- Issued on 11/27/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2018 | APPLICANT |
| Green Plans Picked Up | 9/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2018 | DAWN MC NULTY |
| Corrections Issued | 9/24/2018 | DAWN MC NULTY |
| Quality Review Completed | 9/26/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 10/2/2018 | APPLICANT |
| Plan Check Approved | 11/27/2018 | DAWN MC NULTY |
| Issued | 11/27/2018 | LADBS |
| CofO in Progress | 6/21/2021 | SEAN WIRCH |
| CofO Issued | 6/29/2021 | MICHAEL SMITH |
| Permit Finaled | 6/29/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2018 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 10/23/2018 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 10/23/2018 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 10/23/2018 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2018 | MARKOS PEREZ-BRAN |
| Permit | Cleared | 10/23/2018 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 10/23/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 10/23/2018 | MARKOS PEREZ-BRAN |
| "Q" conditions | Cleared | 11/2/2018 | STEVEN WECHSLER |
| CPC | Cleared | 11/2/2018 | STEVEN WECHSLER |
| Frnt yard landscape/Water mgmt | Cleared | 11/2/2018 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 11/2/2018 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 11/2/2018 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 11/2/2018 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 11/2/2018 | STEVEN WECHSLER |
| Private street | Cleared | 11/2/2018 | STEVEN WECHSLER |
| Private street | Cleared | 11/2/2018 | STEVEN WECHSLER |
| Tract Map conditions | Cleared | 11/2/2018 | STEVEN WECHSLER |
| ZA Case | Cleared | 11/2/2018 | STEVEN WECHSLER |
| GPI Written Notices | Cleared | 11/13/2018 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 11/13/2018 | DAWN MC NULTY |
| Miscellaneous | Cleared | 11/13/2018 | DAWN MC NULTY |
| Green Code | Cleared | 11/14/2018 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 11/14/2018 | ROBERT DUFF |
| Low Impact Development | Cleared | 11/14/2018 | IDA MEISAMI-FARD |
Contact Information
| Architect | Gorrill, Ernest Bernard; Lic. No.: C13407 | 419 E BAY ST COSTA MESA, CA 92627 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Braatz, Tara Elizabeth; Lic. No.: C79028 | 38 RED BUD ALISO VIEJO, CA 92656 |
| Engineer | Christian, Dale Alan; Lic. No.: S2705 | 1744 W KATELLA AVENUE SUITE 107 ORANGE, CA 92867 |
| Engineer | Waddell, Ian Robertson; Lic. No.: C41219 | 519 10TH ST HUNTINGTON BEACH, CA 92648 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/15/2020 | Partial Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 9/29/2020 | Approved | SEAN WIRCH |
| Sewer | 10/8/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2020 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2020 | Not Ready for Inspection | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2021 | Not Ready for Inspection | DONALD SUNSERI |
| ELECTRICAL-Rough | 1/7/2021 | Approved | SEAN WIRCH |
| HVAC-Rough | 1/7/2021 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 1/7/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2021 | Partial Approval | SEAN WIRCH |
| BUILDING-Rough-Frame | 1/15/2021 | Corrections Issued | SEAN WIRCH |
| Green Building Rough | 1/15/2021 | Not Ready for Inspection | SEAN WIRCH |
| MERV13>=Rough | 1/15/2021 | Not Ready for Inspection | SEAN WIRCH |
| Verify Sprinkler Sign Off | 1/15/2021 | Not Ready for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 1/22/2021 | Corrections Issued | SEAN WIRCH |
| Green Building Rough | 1/22/2021 | Not Ready for Inspection | SEAN WIRCH |
| MERV13>=Rough | 1/22/2021 | Not Ready for Inspection | SEAN WIRCH |
| Underground Mechanical | 1/22/2021 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 1/22/2021 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 1/26/2021 | Approved | SEAN WIRCH |
| Green Building Rough | 1/26/2021 | Approved | SEAN WIRCH |
| MERV13>=Rough | 1/26/2021 | Approved | SEAN WIRCH |
| SWPPP-Const. Storm Water | 1/29/2021 | Completed | SEAN WIRCH |
| Drywall Nailing | 2/5/2021 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 2/5/2021 | Partial Approval | SEAN WIRCH |
| Interior/Exterior Lathing | 3/11/2021 | Partial Approval | SEAN WIRCH |
| Gas Test | 3/26/2021 | Approved | SEAN WIRCH |
| Service/Power Release | 4/13/2021 | Not Ready for Inspection | SEAN WIRCH |
| Service/Power Release | 4/19/2021 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 5/3/2021 | SGSOV Approved | JOSEPH SAGEN |
| ELECTRICAL-Final | 5/27/2021 | Approved | JOSEPH SAGEN |
| HVAC-Final | 5/27/2021 | Approved | JOSEPH SAGEN |
| Final | 6/4/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Green Building Final | 6/4/2021 | Approved | JOSEPH SAGEN |
| MERV13>=Final | 6/4/2021 | Approved | JOSEPH SAGEN |
| PLUMBING-Final | 6/4/2021 | Approved | JOSEPH SAGEN |
| Smoke Detectors | 6/4/2021 | Approved | JOSEPH SAGEN |
| Final | 6/10/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Final | 6/18/2021 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 6/18/2021 | Approved | SEAN WIRCH |
| Smoke Detectors | 6/18/2021 | Approved | SEAN WIRCH |