4311 E MONT EAGLE PL 90041
Certificate Information: 4311 E MONT EAGLE PL 90041
- Application / Permit
- 18010-20000-03706
- Plan Check / Job No.
- B18VN12558
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 32' X 70' 2-STORY IRREGULAR-SHAPE SINGLE FAMILY DWELLING WITH ATTACHED 21' 9" X 19' 10" IRREGULAR-SHAPED 2-CAR GARAGE. ALL WORK DONE PER STRUCTURAL ENGINEERING. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED.
- Permit Issued
- Issued on 7/3/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2018 | MENA WASSEF |
| Corrections Issued | 8/27/2018 | MENA WASSEF |
| Quality Review Completed | 8/29/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 8/31/2018 | APPLICANT |
| Green Plans Picked Up | 8/31/2018 | APPLICANT |
| Plan Check Approved | 6/26/2019 | GURUNATH NESARAJAH |
| Issued | 7/3/2019 | LADBS |
| CofO in Progress | 2/5/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
| CofO Issued | 2/6/2021 | DEROLD HAUFF |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/20/2018 | ROBERT DUFF |
| Address approval | Cleared | 10/10/2018 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/10/2018 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/10/2018 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/10/2018 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/10/2018 | LEE GUILBEAUX |
| Distance to fire station | Cleared | 10/22/2018 | JOHN DALLAS |
| Low Impact Development | Cleared | 4/10/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/10/2019 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 4/10/2019 | ADRIAN SANCHEZ |
| Permit | Cleared | 6/11/2019 | CELINA MORENO |
| Green Code | Cleared | 6/18/2019 | DAVID MATSON |
| GPI Written Notices | Cleared | 6/26/2019 | MENA WASSEF |
| Grading Pre-Inspection | Cleared | 6/26/2019 | MENA WASSEF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/10/2019 | Approved | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 8/26/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/26/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/29/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/6/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/3/2019 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/16/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 10/18/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 10/23/2019 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 11/19/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 12/11/2019 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Steel/Welding | 1/10/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/10/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/16/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Special/Order Compliance | 1/16/2020 | Partial Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 2/5/2020 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/27/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 3/27/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 3/27/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/16/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/16/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/17/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/29/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/29/2020 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/29/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 5/11/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/11/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/22/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 5/27/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/27/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/4/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/11/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/18/2020 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/7/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/29/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Sewer | 8/3/2020 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/13/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Masonry Wall/Backfill | 10/16/2020 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/9/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 12/9/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/9/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 12/9/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 12/9/2020 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2020 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 12/9/2020 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/9/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 12/9/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 1/5/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/5/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 2/3/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/3/2021 | Approved | HAMIK HARTOUNIAN |