20430 W BIRMINGHAM WAY 91326

Certificate Information: 20430 W BIRMINGHAM WAY 91326

Application / Permit
18010-20000-03700
Plan Check / Job No.
B18VN12523
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
TWO STORY SFD WITH ATTACH 3 CAR GARAGE_STANDARD PLAN # 648 PLAN 4X
Permit Issued
Issued on 10/30/2018
Issuing Office
Valley
Current Status
CofO Issued on 6/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2018 APPLICANT
Green Plans Picked Up 8/9/2018 APPLICANT
Assigned to Plan Check Engineer 8/23/2018 DAWN MC NULTY
Corrections Issued 8/27/2018 DAWN MC NULTY
Quality Review Completed 8/27/2018 CHON CHIO KUO
Building Plans Picked Up 8/31/2018 APPLICANT
Plan Check Approved 10/30/2018 DAWN MC NULTY
Issued 10/30/2018 LADBS
CofO in Progress 6/25/2020 SEAN WIRCH
Permit Finaled 6/25/2020 DONALD SUNSERI
CofO Issued 6/25/2020 DONALD SUNSERI
Permit Finaled 6/25/2020 DONALD SUNSERI

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/20/2018 ROBERT DUFF
Address approval Cleared 9/25/2018 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 9/25/2018 AMMAR ELTAWIL
Permit Cleared 9/25/2018 APEKSHYA BAJRACHARYA
Sewer availability Cleared 9/25/2018 APEKSHYA BAJRACHARYA
"T" removal Cleared 9/28/2018 STEVEN WECHSLER
CPC Cleared 9/28/2018 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 9/28/2018 RUDY TERRIQUEZ.
Miscellaneous Cleared 9/28/2018 STEVEN WECHSLER
Miscellaneous Cleared 9/28/2018 STEVEN WECHSLER
Miscellaneous Cleared 9/28/2018 STEVEN WECHSLER
Miscellaneous Cleared 9/28/2018 STEVEN WECHSLER
Miscellaneous Cleared 9/28/2018 STEVEN WECHSLER
Specific Plan Cleared 9/28/2018 STEVEN WECHSLER
Tract Map conditions Cleared 9/28/2018 STEVEN WECHSLER
ZA Case Cleared 9/28/2018 STEVEN WECHSLER
ZA Case Cleared 9/28/2018 STEVEN WECHSLER
Roof/Waste drainage to street Cleared 10/3/2018 APEKSHYA BAJRACHARYA
Green Code Cleared 10/30/2018 MICHAEL AYERS

Contact Information

Architect Gorrill, Ernest Bernard; Lic. No.: C13407 419 E BAY ST      COSTA MESA, CA 92627
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 250 GIBRALTAR RD   ATTN: GATES/LEGAL    HORSHAM, PA 19044
Engineer Kim, Kevin Chae; Lic. No.: C53821 2349 N CAMPUS AVENUE      UPLAND, CA 91784
Engineer Miller, Karen Lynn; Lic. No.: GE2257 5364 DORIS WY      TORRANCE, CA 90505
Engineer Wong, Ramon Roman Ii; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/11/2019 Approved BRUCE ROZAK
Footing/Foundation/Slab 2/27/2019 Approved BRUCE ROZAK
Deputy Pre-Stress Concrete 3/1/2019 Conditional Approval RYAN MCGILL
Floor/Roof Diaphrgm/Shear Wall 3/29/2019 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 4/15/2019 Partial Approval BRUCE ROZAK
Underground Mechanical 5/7/2019 Not Ready for Inspection BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 5/10/2019 Not Ready for Inspection BRUCE ROZAK
Sewer 5/10/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 5/14/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 6/10/2019 Approved BRUCE ROZAK
BUILDING-Rough-Frame 6/27/2019 Not Ready for Inspection BRUCE ROZAK
ELECTRICAL-Rough 6/27/2019 Approved BRUCE ROZAK
Green Building Rough 6/27/2019 Approved BRUCE ROZAK
HVAC-Rough 6/27/2019 Not Ready for Inspection BRUCE ROZAK
PLUMBING-Rough 6/27/2019 Approved BRUCE ROZAK
Verify Sprinkler Sign Off 6/27/2019 Approved BRUCE ROZAK
BUILDING-Rough-Frame 7/1/2019 Approved BRUCE ROZAK
HVAC-Rough 7/1/2019 Approved BRUCE ROZAK
Drywall Nailing 7/12/2019 Approved BRUCE ROZAK
Interior/Exterior Lathing 7/12/2019 Partial Approval BRUCE ROZAK
Interior/Exterior Lathing 7/18/2019 Approved BRUCE ROZAK
Underground Mechanical 8/21/2019 Approved BRUCE ROZAK
Service/Power Release 8/29/2019 Approved BRUCE ROZAK
Gas Test 9/5/2019 Approved DONALD SUNSERI
SGSOV-Seismic Gas S/O Valve 10/4/2019 SGSOV Approved BRUCE ROZAK
SWPPP-Const. Storm Water 12/4/2019 Completed BRUCE ROZAK
ELECTRICAL-Final 6/8/2020 Approved SEAN WIRCH
HVAC-Final 6/8/2020 Approved SEAN WIRCH
PLUMBING-Final 6/8/2020 Approved SEAN WIRCH
Final 6/23/2020 Corrections Issued SEAN WIRCH
Green Building Final 6/23/2020 Approved SEAN WIRCH
Smoke Detectors 6/23/2020 Approved SEAN WIRCH
Final 6/26/2020 OK to Issue CofO SEAN WIRCH