943 N AVENUE 66 90042
Certificate Information: 943 N AVENUE 66 90042
- Application / Permit
- 18010-20000-03526
- Plan Check / Job No.
- B18VN11823
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 38' x 47' THREE-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 12/4/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2018 | DANNY MORALES |
| Corrections Issued | 8/23/2018 | DANNY MORALES |
| Quality Review Completed | 8/27/2018 | OMID HEDAYAT |
| Building Plans Picked Up | 8/28/2018 | APPLICANT |
| Green Plans Picked Up | 9/11/2018 | APPLICANT |
| Applicant returned to address corrections | 1/30/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 5/30/2023 | SEAN SHAHMIRI |
| Issued | 12/4/2023 | APPLICANT |
| CofO in Progress | 9/15/2025 | DAVID WILLIAMS |
| No Progress | 9/17/2025 | CHARLES BOGHOSKHAN |
| CofO in Progress | 9/17/2025 | CHARLES BOGHOSKHAN |
| Permit Finaled | 9/30/2025 | DEROLD HAUFF |
| Permit Finaled | 9/30/2025 | DEROLD HAUFF |
| CofO Issued | 9/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2018 | LEE GUILBEAUX |
| Address approval | Cleared | 9/19/2018 | ADOLFO GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 9/19/2018 | ADOLFO GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 9/19/2018 | ADOLFO GUTIERREZ |
| Distance to fire station | Cleared | 9/19/2018 | ROBERT DUFF |
| Hydrant and Access approval | Cleared | 9/19/2018 | ROBERT DUFF |
| Sewer availability | Cleared | 9/19/2018 | ADOLFO GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 9/24/2018 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 10/4/2018 | ANNA VIDAL |
| Miscellaneous | Cleared | 10/4/2018 | ANNA VIDAL |
| Miscellaneous | Cleared | 5/7/2019 | SHEILA GERSHON |
| Private street | Cleared | 5/7/2019 | SHEILA GERSHON |
| Low Impact Development | Cleared | 11/18/2022 | CHRIS VONG |
| GPI Written Notices | Cleared | 1/30/2023 | DANNY MORALES |
| Grading Pre-Inspection | Cleared | 1/30/2023 | DANNY MORALES |
| Green Code | Cleared | 1/30/2023 | DANNY MORALES |
| Roof/Waste drainage to street | Cleared | 4/1/2023 | CINDY QI |
| Trees in Parkway | Cleared | 4/17/2023 | ADALBERTO VERA |
| Disturb/Remove Protected Trees | Cleared | 4/29/2023 | ADALBERTO VERA |
Contact Information
| Architect | Knitter, M J; Lic. No.: C10524 | 1401 DOVE STREET SUITE 240 NEWPORT BEACH, CA 92660 |
| Contractor | S K L Construction; Lic. No.: 958490-B | PO BOX 9559 RANCHO CUCAMONGA, CA 91701 |
| Engineer | Nguyen, Huan Ngoc; Lic. No.: C64238 | 7015 PINNACLE POINTE ORANGE, CA 92869 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/24/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 5/15/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 5/15/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Protected Tree Letter | 5/15/2024 | Partial Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 5/20/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 5/20/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Protected Tree Letter | 5/20/2024 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 6/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 6/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 6/20/2024 | Partial Approval | JOAQUIN GREENOUGH |
| Masonry Wall/Backfill | 6/20/2024 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 6/24/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Reinforced Masonry Frame | 6/24/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Reinf. Concrete | 6/25/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/29/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/6/2024 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 8/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/15/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 11/19/2024 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 11/19/2024 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 11/21/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 11/22/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 12/3/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/3/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/9/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 12/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 12/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/10/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 12/13/2024 | Approved | ROY SPAULDING |
| Shower Pan | 12/13/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Partial Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 12/30/2024 | Corrections Issued | BRENDAN MORELLI |
| Green Building Rough | 12/30/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/30/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 12/30/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/3/2025 | Approved | CRAIG DAVIS |
| Green Building Rough | 1/3/2025 | Approved | CRAIG DAVIS |
| Insulation | 1/3/2025 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 1/3/2025 | Approved | CRAIG DAVIS |
| Insulation | 1/8/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 1/16/2025 | Partial Approval | CRAIG DAVIS |
| Interior/Exterior Lathing | 1/16/2025 | Approved | CRAIG DAVIS |
| Drywall Nailing | 1/22/2025 | Approved | CRAIG DAVIS |
| Sewer | 1/27/2025 | Approved | ANTHONY RAMOS |
| Gas Test | 3/27/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 4/14/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 5/29/2025 | Approved | DAVID WILLIAMS |
| HVAC-Final | 6/6/2025 | Approved | DAVID WILLIAMS |
| Service/Power Release | 6/6/2025 | Approved | DAVID WILLIAMS |
| Final | 8/1/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 8/1/2025 | Approved | DAVID WILLIAMS |
| Reinforced Concrete Frame | 8/1/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 8/1/2025 | Approved | DAVID WILLIAMS |
| Final | 9/5/2025 | Corrections Issued | DAVID WILLIAMS |
| Final | 9/15/2025 | OK to Issue CofO | DAVID WILLIAMS |
| Special/Order Compliance | 9/17/2025 | Corrections Issued | DAVID WILLIAMS |
| Special/Order Compliance | 9/26/2025 | Approved | DAVID WILLIAMS |