4311 E MONT EAGLE PL 90041

Certificate Information: 4311 E MONT EAGLE PL 90041

Application / Permit
18010-20000-03706
Plan Check / Job No.
B18VN12558
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 32' X 70' 2-STORY IRREGULAR-SHAPE SINGLE FAMILY DWELLING WITH ATTACHED 21' 9" X 19' 10" IRREGULAR-SHAPED 2-CAR GARAGE. ALL WORK DONE PER STRUCTURAL ENGINEERING. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED.
Permit Issued
Issued on 7/3/2019
Issuing Office
Valley
Current Status
CofO Issued on 2/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2018 APPLICANT
Assigned to Plan Check Engineer 8/23/2018 MENA WASSEF
Corrections Issued 8/27/2018 MENA WASSEF
Quality Review Completed 8/29/2018 CHON CHIO KUO
Building Plans Picked Up 8/31/2018 APPLICANT
Green Plans Picked Up 8/31/2018 APPLICANT
Plan Check Approved 6/26/2019 GURUNATH NESARAJAH
Issued 7/3/2019 LADBS
CofO in Progress 2/5/2021 HAMIK HARTOUNIAN
Permit Finaled 2/6/2021 DEROLD HAUFF
CofO Issued 2/6/2021 DEROLD HAUFF
Permit Finaled 2/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/20/2018 ROBERT DUFF
Address approval Cleared 10/10/2018 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 10/10/2018 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 10/10/2018 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 10/10/2018 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/10/2018 LEE GUILBEAUX
Sewer availability Cleared 10/10/2018 LEE GUILBEAUX
Distance to fire station Cleared 10/22/2018 JOHN DALLAS
Low Impact Development Cleared 4/10/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/10/2019 ADRIAN SANCHEZ
Trees in Parkway Cleared 4/10/2019 ADRIAN SANCHEZ
Permit Cleared 6/11/2019 CELINA MORENO
Green Code Cleared 6/18/2019 DAVID MATSON
GPI Written Notices Cleared 6/26/2019 MENA WASSEF
Grading Pre-Inspection Cleared 6/26/2019 MENA WASSEF

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/10/2019 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/26/2019 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/26/2019 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/29/2019 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/6/2019 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/3/2019 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/16/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 10/18/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 10/23/2019 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 11/19/2019 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/6/2019 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 12/11/2019 Corrections Issued HAMIK HARTOUNIAN
Deputy Steel/Welding 1/10/2020 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 1/10/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 1/16/2020 Partial Approval HAMIK HARTOUNIAN
Special/Order Compliance 1/16/2020 Partial Inspection RUBEN SALAS
Footing/Foundation/Slab 2/5/2020 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 3/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 3/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 4/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 4/17/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/29/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 4/29/2020 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 4/29/2020 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 5/11/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 5/11/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/22/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Insulation 5/27/2020 Approved CHRISTOPHER DELLEFIELD
Shower Pan 5/27/2020 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 6/4/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/11/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/18/2020 Approved HAMIK HARTOUNIAN
Pre-Inspection 7/7/2020 Partial Inspection HAMIK HARTOUNIAN
Pre-Inspection 7/29/2020 Partial Inspection HAMIK HARTOUNIAN
Sewer 8/3/2020 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 10/13/2020 Partial Approval HAMIK HARTOUNIAN
Masonry Wall/Backfill 10/16/2020 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/9/2020 Approved HAMIK HARTOUNIAN
Final 12/9/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/9/2020 Approved HAMIK HARTOUNIAN
Green Building Final 12/9/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 12/9/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/9/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 12/9/2020 Approved HAMIK HARTOUNIAN
Smoke Detectors 12/9/2020 Corrections Issued HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 12/9/2020 Approved HAMIK HARTOUNIAN
Final 1/5/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/5/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 1/5/2021 Partial Approval HAMIK HARTOUNIAN
Final 2/3/2021 OK to Issue CofO HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/3/2021 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 2/3/2021 Approved HAMIK HARTOUNIAN