14308 W GREENLEAF ST 91423
Certificate Information: 14308 W GREENLEAF ST 91423
- Application / Permit
- 18010-20000-03828
- Plan Check / Job No.
- B18VN13119
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- (N) 1-STORY ACCESSORY LIVING QUARTERS (NFPA-13D FIRE SRINKLERS THROUGHTOUT)
- Permit Issued
- Issued on 8/12/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2018 | APPLICANT |
| Green Plans Picked Up | 8/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2018 | DANNY MORALES |
| Corrections Issued | 9/1/2018 | DANNY MORALES |
| Quality Review Completed | 9/5/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 9/6/2018 | APPLICANT |
| Applicant returned to address corrections | 7/17/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/6/2019 | NILOOFAR MEHRAIN |
| Issued | 8/12/2019 | LADBS |
| CofO in Progress | 11/30/2021 | MISAEL ESPARZA |
| Permit Finaled | 12/13/2021 | MICHAEL SMITH |
| CofO Issued | 12/13/2021 | MICHAEL SMITH |
| Permit Finaled | 12/13/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 1/3/2019 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 1/4/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/14/2019 | CELINA MORENO |
| Construction near power lines | Cleared | 5/30/2019 | OSCAR CASTRO |
| Green Code | Cleared | 6/7/2019 | MICHAEL AYERS |
| Grading Pre-Inspection | Cleared | 7/17/2019 | DANNY MORALES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Wang, Hongyu; Lic. No.: C72679 | 10530 HOPE MILLS DR LAS VEGAS, NV 89135 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/20/2020 | Approved | MARK JOHNSON |
| Footing/Foundation/Slab | 4/23/2020 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2020 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 9/23/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/4/2020 | Approved | CHARLES POWELL |
| HVAC-Rough | 11/4/2020 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 11/4/2020 | Approved | CHARLES POWELL |
| Insulation | 11/30/2020 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/30/2020 | Conditional Approval | MISAEL ESPARZA |
| Drywall Nailing | 12/14/2020 | Not Ready for Inspection | CHARLES POWELL |
| Drywall Nailing | 12/18/2020 | Approved | CHARLES POWELL |
| Shower Pan | 12/18/2020 | Approved | CHARLES POWELL |
| ELECTRICAL-Final | 8/27/2021 | Partial Approval | CHARLES POWELL |
| Special/Order Compliance | 8/27/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 9/29/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 9/29/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 9/29/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 9/29/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/2/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/2/2021 | Corrections Issued | MISAEL ESPARZA |
| Final | 11/2/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 11/2/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 11/2/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 11/2/2021 | Conditional Approval | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 11/2/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 11/2/2021 | Corrections Issued | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 11/2/2021 | Approved | MISAEL ESPARZA |
| Final | 11/30/2021 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 11/30/2021 | Approved | MISAEL ESPARZA |
| Service/Power Release | 11/30/2021 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 11/30/2021 | Approved | MISAEL ESPARZA |