838 N POINSETTIA PL 90046
Certificate Information: 838 N POINSETTIA PL 90046
- Application / Permit
- 18010-20000-03475
- Plan Check / Job No.
- B18VN11657
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SMALL LOT SUDDIVISION. Lot 3 Plan Type C
- Permit Issued
- Issued on 2/21/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2018 | APPLICANT |
| Green Plans Picked Up | 7/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2018 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 8/15/2018 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 8/16/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 8/21/2018 | APPLICANT |
| Plan Check Approved | 2/15/2019 | VLADIMIR ARUTYUNYAN |
| Issued | 2/21/2019 | LADBS |
| CofO in Progress | 9/1/2020 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
| CofO Issued | 9/3/2020 | DEROLD HAUFF |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 7/13/2018 | CYNTHIA RYAN |
| Hold | Cleared | 8/15/2018 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 9/27/2018 | MICHAEL CASTILLO |
| Hydrant and Access approval | Cleared | 11/15/2018 | ROBERT DUFF |
| Green Code | Cleared | 1/14/2019 | DAVID MATSON |
| Address approval | Cleared | 1/17/2019 | JEANETTE VONG |
| Miscellaneous | Cleared | 1/18/2019 | BLAYNE SUTTON-WILLS |
| Miscellaneous | Cleared | 1/18/2019 | GEORGE SUCHAND |
| "Q" conditions | Cleared | 1/22/2019 | BLAYNE SUTTON-WILLS |
| Low Impact Development | Cleared | 1/22/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/22/2019 | MICHAEL CASTILLO |
| Highway dedication | Cleared | 1/31/2019 | CELINA MORENO |
| Miscellaneous | Cleared | 1/31/2019 | HOK CHI CHIU |
Contact Information
| Architect | Maly, Farzin; Lic. No.: C33731 | PO BOX 57002 SHERMAN OAKS, CA 91413 |
| Contractor | Owner-Builder | , |
| Engineer | Nazari, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/9/2019 | Partial Approval | JOSEPH MCGARRY |
| METHANE-Barrier | 5/9/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Subgrade | 5/9/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/13/2019 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/14/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/29/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 5/29/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 5/29/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/3/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 6/3/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 6/3/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 6/4/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 6/5/2019 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 6/5/2019 | Approved | SCOTT FINNILA |
| METHANE-Barrier | 6/5/2019 | Approved | SCOTT FINNILA |
| METHANE-Subgrade | 6/5/2019 | Approved | SCOTT FINNILA |
| Drywall Nailing | 7/23/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/29/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/7/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/28/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/23/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/24/2019 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/28/2019 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/29/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/29/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/31/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/1/2019 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/18/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/18/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 11/18/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 11/18/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/20/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/20/2019 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 11/20/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 11/20/2019 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 11/21/2019 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 12/2/2019 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/6/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/9/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/12/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 12/13/2019 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/19/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/23/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/27/2019 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/10/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/14/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/2/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/3/2020 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/8/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/12/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/15/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 5/15/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/19/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/22/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 5/27/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/27/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/28/2020 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/22/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/22/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/22/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Final | 6/22/2020 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 6/22/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/22/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/22/2020 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/22/2020 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/1/2020 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/7/2020 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Final | 7/8/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/8/2020 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Final | 8/11/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |