11956 W FOXBORO DR 90049
Certificate Information: 11956 W FOXBORO DR 90049
- Application / Permit
- 18010-20000-03649
- Plan Check / Job No.
- B18VN12338
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY, 59'-0" X 46'-0" SINGLE FAMILY DWELLING W/ ATTACHED 2-CAR GARAGE AND HABITABLE BASEMENT; FIRE SPRINKLERS REQ'D THROUGH-OUT.
- Permit Issued
- Issued on 4/23/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2018 | APPLICANT |
| Green Plans Picked Up | 8/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2018 | DANNY MORALES |
| Corrections Issued | 8/25/2018 | DANNY MORALES |
| Quality Review Completed | 8/30/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 9/4/2018 | APPLICANT |
| Applicant returned to address corrections | 11/30/2018 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 12/10/2018 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 1/17/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 1/29/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 2/11/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/14/2019 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/19/2019 | ALEXANDER SBARDELLATI |
| Plan Check Approved | 4/1/2019 | ALEXANDER SBARDELLATI |
| Issued | 4/23/2019 | LADBS |
| CofO in Progress | 3/12/2021 | JOHN KIDWELL |
| Permit Finaled | 3/18/2021 | VINCENT COTTON |
| CofO Issued | 3/18/2021 | VINCENT COTTON |
| Permit Finaled | 3/18/2021 | VINCENT COTTON |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 12/10/2018 | DANNY MORALES |
| Grading Pre-Inspection | Cleared | 12/10/2018 | DANNY MORALES |
| Green Code | Cleared | 2/11/2019 | DAVID MATSON |
| Address approval | Cleared | 2/20/2019 | JOSE CRUZ RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2019 | JOSE CRUZ RODRIGUEZ |
| Excavation more than 5-ft deep | Cleared | 3/4/2019 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 3/18/2019 | ROBERT DUFF |
| Low Impact Development | Cleared | 3/18/2019 | MITESH PATEL |
| Permit | Cleared | 3/18/2019 | ELAINE LEI |
| Sewer availability | Cleared | 3/18/2019 | ELAINE LEI |
| Trees in Parkway | Cleared | 3/18/2019 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 4/1/2019 | LEE GUILBEAUX |
Contact Information
| Contractor | Free Creation Inc; Lic. No.: 1003352-B | 8019 SALE AVENUE CANOGA PARK, CA 91304 |
| Engineer | De, Leon Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/15/2019 | Partial Inspection | RICHARD STEINBACH |
| Underground Mechanical | 6/7/2019 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 7/22/2019 | Conditional Approval | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 7/26/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 8/15/2019 | Partial Approval | DANNY TOLENTINO |
| Deputy Shotcrete | 8/26/2019 | Conditional Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 9/4/2019 | Corrections Issued | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 9/5/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 9/18/2019 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2019 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2019 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2020 | Corrections Issued | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2020 | Conditional Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 2/6/2020 | Corrections Issued | DANNY TOLENTINO |
| PLUMBING-Rough | 2/13/2020 | Corrections Issued | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2020 | Corrections Issued | DANNY TOLENTINO |
| Sewer | 3/4/2020 | Partial Approval | DANNY TOLENTINO |
| ELECTRICAL-Rough | 3/16/2020 | Corrections Issued | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2020 | Partial Approval | DANNY TOLENTINO |
| HVAC-Rough | 3/16/2020 | Approved | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 3/31/2020 | Partial Approval | DANNY TOLENTINO |
| ELECTRICAL-Rough | 3/31/2020 | Approved | DANNY TOLENTINO |
| Green Building Rough | 3/31/2020 | Approved | DANNY TOLENTINO |
| Interior/Exterior Lathing | 3/31/2020 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 3/31/2020 | Approved | DANNY TOLENTINO |
| Shower Pan | 3/31/2020 | Approved | DANNY TOLENTINO |
| Verify Sprinkler Sign Off | 3/31/2020 | Approved | DANNY TOLENTINO |
| Insulation | 4/7/2020 | Approved | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 4/7/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 4/10/2020 | Partial Approval | DANNY TOLENTINO |
| Drywall Nailing | 4/20/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 4/22/2020 | Approved | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/22/2020 | Approved | DANNY TOLENTINO |
| ELECTRICAL-Final | 11/9/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Gas Test | 11/9/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Gas Test | 11/20/2020 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 12/4/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 12/11/2020 | Approved | JOHN KIDWELL |
| HVAC-Final | 2/10/2021 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 2/10/2021 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 3/12/2021 | Approved | JOHN KIDWELL |
| Final | 3/12/2021 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 3/12/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 3/12/2021 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/12/2021 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 3/12/2021 | Approved | JOHN KIDWELL |
| Smoke Detectors | 3/12/2021 | Approved | JOHN KIDWELL |