818 N SYCAMORE AVE 90038

Certificate Information: 818 N SYCAMORE AVE 90038

Application / Permit
18010-20000-03767
Plan Check / Job No.
B18VN12871
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 38' X 16' DETACHED 1ST FLOOR RECREATION ROOM AND STORAGE ROOM WITH 38' X 16' 2ND FLOOR ACCESSORY DWELLING UNIT AS PER AB 494 AND SB 229. FIRE SPRINKLERS REQUIRED NFPA-13D.. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/28/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2018 APPLICANT
Green Plans Picked Up 8/9/2018 APPLICANT
Assigned to Plan Check Engineer 8/23/2018 RARES BODEA
Corrections Issued 8/25/2018 RARES BODEA
Quality Review Completed 8/28/2018 OMID HEDAYAT
Building Plans Picked Up 8/29/2018 APPLICANT
Applicant returned to address corrections 11/2/2018 RARES BODEA
Applicant returned to address corrections 12/11/2018 RARES BODEA
Plan Check Approved 1/30/2019 RARES BODEA
Issued 6/28/2019 LADBS
CofO in Progress 3/8/2021 BRIAN SULLIVAN
Permit Finaled 3/20/2021 DEROLD HAUFF
CofO Issued 3/20/2021 DEROLD HAUFF
Permit Finaled 3/20/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/5/2018 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 9/5/2018 MARKOS PEREZ-BRAN
Sewer availability Cleared 9/5/2018 MARKOS PEREZ-BRAN
Low Impact Development Cleared 10/16/2018 ANDRES COVARRUBIAS
Green Code Cleared 11/9/2018 MICHAEL AYERS
Roof/Waste drainage to street Cleared 11/13/2018 LEE GUILBEAUX
Construction near power lines Cleared 1/12/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Kaligi,, Sean; Lic. No.: M37797 26905 ROLLING HILLS AVE      SANTA CLARITA, CA 91387
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/2/2019 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 7/5/2019 Approved RONALD COWAN
Footing/Foundation/Slab 7/25/2019 Approved BRIAN SULLIVAN
METHANE-Barrier 7/25/2019 Approved BRIAN SULLIVAN
METHANE-Subgrade 7/25/2019 Approved BRIAN SULLIVAN
Underground Mechanical 8/19/2019 Not Ready for Inspection ROBERT CORNELL
PLUMBING-Rough 8/20/2019 Corrections Issued ROBERT CORNELL
Underground Mechanical 8/22/2019 Partial Inspection ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 8/23/2019 Partial Inspection ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 9/11/2019 Not Ready for Inspection ROBERT CORNELL
ELECTRICAL-Rough 9/24/2019 Corrections Issued ROBERT CORNELL
HVAC-Rough 9/24/2019 Corrections Issued ROBERT CORNELL
Insulation 9/24/2019 Corrections Issued ROBERT CORNELL
PLUMBING-Rough 9/24/2019 Approved ROBERT CORNELL
Underground Mechanical 9/24/2019 Approved ROBERT CORNELL
Insulation 10/9/2019 Approved ROBERT CORNELL
Drywall Nailing 10/11/2019 Corrections Issued ROBERT CORNELL
Green Building Rough 10/11/2019 Corrections Issued ROBERT CORNELL
Interior/Exterior Lathing 10/11/2019 Corrections Issued ROBERT CORNELL
Interior/Exterior Lathing 10/17/2019 Not Ready for Inspection HENRY KIM
Shower Pan 10/17/2019 Corrections Issued HENRY KIM
Interior/Exterior Lathing 10/22/2019 Approved ROBERT CORNELL
Shower Pan 10/22/2019 Approved ROBERT CORNELL
Interior/Exterior Lathing 1/8/2020 Approved ROBERT CORNELL
ELECTRICAL-Final 10/2/2020 Corrections Issued BRIAN SULLIVAN
HVAC-Final 10/2/2020 Corrections Issued BRIAN SULLIVAN
PLUMBING-Final 10/2/2020 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Final 12/11/2020 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 12/11/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 12/11/2020 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 12/21/2020 Approved BRIAN SULLIVAN
Drywall Nailing 12/21/2020 Approved BRIAN SULLIVAN
ELECTRICAL-Final 12/21/2020 Not Ready for Inspection BRIAN SULLIVAN
Final 12/21/2020 Corrections Issued BRIAN SULLIVAN
Green Building Final 12/21/2020 Approved BRIAN SULLIVAN
Green Building Rough 12/21/2020 Approved BRIAN SULLIVAN
HVAC-Final 12/21/2020 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Final 12/21/2020 Approved BRIAN SULLIVAN
METHANE-Rough 12/21/2020 Approved BRIAN SULLIVAN
PLUMBING-Final 12/21/2020 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 12/21/2020 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 12/21/2020 Not Ready for Inspection BRIAN SULLIVAN
Smoke Detectors 12/21/2020 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 12/21/2020 Approved BRIAN SULLIVAN
Final 3/8/2021 OK to Issue CofO BRIAN SULLIVAN
HVAC-Final 3/8/2021 Approved BRIAN SULLIVAN
PLUMBING-Final 3/8/2021 Approved BRIAN SULLIVAN
Service/Power Release 3/8/2021 Approved BRIAN SULLIVAN
Smoke Detectors 3/8/2021 Approved BRIAN SULLIVAN