11502 W CUMPSTON ST 91601
Certificate Information: 11502 W CUMPSTON ST 91601
- Application / Permit
- 18010-20000-03247
- Plan Check / Job No.
- B18VN10786
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3 STORY 12 UNITS APARTMENT WITH OPEN ROOF DECK OVER BASEMENT GARAGE (TYPE VA/IA CONSTRUCTION, R2/S2 OCCUPANCY) _ BUILDING SHALL BE FULLY SPRINKLER W/ NFPA 13. _1 extremely low, 1 very low, 1 low, and 1 market rate RSO unit required.
- Permit Issued
- Issued on 12/23/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 7/24/2018 | APPLICANT |
| Green Plans Picked Up | 8/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2018 | DAWN MC NULTY |
| Corrections Issued | 9/5/2018 | DAWN MC NULTY |
| Quality Review Completed | 9/7/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 9/10/2018 | APPLICANT |
| Applicant returned to address corrections | 9/20/2018 | DAWN MC NULTY |
| Applicant returned to address corrections | 10/4/2018 | DAWN MC NULTY |
| Applicant returned to address corrections | 3/7/2019 | DAWN MC NULTY |
| Applicant returned to address corrections | 9/23/2019 | DAWN MC NULTY |
| Applicant returned to address corrections | 10/8/2019 | DAWN MC NULTY |
| Plan Check Approved | 12/23/2019 | DAWN MC NULTY |
| Issued | 12/23/2019 | LADBS |
| TCO Issued (Expire Date: 12-03-2022) | 6/6/2022 | JEFFREY DURAN |
| CofO in Progress | 7/29/2022 | ROBERT DAVIS |
| Permit Finaled | 8/5/2022 | JEFFREY DURAN |
| CofO Issued | 8/5/2022 | JEFFREY DURAN |
| Permit Finaled | 8/5/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2018 | KAYLA PEJI |
| Address approval | Cleared | 12/6/2018 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 1/3/2019 | JOHN DALLAS |
| CPC | Cleared | 1/8/2019 | RINA LARA |
| Frnt yard landscape/Water mgmt | Cleared | 1/8/2019 | RINA LARA |
| Opn space landscape/Water mgmt | Cleared | 1/8/2019 | RINA LARA |
| Green Code | Cleared | 1/9/2019 | MICHAEL AYERS |
| Sewer availability | Cleared | 6/18/2019 | JOHN LIN |
| Low Impact Development | Cleared | 7/24/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/24/2019 | CELINA MORENO |
| "Q" conditions | Cleared | 8/22/2019 | HERMINIGILDO AGUSTIN |
| Highway dedication | Cleared | 9/5/2019 | LEE GUILBEAUX |
| Permit | Cleared | 9/5/2019 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 9/9/2019 | LEE GUILBEAUX |
| Fire Marshall Fire Life Safety | Cleared | 10/28/2019 | OSCAR SALGADO JR |
| Building over 3-story or 36-ft | Cleared | 10/31/2019 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 10/31/2019 | DAWN MC NULTY |
| DAS Clearance | Cleared | 11/26/2019 | NORLITO MEDRANO |
| Density Bonus 12.22.A.31 | Cleared | 12/16/2019 | MICHAEL ZIRBES |
| Miscellaneous | Cleared | 12/19/2019 | ULISES GONZALEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/13/2020 | Corrections Issued | JOHN KITCKO |
| Footing/Foundation/Slab | 1/24/2020 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 2/3/2020 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 2/4/2020 | Approved | JOHN KITCKO |
| Deputy Reinf. Masonry | 2/5/2020 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 2/7/2020 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 2/7/2020 | Approved | ROBERT DAVIS |
| Footing/Foundation/Slab | 2/7/2020 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 2/11/2020 | Conditional Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 2/12/2020 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 2/14/2020 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 2/20/2020 | Conditional Approval | ROBERT DAVIS |
| Green Building Rough | 2/21/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Reinforced Concrete Frame | 2/21/2020 | Partial Approval | ROBERT DAVIS |
| Reinforced Masonry Frame | 2/21/2020 | Partial Approval | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 2/21/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Reinf. Concrete | 2/24/2020 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 2/27/2020 | Conditional Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 3/2/2020 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 3/9/2020 | Partial Approval | ROBERT DAVIS |
| Special/Order Compliance | 3/9/2020 | Corrections Issued | ROBERT DAVIS |
| Deputy Reinf. Concrete | 4/3/2020 | Conditional Approval | ROBERT DAVIS |
| Green Building Rough | 4/3/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Reinforced Concrete Frame | 4/3/2020 | Partial Approval | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 4/3/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Reinf. Concrete | 4/7/2020 | Conditional Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 5/11/2020 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 5/11/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Reinforced Concrete Frame | 5/11/2020 | Partial Approval | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 5/11/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2020 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2020 | Partial Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2020 | Approved | ROBERT DAVIS |
| Insulation | 8/25/2020 | Not Ready for Inspection | JOHN KITCKO |
| Insulation | 8/26/2020 | No Access for Inspection | SORIN CIRSTOIU |
| Insulation | 8/28/2020 | Not Ready for Inspection | JOHN KITCKO |
| Insulation | 8/31/2020 | Partial Approval | ROBERT DAVIS |
| Insulation | 9/22/2020 | Partial Inspection | SORIN CIRSTOIU |
| Insulation | 9/24/2020 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 10/1/2020 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 10/9/2020 | Partial Inspection | ROBERT DAVIS |
| Interior/Exterior Lathing | 10/14/2020 | Order to Comply Issued | ROBERT DAVIS |
| Drywall Nailing | 11/6/2020 | Partial Approval | ROBERT DAVIS |
| Insulation | 11/6/2020 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 1/29/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 1/29/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 2/12/2021 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 2/22/2021 | Partial Approval | ROBERT DAVIS |
| Interior/Exterior Lathing | 4/1/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Interior/Exterior Lathing | 4/7/2021 | Partial Inspection | JEFFREY FULTON |
| Interior/Exterior Lathing | 5/4/2021 | Partial Approval | ROBERT DAVIS |
| Special/Order Compliance | 4/22/2022 | Partial Inspection | ROBERT DAVIS |
| Special/Order Compliance | 4/27/2022 | Partial Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 5/17/2022 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 5/19/2022 | Approved | ROBERT DAVIS |
| Final | 7/29/2022 | OK to Issue CofO | ROBERT DAVIS |
| Footing/Foundation/Slab | 7/29/2022 | Approved | ROBERT DAVIS |
| Green Building Final | 7/29/2022 | Approved | ROBERT DAVIS |
| Green Building Rough | 7/29/2022 | Approved | ROBERT DAVIS |
| Reinforced Concrete Frame | 7/29/2022 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 7/29/2022 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 7/29/2022 | Approved | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 7/29/2022 | Approved | ROBERT DAVIS |
| Wood Frame | 7/29/2022 | Approved | ROBERT DAVIS |