453 N STANLEY AVE 1-4 90036

Certificate Information: 453 N STANLEY AVE 1-4 90036

Application / Permit
18010-20000-03540
Plan Check / Job No.
B18VN11858
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 36'-0'' x 97'-0'' Four-Story Fully Sprinklered (NFPA 13) 4-Unit Apartment Building (Type VA Construction) with attached Garage (Type IA Construction) on Grade level.
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
CofO Issued on 12/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2018 APPLICANT
Disabled Access Plans Picked Up 8/21/2018 APPLICANT
Green Plans Picked Up 8/21/2018 APPLICANT
Assigned to Plan Check Engineer 8/23/2018 DANNY MORALES
Corrections Issued 9/7/2018 DANNY MORALES
Quality Review Completed 9/17/2018 OMID HEDAYAT
Building Plans Picked Up 9/20/2018 APPLICANT
Applicant returned to address corrections 6/10/2019 OMID HEDAYAT
Applicant returned to address corrections 7/16/2019 OMID HEDAYAT
Applicant returned to address corrections 8/28/2019 OMID HEDAYAT
Plan Check Approved 8/28/2019 OMID HEDAYAT
Plan Check Approved 4/8/2021 OMID HEDAYAT
Issued 4/29/2021 APPLICANT
CofO in Progress 12/19/2024 EDWIN GREGORYONA
Permit Finaled 12/23/2024 ERNESTO CORRAL
CofO Issued 12/23/2024 ERNESTO CORRAL
Permit Finaled 12/23/2024 ERNESTO CORRAL

Permit Application Clearance Information

Historic monument Cleared 1/24/2019 MELISSA JONES
Address approval Cleared 2/13/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/13/2019 JEANETTE VONG
Highway dedication Cleared 2/13/2019 JEANETTE VONG
Permit Cleared 2/13/2019 JEANETTE VONG
Sewer availability Cleared 2/13/2019 JEANETTE VONG
Green Code Cleared 5/24/2019 MICHAEL AYERS
DAS Clearance Cleared 5/28/2019 OLLIE CARTER
Frnt yard landscape/Water mgmt Cleared 7/26/2019 HERMINIGILDO AGUSTIN
Hydrant and Access approval Cleared 7/26/2019 JEREMY CARTER
Low Impact Development Cleared 7/26/2019 SARAH YOUSSEF
Miscellaneous Cleared 7/26/2019 HERMINIGILDO AGUSTIN
Roof/Waste drainage to street Cleared 7/26/2019 CELINA MORENO
Fire Marshall Fire Life Safety Cleared 8/19/2019 WILLIAM JOHNS
Building over 3-story or 36-ft Cleared 8/28/2019 CALOSHA APPROVED

Contact Information

Architect Brumer,, Aaron Jason; Lic. No.: C30005 10999 RIVERSIDE DRIVE SUITE 300      STUDIO CITY, CA 91602
Contractor Owner-Builder       ,
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 8/18/2021 Approved EDWIN GREGORYONA
Special/Order Compliance 8/31/2021 Approved EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/20/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 4/21/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 4/21/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 4/21/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 5/13/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 5/13/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 5/13/2022 Not Ready for Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 5/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 5/19/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/20/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 5/20/2022 Approved EDWIN GREGORYONA
Masonry Wall/Backfill 5/20/2022 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 5/20/2022 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 5/20/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/20/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Methane Barrier 6/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/2/2022 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 6/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 7/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 7/5/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/14/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/14/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 7/14/2022 Approved EDWIN GREGORYONA
METHANE-Subgrade 7/14/2022 Approved EDWIN GREGORYONA
Deputy Steel/Welding 10/14/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/22/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 11/1/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 11/21/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/21/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/26/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/27/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 3/15/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Partial Approval EDWIN GREGORYONA
Pre-Inspection 4/27/2023 Partial Approval LARRY ARNICK
Drywall Nailing 5/5/2023 Partial Approval JEROME BLACKWOOD
Green Building Rough 5/5/2023 Approved JEROME BLACKWOOD
Drywall Nailing 5/19/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 5/23/2023 Partial Approval EDWIN GREGORYONA
Insulation 5/25/2023 Partial Inspection EDWIN GREGORYONA
Insulation 6/13/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 8/1/2023 Not Ready for Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 8/4/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 8/11/2023 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 8/16/2023 Partial Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Not Ready EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 8/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 9/26/2023 Partial Approval EDWIN GREGORYONA
Wood Frame 10/6/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 10/24/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 11/1/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 11/1/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 11/21/2023 Approved EDWIN GREGORYONA
Wood Frame 11/21/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/6/2023 Partial Approval EDWIN GREGORYONA
Wood Frame 12/6/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/27/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 2/1/2024 Approved EDWIN GREGORYONA
Special/Order Compliance 5/8/2024 Approved EDWIN GREGORYONA
Footing/Foundation/Slab 5/28/2024 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 6/7/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 6/17/2024 Approved EDWIN GREGORYONA
Pre-Inspection 8/1/2024 Approved EDWIN GREGORYONA
Pre-Inspection 12/5/2024 Approved EDWIN GREGORYONA
Drywall Nailing 12/19/2024 Approved EDWIN GREGORYONA
Final 12/19/2024 OK to Issue CofO EDWIN GREGORYONA
Footing/Foundation/Slab 12/19/2024 Approved EDWIN GREGORYONA
Green Building Final 12/19/2024 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 12/19/2024 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 12/19/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 12/19/2024 Approved EDWIN GREGORYONA
Structural Steel Frame 12/19/2024 Approved EDWIN GREGORYONA
Wood Frame 12/19/2024 Approved EDWIN GREGORYONA