Footing/Foundation/Slab
|
11/1/2018
|
Conditional Approval
|
JOHN COLEMAN
|
|
ELECTRICAL-Rough
|
11/6/2018
|
Not Ready for Inspection
|
FRED HANNUM
|
|
Excavation/Setback/Form/Re-Bar
|
11/30/2018
|
Order to Comply Issued
|
FRED HANNUM
|
|
Footing/Foundation/Slab
|
11/30/2018
|
Order to Comply Issued
|
FRED HANNUM
|
|
Light Gage Steel Frame
|
11/30/2018
|
Order to Comply Issued
|
FRED HANNUM
|
|
Excavation/Setback/Form/Re-Bar
|
12/4/2018
|
No Access for Inspection
|
FRED HANNUM
|
|
Excavation/Setback/Form/Re-Bar
|
12/11/2018
|
Approved
|
FRED HANNUM
|
|
Footing/Foundation/Slab
|
12/11/2018
|
Partial Approval
|
FRED HANNUM
|
|
Special/Order Compliance
|
12/11/2018
|
Approved
|
DONALD SUNSERI
|
|
Reinforced Concrete Frame
|
12/18/2018
|
Partial Approval
|
PETER FOLLING
|
|
Structural Steel Frame
|
12/18/2018
|
Partial Approval
|
PETER FOLLING
|
|
Deputy Shotcrete
|
12/20/2018
|
Approved
|
FRED HANNUM
|
|
Footing/Foundation/Slab
|
1/10/2019
|
Approved
|
FRED HANNUM
|
|
PLUMBING-Rough
|
1/10/2019
|
Partial Approval
|
FRED HANNUM
|
|
Sewer
|
1/10/2019
|
Approved
|
FRED HANNUM
|
|
Footing/Foundation/Slab
|
3/21/2019
|
Approved
|
RYAN MCGILL
|
|
Structural Steel Frame
|
3/21/2019
|
Partial Approval
|
RYAN MCGILL
|
|
Underground Mechanical
|
3/21/2019
|
Partial Approval
|
RYAN MCGILL
|
|
Footing/Foundation/Slab
|
3/22/2019
|
Corrections Issued
|
RYAN MCGILL
|
|
PLUMBING-Rough
|
8/6/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/7/2019
|
Not Ready for Inspection
|
RYAN MCGILL
|
|
Special/Order Compliance
|
8/7/2019
|
Approved
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/9/2019
|
Corrections Issued
|
RYAN MCGILL
|
|
PLUMBING-Rough
|
8/9/2019
|
Corrections Issued
|
RYAN MCGILL
|
|
Special/Order Compliance
|
8/9/2019
|
Approved
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/12/2019
|
Corrections Issued
|
RYAN MCGILL
|
|
PLUMBING-Rough
|
8/12/2019
|
Partial Approval
|
RYAN MCGILL
|
|
Special/Order Compliance
|
8/12/2019
|
Approved
|
DONALD SUNSERI
|
|
ELECTRICAL-Rough
|
9/9/2019
|
Not Ready for Inspection
|
SEAN WIRCH
|
|
PLUMBING-Rough
|
9/9/2019
|
Approved
|
RYAN MCGILL
|
|
Underground Mechanical
|
9/9/2019
|
Partial Approval
|
RYAN MCGILL
|
|
Wood Frame
|
9/9/2019
|
Not Ready for Inspection
|
RYAN MCGILL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/12/2019
|
Partial Approval
|
RYAN MCGILL
|
|
PLUMBING-Rough
|
9/12/2019
|
Approved
|
RYAN MCGILL
|
|
Special/Order Compliance
|
9/12/2019
|
Approved
|
DONALD SUNSERI
|
|
ELECTRICAL-Rough
|
10/7/2019
|
Not Ready for Inspection
|
RYAN MCGILL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/7/2019
|
Partial Approval
|
RYAN MCGILL
|
|
Interior/Exterior Lathing
|
10/7/2019
|
Not Ready for Inspection
|
RYAN MCGILL
|
|
Special/Order Compliance
|
10/7/2019
|
Approved
|
DONALD SUNSERI
|
|
Shower Pan
|
10/10/2019
|
Corrections Issued
|
RYAN MCGILL
|
|
Special/Order Compliance
|
10/10/2019
|
Approved
|
DONALD SUNSERI
|
|
ELECTRICAL-Rough
|
10/11/2019
|
Not Ready for Inspection
|
SEAN WIRCH
|
|
HVAC-Rough
|
10/11/2019
|
Not Ready for Inspection
|
RYAN MCGILL
|
|
Wood Frame
|
10/11/2019
|
Not Ready for Inspection
|
RYAN MCGILL
|
|
BUILDING-Rough-Frame
|
10/24/2019
|
Corrections Issued
|
DONALD SUNSERI
|
|
Green Building Rough
|
10/24/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
HVAC-Rough
|
10/24/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
Interior/Exterior Lathing
|
10/24/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
Shower Pan
|
10/24/2019
|
Approved
|
DONALD SUNSERI
|
|
Verify Sprinkler Sign Off
|
10/24/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
BUILDING-Rough-Frame
|
11/14/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
ELECTRICAL-Rough
|
11/14/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Enclosure/Fence
|
11/14/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Green Building Rough
|
11/14/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
HVAC-Rough
|
11/14/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Interior/Exterior Lathing
