951 N AVENUE 66 90042

Certificate Information: 951 N AVENUE 66 90042

Application / Permit
18010-20000-03524
Plan Check / Job No.
B18VN11823
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 38' x 47' THREE-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE; NFPA-13D THRU-OUT
Permit Issued
Issued on 12/4/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2018 APPLICANT
Assigned to Plan Check Engineer 8/16/2018 DANNY MORALES
Corrections Issued 8/23/2018 DANNY MORALES
Quality Review Completed 8/27/2018 OMID HEDAYAT
Building Plans Picked Up 8/28/2018 APPLICANT
Green Plans Picked Up 9/11/2018 APPLICANT
Applicant returned to address corrections 1/30/2023 SEAN SHAHMIRI
Plan Check Approved 5/30/2023 SEAN SHAHMIRI
Issued 12/4/2023 APPLICANT
CofO in Progress 9/15/2025 DAVID WILLIAMS
Permit Finaled 9/20/2025 DEROLD HAUFF
CofO Issued 9/20/2025 DEROLD HAUFF
Permit Finaled 9/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/28/2018 LEE GUILBEAUX
Address approval Cleared 9/19/2018 ADOLFO GUTIERREZ
BHO/Hillside ordinance Cleared 9/19/2018 ADOLFO GUTIERREZ
BHO/Hillside ordinance Cleared 9/19/2018 ADOLFO GUTIERREZ
Distance to fire station Cleared 9/19/2018 ROBERT DUFF
Hydrant and Access approval Cleared 9/19/2018 ROBERT DUFF
Sewer availability Cleared 9/19/2018 ADOLFO GUTIERREZ
BHO/Hillside ordinance Cleared 9/24/2018 LEE GUILBEAUX
Miscellaneous Cleared 10/9/2018 DAISY BENICIA
Miscellaneous Cleared 10/9/2018 DAISY BENICIA
Miscellaneous Cleared 5/7/2019 SHEILA GERSHON
Private street Cleared 5/7/2019 SHEILA GERSHON
Low Impact Development Cleared 12/13/2022 LUIS LUVANO
GPI Written Notices Cleared 1/30/2023 DANNY MORALES
Grading Pre-Inspection Cleared 1/30/2023 DANNY MORALES
Green Code Cleared 1/30/2023 DANNY MORALES
Roof/Waste drainage to street Cleared 4/5/2023 CINDY QI
Trees in Parkway Cleared 4/17/2023 ADALBERTO VERA
Disturb/Remove Protected Trees Cleared 4/29/2023 ADALBERTO VERA

Contact Information

Architect Knitter, M J; Lic. No.: C10524 1401 DOVE STREET SUITE 240      NEWPORT BEACH, CA 92660
Contractor S K L Construction; Lic. No.: 958490-B PO BOX 9559      RANCHO CUCAMONGA, CA 91701
Engineer Nguyen, Huan Ngoc; Lic. No.: C64238 7015 PINNACLE POINTE      ORANGE, CA 92869

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/24/2024 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 5/15/2024 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/15/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Protected Tree Letter 5/15/2024 Partial Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 5/20/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/20/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Protected Tree Letter 5/20/2024 Approved ALIZAH MAYAGOITIA
Special/Order Compliance 5/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 5/30/2024 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 6/7/2024 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/7/2024 Approved ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 6/20/2024 Partial Approval JOAQUIN GREENOUGH
Masonry Wall/Backfill 6/20/2024 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 6/24/2024 Partial Approval ALIZAH MAYAGOITIA
Reinforced Masonry Frame 6/24/2024 Partial Approval ALIZAH MAYAGOITIA
Deputy Reinf. Concrete 6/25/2024 Conditional Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 7/29/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/6/2024 Approved ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 8/7/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/3/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 11/15/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/19/2024 Corrections Issued LUIS CASTRO
PLUMBING-Rough 11/19/2024 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 11/21/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/22/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 12/3/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 12/3/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/9/2024 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 12/9/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 12/9/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 12/10/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 12/13/2024 Approved ROY SPAULDING
Shower Pan 12/13/2024 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Partial Inspection CRAIG DAVIS
BUILDING-Rough-Frame 12/30/2024 Corrections Issued BRENDAN MORELLI
Green Building Rough 12/30/2024 Not Ready for Inspection BRENDAN MORELLI
Interior/Exterior Lathing 12/30/2024 Not Ready for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 12/30/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 1/3/2025 Approved CRAIG DAVIS
Green Building Rough 1/3/2025 Approved CRAIG DAVIS
Insulation 1/3/2025 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 1/3/2025 Approved CRAIG DAVIS
Insulation 1/8/2025 Approved ALEX COLIN
Drywall Nailing 1/15/2025 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 1/16/2025 Approved CRAIG DAVIS
Drywall Nailing 1/22/2025 Approved CRAIG DAVIS
Interior/Exterior Lathing 1/22/2025 Approved CRAIG DAVIS
Sewer 1/27/2025 Approved ANTHONY RAMOS
Gas Test 3/27/2025 Approved DAVID WILLIAMS
PLUMBING-Final 4/14/2025 Approved DAVID WILLIAMS
ELECTRICAL-Final 5/29/2025 Approved DAVID WILLIAMS
HVAC-Final 6/6/2025 Approved DAVID WILLIAMS
Service/Power Release 6/6/2025 Approved DAVID WILLIAMS
Final 8/1/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 8/1/2025 Approved DAVID WILLIAMS
Reinforced Concrete Frame 8/1/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 8/1/2025 Approved DAVID WILLIAMS
Final 9/5/2025 Corrections Issued DAVID WILLIAMS
Final 9/15/2025 OK to Issue CofO DAVID WILLIAMS
Special/Order Compliance 9/17/2025 Approved DAVID WILLIAMS