6932 N QUAKERTOWN AVE 91306
Certificate Information: 6932 N QUAKERTOWN AVE 91306
- Application / Permit
- 18010-20000-03202
- Plan Check / Job No.
- B18VN10600
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 25' X 23' 1-STORY IRREGULAR-SHAPED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WOOD FRAME PRESCRIPTIVE PROVISIONS. "COMPLY WITH DEPARTMENT ORDER effective date 12/19/2016. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 3/29/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2018 | APPLICANT |
| Green Plans Picked Up | 8/1/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2018 | GURUNATH NESARAJAH |
| Corrections Issued | 8/13/2018 | GURUNATH NESARAJAH |
| Quality Review Completed | 8/21/2018 | STEVEN KIM |
| Building Plans Picked Up | 8/29/2018 | APPLICANT |
| Plan Check Approved | 3/29/2019 | GURUNATH NESARAJAH |
| Issued | 3/29/2019 | LADBS |
| CofO Issued | 12/4/2024 | DAVID JAMES |
| Permit Finaled | 12/4/2024 | DAVID JAMES |
Permit Application Clearance Information
| Green Code | Cleared | 8/8/2018 | PARISA ZAHABI |
| Address approval | Cleared | 10/2/2018 | KAYLA PEJI |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2018 | KAYLA PEJI |
| Hydrant and Access approval | Cleared | 10/2/2018 | JOHN DALLAS |
| ZI | Cleared | 12/31/2018 | DAISY BENICIA |
| Construction near power lines | Cleared | 3/1/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/1/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/18/2019 | MITESH PATEL |
| Sewer availability | Cleared | 3/26/2019 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 3/27/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/2/2019 | Not Ready for Inspection | RONALD PACHECO |
| Gas Test | 5/2/2019 | Not Ready for Inspection | RONALD PACHECO |
| PLUMBING-Rough | 5/2/2019 | Not Ready for Inspection | RONALD PACHECO |
| Underground Mechanical | 5/2/2019 | Partial Approval | RONALD PACHECO |
| BUILDING-Rough-Frame | 4/28/2020 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Drywall Nailing | 4/28/2020 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Final | 4/28/2020 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Footing/Foundation/Slab | 4/28/2020 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Green Building Final | 4/28/2020 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Green Building Rough | 4/28/2020 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2020 | SGSOV Not Ready | EMIL ALEXANDRIAN |
| Service/Power Release | 4/28/2020 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Smoke Detectors | 4/28/2020 | Corrections Issued | EMIL ALEXANDRIAN |
| Verify Sprinkler Sign Off | 4/28/2020 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Pre-Inspection | 12/20/2022 | Approved | EMIL ALEXANDRIAN |
| Footing/Foundation/Slab | 2/6/2023 | Approved | EMIL ALEXANDRIAN |
| PLUMBING-Rough | 6/15/2023 | Corrections Issued | EMIL ALEXANDRIAN |
| BUILDING-Rough-Frame | 8/23/2023 | Approved | EMIL ALEXANDRIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Approved | EMIL ALEXANDRIAN |
| Green Building Rough | 8/23/2023 | Approved | EMIL ALEXANDRIAN |
| Rough-Elec/Plmb/HVAC | 8/23/2023 | Approved | EMIL ALEXANDRIAN |
| Verify Sprinkler Sign Off | 8/23/2023 | Approved | EMIL ALEXANDRIAN |
| Insulation | 8/28/2023 | Approved | EMIL ALEXANDRIAN |
| Interior/Exterior Lathing | 8/28/2023 | Approved | EMIL ALEXANDRIAN |
| Shower Pan | 8/28/2023 | Approved | EMIL ALEXANDRIAN |
| Drywall Nailing | 8/31/2023 | Approved | EMIL ALEXANDRIAN |
| Final | 11/16/2023 | Conditional Approval | ARA SINANIAN |
| Green Building Final | 11/16/2023 | Approved | ARA SINANIAN |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Approved | ARA SINANIAN |
| Smoke Detectors | 11/16/2023 | Approved | ARA SINANIAN |