1160 N MONUMENT ST 90272

Certificate Information: 1160 N MONUMENT ST 90272

Application / Permit
18010-20000-04068
Plan Check / Job No.
B18VN14154
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW 2 STORY SFD W/ HABITABLE BASEMENT & 2-CAR GARAGE BELOW. AND ROOF DECK ABOVE. (TRUSS ROOF UNDER DEFERRED PERMIT)
Permit Issued
Issued on 10/2/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2018 APPLICANT
Assigned to Plan Check Engineer 9/20/2018 HAYATO TSUCHIYA
Corrections Issued 10/3/2018 HAYATO TSUCHIYA
Quality Review Completed 10/4/2018 ABDUL CHEGENI
Building Plans Picked Up 10/15/2018 APPLICANT
Green Plans Picked Up 10/15/2018 APPLICANT
Applicant returned to address corrections 1/31/2019 HAYATO TSUCHIYA
Applicant returned to address corrections 2/27/2019 HAYATO TSUCHIYA
Plan Check Approved 2/12/2020 HAYATO TSUCHIYA
Issued 10/2/2020 APPLICANT
CofO in Progress 3/25/2022 JOHN KIDWELL
Permit Finaled 4/15/2022 DANIEL ORRANTE
CofO Issued 4/15/2022 DANIEL ORRANTE
Permit Finaled 4/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/8/2018 KAYLA PEJI
Hydrant and Access approval Cleared 11/8/2018 JOHN DALLAS
Sewer availability Cleared 11/8/2018 KAYLA PEJI
Low Impact Development Cleared 11/15/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 11/19/2018 APEKSHYA BAJRACHARYA
Green Code Cleared 12/21/2018 MICHAEL AYERS
Grading Pre-Inspection Cleared 1/18/2019 HAYATO TSUCHIYA
GPI Written Notices Cleared 2/12/2020 HAYATO TSUCHIYA

Contact Information

Contractor J J P Construction Inc; Lic. No.: 960864-B 7379 GREENBUSH AVE      NORTH HOLLYWOOD, CA 91605
Engineer , ; Lic. No.: C72679       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/17/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 12/23/2020 Not Ready for Inspection KENNETH NAGLE
PLUMBING-Rough 12/23/2020 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 12/31/2020 Corrections Issued ANDREW NAVE
Footing/Foundation/Slab 12/31/2020 Not Ready for Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 1/4/2021 Not Ready for Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 1/5/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 1/5/2021 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 1/6/2021 Corrections Issued ROBERT SHELLY
Deputy Reinf. Concrete 1/11/2021 No Result Entered REINALDO SANCHEZ
Excavation/Setback/Form/Re-Bar 1/12/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 3/1/2021 Approved JOHN KIDWELL
Footing/Foundation/Slab 3/1/2021 Approved JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 3/9/2021 Corrections Issued JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 4/20/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Not Ready for Inspection JOHN KIDWELL
Wood Frame 5/25/2021 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Conditional Approval JOHN KIDWELL
Wood Frame 5/28/2021 Conditional Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/2/2021 Conditional Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Partial Inspection JUAN VALENZUELA
Deputy Wood Construction 6/10/2021 Conditional Approval ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 6/10/2021 Conditional Approval JOHN KIDWELL
Wood Frame 6/10/2021 Conditional Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 6/16/2021 Not Ready for Inspection JUAN VALENZUELA
Interior/Exterior Lathing 6/18/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 7/7/2021 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 7/7/2021 Approved JOHN KIDWELL
PLUMBING-Rough 7/7/2021 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 7/9/2021 Approved JOHN KIDWELL
PLUMBING-Rough 7/9/2021 Not Ready for Inspection JOHN KIDWELL
Gas Test 7/13/2021 Partial Approval JOHN KIDWELL
PLUMBING-Rough 7/13/2021 Approved JOHN KIDWELL
BUILDING-Rough-Frame 7/15/2021 Approved JOHN KIDWELL
Green Building Rough 7/15/2021 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 7/15/2021 Approved JOHN KIDWELL
Insulation 7/16/2021 Approved JOHN KIDWELL
Drywall Nailing 7/20/2021 Partial Approval MORRIS JACKSON
Drywall Nailing 7/26/2021 Approved ANDREW NAVE
Shower Pan 7/28/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 8/2/2021 Approved KRISTEN CAUSEY
Gas Test 11/12/2021 Corrections Issued JOHN KIDWELL
PLUMBING-Rough 11/12/2021 Not Ready for Inspection JOHN KIDWELL
Sewer 11/12/2021 Not Ready for Inspection JOHN KIDWELL
Gas Test 11/16/2021 Partial Approval KENNETH NAGLE
PLUMBING-Rough 11/16/2021 Partial Approval KENNETH NAGLE
Sewer 11/16/2021 Approved KENNETH NAGLE
Special/Order Compliance 11/17/2021 Corrections Issued JOHN KIDWELL
Special/Order Compliance 12/8/2021 Corrections Issued JOHN KIDWELL
Gas Test 2/3/2022 Partial Approval ANDREW NAVE
Special/Order Compliance 2/3/2022 Partial Inspection ANDREW NAVE
ELECTRICAL-Final 2/24/2022 Approved JOHN KIDWELL
PLUMBING-Final 3/4/2022 Corrections Issued ANDREW NAVE
Special/Order Compliance 3/4/2022 Not Ready for Inspection ANDREW NAVE
PLUMBING-Final 3/7/2022 Corrections Issued JUAN VALENZUELA
Final 3/15/2022 Corrections Issued JOHN KIDWELL
Green Building Final 3/15/2022 Approved JOHN KIDWELL
HVAC-Final 3/15/2022 Approved JOHN KIDWELL
PLUMBING-Final 3/15/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 3/15/2022 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 3/15/2022 Approved JOHN KIDWELL
Verify Rec and Parks Fee Memo 3/15/2022 Approved JOHN KIDWELL
Service/Power Release 3/16/2022 Approved MICHAEL PELHAM
Final 3/24/2022 OK to Issue CofO JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Approved JOHN KIDWELL