159 W VERNON AVE 90037

Certificate Information: 159 W VERNON AVE 90037

Application / Permit
18010-20000-03709
Plan Check / Job No.
B18VN12574
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DET. ADU PER AB 494 AND SB 229. ALL WORK PER WFPP SHEET.
Permit Issued
Issued on 12/20/2018
Issuing Office
Valley
Current Status
Issued on 12/20/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/24/2018 APPLICANT
Green Plans Picked Up 8/14/2018 APPLICANT
Assigned to Plan Check Engineer 8/23/2018 RODNEY SAMIIAN
Corrections Issued 8/27/2018 RODNEY SAMIIAN
Quality Review Completed 8/28/2018 ABDUL CHEGENI
Applicant returned to address corrections 10/22/2018 RODNEY SAMIIAN
Applicant returned to address corrections 12/19/2018 RODNEY SAMIIAN
Plan Check Approved 12/20/2018 RODNEY SAMIIAN
Issued 12/20/2018 LADBS

Permit Application Clearance Information

Green Code Cleared 10/3/2018 DAVID MATSON
Address approval Cleared 10/26/2018 KAYLA PEJI
Eng Process Fee Ord 176,300 Cleared 10/26/2018 KAYLA PEJI
Highway dedication Cleared 10/30/2018 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 10/30/2018 GEORGE SUCHAND
Sewer availability Cleared 10/30/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 11/29/2018 ANDRES COVARRUBIAS
Frnt yard landscape/Water mgmt Cleared 12/7/2018 EDBER MACEDO
Project located in CRA area Cleared 12/7/2018 JIM URQUHART
Roof/Waste drainage to street Cleared 12/7/2018 JEANETTE VONG
CPC Cleared 12/19/2018 LATANYA ROUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/16/2019 No Access for Inspection COREY HUPP
Footing/Foundation/Slab 5/3/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 5/6/2019 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/13/2019 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 5/14/2019 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/17/2019 Approved VICTOR PUKHALSKY
PLUMBING-Rough 11/1/2023 Partial Approval MICHAEL LEWIS
Wood Frame 11/1/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 11/17/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Partial Approval BRENDAN MORELLI
Insulation 11/27/2023 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 1/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/29/2024 No Access for Inspection BRENDAN MORELLI
HVAC-Rough 3/29/2024 No Access for Inspection BRENDAN MORELLI
Interior/Exterior Lathing 3/29/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 3/29/2024 No Access for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 4/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 4/3/2024 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 4/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/2/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 8/2/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/2/2024 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 8/2/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/7/2024 No Access for Inspection JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 No Access for Inspection JOHN QUINTANILLA
Gas Test 10/7/2024 No Access for Inspection JOHN QUINTANILLA
PLUMBING-Rough 10/7/2024 No Access for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 10/11/2024 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Approved JOAQUIN GREENOUGH
Gas Test 10/11/2024 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 10/11/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 10/11/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 12/30/2024 Corrections Issued SABAS ALONSO
HVAC-Rough 10/15/2025 Partial Approval JOSH MEISTER
PLUMBING-Rough 10/15/2025 Approved JOSH MEISTER
Wood Frame 10/15/2025 Conditional Approval JOSH MEISTER
BUILDING-Rough-Frame 10/23/2025 Approved ALEX COLIN
Green Building Rough 10/23/2025 Approved ALEX COLIN
Insulation 10/23/2025 Approved ALEX COLIN
Interior/Exterior Lathing 10/23/2025 Partial Approval ALEX COLIN
Drywall Nailing 12/29/2025 Approved ALEJANDRO DE ARTOLA