7818 N FULTON AVE 91605
Certificate Information: 7818 N FULTON AVE 91605
- Application / Permit
- 18010-20000-03262
- Plan Check / Job No.
- B18VN10897
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE 25'X47' ACCESSORY DWELLING UNIT (PER AB 494 AND SB 229) ADDITION TO (E) DETACHED TWO CAR GARAGE
- Permit Issued
- Issued on 6/19/2020
- Issuing Office
- Current Status
- CofO Issued on 2/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2018 | APPLICANT |
| Green Plans Picked Up | 8/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2018 | DAWN MC NULTY |
| Corrections Issued | 8/15/2018 | DAWN MC NULTY |
| Quality Review Completed | 8/16/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 8/28/2018 | APPLICANT |
| Applicant returned to address corrections | 12/6/2019 | DAWN MC NULTY |
| Plan Check Approved | 6/19/2020 | DAWN MC NULTY |
| Issued | 6/19/2020 | APPLICANT |
| CofO in Progress | 12/30/2020 | GREGG CUMMINGS |
| CofO Issued | 2/20/2021 | MICHAEL SMITH |
| Permit Finaled | 2/20/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2019 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2019 | GABRIEL ROBLES |
| Permit | Cleared | 7/29/2019 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/29/2019 | GABRIEL ROBLES |
| Green Code | Cleared | 10/24/2019 | PARISA ZAHABI |
| Low Impact Development | Cleared | 11/5/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/5/2019 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 6/15/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/7/2020 | Partial Inspection | WILLIAM KUEHN |
| Excavation/Setback/Form/Re-Bar | 7/14/2020 | Approved | DANIEL ORRANTE |
| Footing/Foundation/Slab | 7/14/2020 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 8/20/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/20/2020 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 8/20/2020 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/20/2020 | Approved | GREGG CUMMINGS |
| Sewer | 8/20/2020 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/27/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/27/2020 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2020 | Approved | GREGG CUMMINGS |
| Green Building Rough | 8/27/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 8/27/2020 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/2/2020 | Approved | GREGG CUMMINGS |
| Green Building Rough | 9/2/2020 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 9/2/2020 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/14/2020 | Partial Approval | THOMAS FINNILA |
| Insulation | 9/14/2020 | Partial Inspection | THOMAS FINNILA |
| Drywall Nailing | 9/22/2020 | Approved | GREGG CUMMINGS |
| Insulation | 9/22/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/22/2020 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 9/22/2020 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/8/2020 | Approved | GREGG CUMMINGS |
| Shower Pan | 10/8/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 12/23/2020 | Corrections Issued | GREGG CUMMINGS |
| Final | 12/23/2020 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 12/23/2020 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 12/23/2020 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Final | 12/23/2020 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 12/23/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 12/30/2020 | Approved | GREGG CUMMINGS |
| Final | 12/30/2020 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 12/30/2020 | Approved | GREGG CUMMINGS |
| HVAC-Final | 12/30/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 12/30/2020 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/30/2020 | SGSOV Approved | GREGG CUMMINGS |