|
11/14/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Smoke Detectors
|
11/14/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Verify Sprinkler Sign Off
|
11/14/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Wood Frame
|
11/14/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
ELECTRICAL-Rough
|
11/21/2019
|
Approved
|
JOHN KIDWELL
|
|
HVAC-Rough
|
11/21/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Interior/Exterior Lathing
|
11/21/2019
|
Partial Approval
|
JOHN KIDWELL
|
|
Rough-Elec/Plmb/HVAC
|
11/21/2019
|
Partial Approval
|
JOHN KIDWELL
|
|
Wood Frame
|
11/21/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Insulation
|
12/2/2019
|
Partial Approval
|
DAVID SCANTLIN
|
|
Interior/Exterior Lathing
|
12/2/2019
|
Partial Approval
|
DAVID SCANTLIN
|
|
BUILDING-Rough-Frame
|
12/16/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Green Building Rough
|
12/16/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Rough-Elec/Plmb/HVAC
|
12/16/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Verify Sprinkler Sign Off
|
12/16/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Wood Frame
|
12/16/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Insulation
|
1/30/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Interior/Exterior Lathing
|
1/30/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Rough-Elec/Plmb/HVAC
|
1/30/2020
|
Approved
|
JOHN KIDWELL
|
|
Wood Frame
|
1/30/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Special/Order Compliance
|
3/27/2020
|
Corrections Issued
|
JOHN KIDWELL
|
|
BUILDING-Rough-Frame
|
6/4/2020
|
Approved
|
JOHN KIDWELL
|
|
Drywall Nailing
|
6/4/2020
|
Approved
|
JOHN KIDWELL
|
|
Final
|
6/4/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Footing/Foundation/Slab
|
6/4/2020
|
Approved
|
JOHN KIDWELL
|
|
Green Building Final
|
6/4/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Green Building Rough
|
6/4/2020
|
Approved
|
JOHN KIDWELL
|
|
Insulation
|
6/4/2020
|
Approved
|
JOHN KIDWELL
|
|
SGSOV-Seismic Gas S/O Valve
|
6/4/2020
|
SGSOV Not Ready
|
JOHN KIDWELL
|
|
Smoke Detectors
|
6/4/2020
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Verify Sprinkler Sign Off
|
6/4/2020
|
Approved
|
JOHN KIDWELL
|
|
Final
|
6/12/2020
|
Not Ready for Inspection
|
TROY SANDERS
|
|
Green Building Final
|
6/12/2020
|
Not Ready for Inspection
|
TROY SANDERS
|
|
SGSOV-Seismic Gas S/O Valve
|
6/12/2020
|
SGSOV Not Ready
|
TROY SANDERS
|
|
Service/Power Release
|
6/12/2020
|
Not Ready for Inspection
|
TROY SANDERS
|
|
Smoke Detectors
|
6/12/2020
|
Not Ready for Inspection
|
TROY SANDERS
|
|
SGSOV-Seismic Gas S/O Valve
|
7/2/2020
|
SGSOV Not Ready
|
TROY SANDERS
|
|
Final
|
7/13/2020
|
Corrections Issued
|
TROY SANDERS
|
|
SGSOV-Seismic Gas S/O Valve
|
7/13/2020
|
SGSOV Not Ready
|
TROY SANDERS
|
|
ELECTRICAL-Final
|
7/17/2020
|
Corrections Issued
|
TROY SANDERS
|
|
Final
|
7/17/2020
|
Corrections Issued
|
TROY SANDERS
|
|
Green Building Final
|
7/17/2020
|
Approved
|
TROY SANDERS
|
|
HVAC-Final
|
7/17/2020
|
Corrections Issued
|
TROY SANDERS
|
|
PLUMBING-Final
|
7/17/2020
|
Corrections Issued
|
TROY SANDERS
|
|
SGSOV-Seismic Gas S/O Valve
|
7/17/2020
|
SGSOV Not Ready
|
TROY SANDERS
|
|
Service/Power Release
|
7/17/2020
|
Corrections Issued
|
TROY SANDERS
|
|
Smoke Detectors
|
7/17/2020
|
Approved
|
TROY SANDERS
|
|
SGSOV-Seismic Gas S/O Valve
|
7/21/2020
|
SGSOV Not Ready
|
TROY SANDERS
|
|
Final
|
7/23/2020
|
Corrections Issued
|
TROY SANDERS
|
|
Service/Power Release
|
7/23/2020
|
Not Ready for Inspection
|
TROY SANDERS
|
|
Special/Order Compliance
|
7/23/2020
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
ELECTRICAL-Final
|
7/30/2020
|
Approved
|
DONALD SUNSERI
|
|
Final
|
7/30/2020
|
OK to Issue CofO
|
DONALD SUNSERI
|
|
HVAC-Final
|
7/30/2020
|
Approved
|
DONALD SUNSERI
|
|
PLUMBING-Final
|
7/30/2020
|
Approved
|
DONALD SUNSERI
|
|
SGSOV-Seismic Gas S/O Valve
|
8/3/2020
|
SGSOV Approved
|
DONALD SUNSERI
|