836 1/2 N POINSETTIA PL 90046

Certificate Information: 836 1/2 N POINSETTIA PL 90046

Application / Permit
18010-20000-03474
Plan Check / Job No.
B18VN11657
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SMALL LOT SUDDIVISION. Lot 2 Plan type B
Permit Issued
Issued on 2/21/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2018 APPLICANT
Green Plans Picked Up 7/17/2018 APPLICANT
Assigned to Plan Check Engineer 8/9/2018 VLADIMIR ARUTYUNYAN
Corrections Issued 8/15/2018 VLADIMIR ARUTYUNYAN
Quality Review Completed 8/16/2018 CHON CHIO KUO
Building Plans Picked Up 8/21/2018 APPLICANT
Plan Check Approved 2/15/2019 VLADIMIR ARUTYUNYAN
Issued 2/21/2019 LADBS
CofO in Progress 8/19/2020 ALEJANDRO DE ARTOLA
Permit Finaled 9/3/2020 DEROLD HAUFF
CofO Issued 9/3/2020 DEROLD HAUFF
Permit Finaled 9/3/2020 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 7/13/2018 CYNTHIA RYAN
Hold Cleared 8/15/2018 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 9/27/2018 MICHAEL CASTILLO
Sewer availability Cleared 9/27/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 11/15/2018 ROBERT DUFF
Green Code Cleared 1/14/2019 DAVID MATSON
Address approval Cleared 1/17/2019 JEANETTE VONG
"Q" conditions Cleared 1/18/2019 BLAYNE SUTTON-WILLS
Miscellaneous Cleared 1/18/2019 BLAYNE SUTTON-WILLS
Miscellaneous Cleared 1/18/2019 GEORGE SUCHAND
Low Impact Development Cleared 1/22/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/22/2019 MICHAEL CASTILLO
Highway dedication Cleared 1/31/2019 CELINA MORENO
Miscellaneous Cleared 1/31/2019 HOK CHI CHIU

Contact Information

Architect Maly, Farzin; Lic. No.: C33731 PO BOX 57002      SHERMAN OAKS, CA 91413
Contractor Owner-Builder       ,
Engineer Nazari, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/8/2019 Not Ready for Inspection SCOTT FINNILA
METHANE-Barrier 5/8/2019 Not Ready for Inspection SCOTT FINNILA
METHANE-Subgrade 5/8/2019 Not Ready for Inspection SCOTT FINNILA
Pre-Inspection 5/8/2019 Partial Inspection SCOTT FINNILA
Underground Mechanical 5/20/2019 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/12/2019 Partial Approval ALEJANDRO DE ARTOLA
METHANE-Barrier 6/12/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
METHANE-Subgrade 6/12/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/20/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
METHANE-Barrier 6/20/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
METHANE-Subgrade 6/20/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/21/2019 Conditional Approval ALEJANDRO DE ARTOLA
Drywall Nailing 7/23/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/23/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 7/24/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/1/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 8/5/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Drywall Nailing 8/7/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/15/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/23/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 8/28/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/3/2019 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/16/2019 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/16/2019 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/17/2019 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 10/18/2019 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/18/2019 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 10/21/2019 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 10/25/2019 Conditional Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/28/2019 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/31/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/7/2019 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/12/2019 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/14/2019 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 11/14/2019 Partial Approval ALEJANDRO DE ARTOLA
METHANE-Rough 11/14/2019 Partial Approval ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 11/14/2019 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/15/2019 Conditional Approval ALEJANDRO DE ARTOLA
Green Building Rough 11/15/2019 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/21/2019 Conditional Approval ALEJANDRO DE ARTOLA
METHANE-Rough 11/21/2019 Partial Approval ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 11/21/2019 Approved ALEJANDRO DE ARTOLA
Shower Pan 12/2/2019 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/6/2019 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/9/2019 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/12/2019 Partial Approval ALEJANDRO DE ARTOLA
Insulation 12/13/2019 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 12/19/2019 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/19/2019 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 1/10/2020 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 1/13/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 1/14/2020 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 1/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 1/16/2020 Partial Approval ALEJANDRO DE ARTOLA
Gas Test 1/17/2020 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/2/2020 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/3/2020 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/8/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/12/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/15/2020 Approved ALEJANDRO DE ARTOLA
Final 5/15/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/19/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/22/2020 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 5/27/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/27/2020 Conditional Approval ALEJANDRO DE ARTOLA
HVAC-Final 5/28/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/22/2020 Approved ALEJANDRO DE ARTOLA
Final 6/22/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/22/2020 Approved ALEJANDRO DE ARTOLA
Green Building Final 6/22/2020 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Barrier 6/22/2020 Approved ALEJANDRO DE ARTOLA
METHANE-Final 6/22/2020 Approved ALEJANDRO DE ARTOLA
METHANE-Rough 6/22/2020 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 6/22/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/22/2020 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/22/2020 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 6/22/2020 Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/1/2020 Approved ALEJANDRO DE ARTOLA
Final 7/7/2020 Conditional Approval ALEJANDRO DE ARTOLA
Green Building Final 7/7/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/7/2020 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/7/2020 SGSOV Approved ALEJANDRO DE ARTOLA
Final 8/11/2020 Conditional Approval ALEJANDRO DE ARTOLA