7734 N MASON AVE 91306

Certificate Information: 7734 N MASON AVE 91306

Application / Permit
18010-20000-03950
Plan Check / Job No.
B18VN13566
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY 31'-3" X 30'-5" ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 WITH ATTACHED 1-CAR GARAGE
Permit Issued
Issued on 10/24/2018
Issuing Office
Valley
Current Status
CofO Issued on 1/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2018 APPLICANT
Assigned to Plan Check Engineer 8/30/2018 SARAH YOUSSEF
Corrections Issued 9/5/2018 SARAH YOUSSEF
Quality Review Completed 9/7/2018 CHON CHIO KUO
Building Plans Picked Up 9/17/2018 APPLICANT
Green Plans Picked Up 9/17/2018 APPLICANT
Plan Check Approved 10/24/2018 SARAH YOUSSEF
Issued 10/24/2018 LADBS
CofO in Progress 12/12/2019 HENRY KIM
Permit Finaled 1/23/2020 DONALD SUNSERI
CofO Issued 1/23/2020 DONALD SUNSERI
Permit Finaled 1/23/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 10/10/2018 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 10/10/2018 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 10/10/2018 JOHN DALLAS
Sewer availability Cleared 10/10/2018 APEKSHYA BAJRACHARYA
Green Code Cleared 10/15/2018 PARISA ZAHABI
Low Impact Development Cleared 10/23/2018 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/24/2018 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/18/2018 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 12/21/2018 Partial Approval JOHN COLEMAN
Footing/Foundation/Slab 1/30/2019 Approved JOHN COLEMAN
BUILDING-Rough-Frame 4/30/2019 Partial Approval JOHN COLEMAN
Green Building Rough 4/30/2019 No Access for Inspection JOHN COLEMAN
Verify Sprinkler Sign Off 4/30/2019 Approved JOHN COLEMAN
BUILDING-Rough-Frame 6/10/2019 Partial Inspection JOSEPH SAGEN
ELECTRICAL-Rough 6/10/2019 Not Ready for Inspection JOSEPH SAGEN
Green Building Rough 6/10/2019 Not Ready for Inspection JOSEPH SAGEN
BUILDING-Rough-Frame 6/26/2019 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 6/26/2019 Approved JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 6/26/2019 Approved JOHN COLEMAN
Green Building Rough 6/26/2019 Approved JOHN COLEMAN
PLUMBING-Rough 6/26/2019 Approved JOHN COLEMAN
Shower Pan 6/26/2019 Approved JOHN COLEMAN
HVAC-Rough 6/28/2019 Approved JOHN COLEMAN
Insulation 7/8/2019 Approved JOHN COLEMAN
Drywall Nailing 7/15/2019 Approved JOHN COLEMAN
Shower Pan 7/15/2019 Approved JOHN COLEMAN
BUILDING-Rough-Frame 11/29/2019 Approved MATTHEW NUCKOLLS
Final 11/29/2019 Corrections Issued MATTHEW NUCKOLLS
Green Building Final 11/29/2019 Approved MATTHEW NUCKOLLS
SGSOV-Seismic Gas S/O Valve 11/29/2019 SGSOV Approved MATTHEW NUCKOLLS
Service/Power Release 11/29/2019 Not Ready for Inspection MATTHEW NUCKOLLS
Smoke Detectors 11/29/2019 Approved MATTHEW NUCKOLLS
Final 12/4/2019 Corrections Issued PETER FOLLING
Service/Power Release 12/4/2019 Not Ready for Inspection PETER FOLLING
Final 12/10/2019 Partial Inspection HENRY KIM
Service/Power Release 12/10/2019 Partial Inspection HENRY KIM
Final 12/12/2019 OK to Issue CofO HENRY KIM
Service/Power Release 12/12/2019 Approved HENRY KIM