11502 W CUMPSTON ST 91601

Certificate Information: 11502 W CUMPSTON ST 91601

Application / Permit
18010-20000-03247
Plan Check / Job No.
B18VN10786
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY 12 UNITS APARTMENT WITH OPEN ROOF DECK OVER BASEMENT GARAGE (TYPE VA/IA CONSTRUCTION, R2/S2 OCCUPANCY) _ BUILDING SHALL BE FULLY SPRINKLER W/ NFPA 13. _1 extremely low, 1 very low, 1 low, and 1 market rate RSO unit required.
Permit Issued
Issued on 12/23/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2018 APPLICANT
Disabled Access Plans Picked Up 7/24/2018 APPLICANT
Green Plans Picked Up 8/8/2018 APPLICANT
Assigned to Plan Check Engineer 8/16/2018 DAWN MC NULTY
Corrections Issued 9/5/2018 DAWN MC NULTY
Quality Review Completed 9/7/2018 CHON CHIO KUO
Building Plans Picked Up 9/10/2018 APPLICANT
Applicant returned to address corrections 9/20/2018 DAWN MC NULTY
Applicant returned to address corrections 10/4/2018 DAWN MC NULTY
Applicant returned to address corrections 3/7/2019 DAWN MC NULTY
Applicant returned to address corrections 9/23/2019 DAWN MC NULTY
Applicant returned to address corrections 10/8/2019 DAWN MC NULTY
Plan Check Approved 12/23/2019 DAWN MC NULTY
Issued 12/23/2019 LADBS
TCO Issued (Expire Date: 12-03-2022) 6/6/2022 JEFFREY DURAN
CofO in Progress 7/29/2022 ROBERT DAVIS
Permit Finaled 8/5/2022 JEFFREY DURAN
CofO Issued 8/5/2022 JEFFREY DURAN
Permit Finaled 8/5/2022 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/29/2018 KAYLA PEJI
Address approval Cleared 12/6/2018 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 1/3/2019 JOHN DALLAS
CPC Cleared 1/8/2019 RINA LARA
Frnt yard landscape/Water mgmt Cleared 1/8/2019 RINA LARA
Opn space landscape/Water mgmt Cleared 1/8/2019 RINA LARA
Green Code Cleared 1/9/2019 MICHAEL AYERS
Sewer availability Cleared 6/18/2019 JOHN LIN
Low Impact Development Cleared 7/24/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 7/24/2019 CELINA MORENO
"Q" conditions Cleared 8/22/2019 HERMINIGILDO AGUSTIN
Highway dedication Cleared 9/5/2019 LEE GUILBEAUX
Permit Cleared 9/5/2019 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 9/9/2019 LEE GUILBEAUX
Fire Marshall Fire Life Safety Cleared 10/28/2019 OSCAR SALGADO JR
Building over 3-story or 36-ft Cleared 10/31/2019 CALOSHA APPROVED
Miscellaneous Cleared 10/31/2019 DAWN MC NULTY
DAS Clearance Cleared 11/26/2019 NORLITO MEDRANO
Density Bonus 12.22.A.31 Cleared 12/16/2019 MICHAEL ZIRBES
Miscellaneous Cleared 12/19/2019 ULISES GONZALEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/13/2020 Corrections Issued JOHN KITCKO
Footing/Foundation/Slab 1/24/2020 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 2/3/2020 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 2/4/2020 Approved JOHN KITCKO
Deputy Reinf. Masonry 2/5/2020 Approved JOHN KITCKO
Deputy Reinf. Concrete 2/7/2020 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 2/7/2020 Approved ROBERT DAVIS
Footing/Foundation/Slab 2/7/2020 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 2/11/2020 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 2/12/2020 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 2/14/2020 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 2/20/2020 Conditional Approval ROBERT DAVIS
Green Building Rough 2/21/2020 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 2/21/2020 Partial Approval ROBERT DAVIS
Reinforced Masonry Frame 2/21/2020 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 2/21/2020 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 2/24/2020 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 2/27/2020 Conditional Approval ROBERT DAVIS
Masonry Wall/Backfill 3/2/2020 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 3/9/2020 Partial Approval ROBERT DAVIS
Special/Order Compliance 3/9/2020 Corrections Issued ROBERT DAVIS
Deputy Reinf. Concrete 4/3/2020 Conditional Approval ROBERT DAVIS
Green Building Rough 4/3/2020 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 4/3/2020 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 4/3/2020 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 4/7/2020 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 5/11/2020 Partial Approval ROBERT DAVIS
Green Building Rough 5/11/2020 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 5/11/2020 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 5/11/2020 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/26/2020 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/6/2020 Approved ROBERT DAVIS
Insulation 8/25/2020 Not Ready for Inspection JOHN KITCKO
Insulation 8/26/2020 No Access for Inspection SORIN CIRSTOIU
Insulation 8/28/2020 Not Ready for Inspection JOHN KITCKO
Insulation 8/31/2020 Partial Approval ROBERT DAVIS
Insulation 9/22/2020 Partial Inspection SORIN CIRSTOIU
Insulation 9/24/2020 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 10/1/2020 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 10/9/2020 Partial Inspection ROBERT DAVIS
Interior/Exterior Lathing 10/14/2020 Order to Comply Issued ROBERT DAVIS
Drywall Nailing 11/6/2020 Partial Approval ROBERT DAVIS
Insulation 11/6/2020 Partial Approval ROBERT DAVIS
Drywall Nailing 1/29/2021 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 1/29/2021 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 2/12/2021 Partial Approval ROBERT DAVIS
Drywall Nailing 2/22/2021 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 4/1/2021 Not Ready for Inspection ROBERT DAVIS
Interior/Exterior Lathing 4/7/2021 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 5/4/2021 Partial Approval ROBERT DAVIS
Special/Order Compliance 4/22/2022 Partial Inspection ROBERT DAVIS
Special/Order Compliance 4/27/2022 Partial Inspection ROBERT DAVIS
Light Gage Steel Frame 5/17/2022 Partial Approval ROBERT DAVIS
Drywall Nailing 5/19/2022 Approved ROBERT DAVIS
Final 7/29/2022 OK to Issue CofO ROBERT DAVIS
Footing/Foundation/Slab 7/29/2022 Approved ROBERT DAVIS
Green Building Final 7/29/2022 Approved ROBERT DAVIS
Green Building Rough 7/29/2022 Approved ROBERT DAVIS
Reinforced Concrete Frame 7/29/2022 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved ROBERT DAVIS
Smoke Detectors 7/29/2022 Approved ROBERT DAVIS
Verify Sprinkler Sign Off 7/29/2022 Approved ROBERT DAVIS
Wood Frame 7/29/2022 Approved ROBERT DAVIS