1754 N BERENDO ST 90027
Certificate Information: 1754 N BERENDO ST 90027
- Application / Permit
- 18010-20000-03049
- Plan Check / Job No.
- B18VN10308
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- 3 STORY 4 UNITS APARTMENT
- Permit Issued
- Issued on 7/28/2020
- Issuing Office
- Current Status
- CofO Issued on 3/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 8/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2018 | LARRY LEE |
| Corrections Issued | 8/14/2018 | LARRY LEE |
| Quality Review Completed | 8/17/2018 | CHARLES CHANG |
| Applicant returned to address corrections | 9/12/2018 | LARRY LEE |
| Applicant returned to address corrections | 10/19/2018 | LARRY LEE |
| Applicant returned to address corrections | 1/30/2019 | LARRY LEE |
| Applicant returned to address corrections | 3/12/2020 | LARRY LEE |
| Green Plans Picked Up | 6/30/2020 | APPLICANT |
| Applicant returned to address corrections | 7/14/2020 | LARRY LEE |
| Plan Check Approved | 7/16/2020 | LARRY LEE |
| Issued | 7/28/2020 | APPLICANT |
| CofO in Progress | 2/29/2024 | DAVID BURKHEAD |
| CofO Issued | 3/5/2024 | ERNESTO CORRAL |
| Permit Finaled | 3/5/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Highway dedication | Cleared | 9/12/2018 | JEANETTE VONG |
| ZA Case | Cleared | 10/24/2019 | HERMINIGILDO AGUSTIN |
| Fire Marshall Fire Life Safety | Cleared | 10/28/2019 | OSCAR SALGADO JR |
| DAS Clearance | Cleared | 12/13/2019 | ELIZABETH TOMS |
| Address approval | Cleared | 12/18/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2019 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 12/18/2019 | GEORGE SUCHAND |
| Permit | Cleared | 12/18/2019 | JEANIE LAM |
| Sewer availability | Cleared | 12/18/2019 | JEANIE LAM |
| Trees in Parkway | Cleared | 1/7/2020 | JOHN KIM |
| Low Impact Development | Cleared | 2/3/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/5/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 2/19/2020 | PARISA ZAHABI |
| Frnt yard landscape/Water mgmt | Cleared | 3/3/2020 | SARAHI ORTEGA |
| Miscellaneous | Cleared | 3/3/2020 | SARAHI ORTEGA |
| Specific Plan | Cleared | 3/3/2020 | SARAHI ORTEGA |
| Miscellaneous | Cleared | 3/12/2020 | MARITZA LEE |
Contact Information
| Architect | Patian,, Haik; Lic. No.: C33549 | 3232 BEAUDRY TERRACE GLENDALE, CA 91208 |
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, David Thomas; Lic. No.: GE2721 | 1641 BORDER AVE TORRANCE, CA 90501 |
| Engineer | Oruncakciel, Sayat; Lic. No.: C77182 | 18246 ANNA LANE TARZANA, CA 91356 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/14/2021 | Partial Approval | KATY RAMIREZ |
| Footing/Foundation/Slab | 9/14/2021 | Partial Approval | KATY RAMIREZ |
| Structural Steel Frame | 11/4/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 11/8/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 11/8/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Structural Steel Frame | 11/8/2021 | Partial Inspection | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 11/10/2021 | Conditional Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 11/12/2021 | Partial Approval | DAVID BURKHEAD |
| Structural Steel Frame | 11/12/2021 | Partial Inspection | DAVID BURKHEAD |
| Deputy Steel/Welding | 12/3/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 12/10/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Steel/Welding | 1/12/2022 | Conditional Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Deputy Steel/Welding | 2/11/2022 | Conditional Approval | DAVID BURKHEAD |
| Deputy Wood Construction | 2/23/2022 | Conditional Approval | DAVID BURKHEAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Partial Approval | DAVID BURKHEAD |
| Deputy Wood Construction | 3/31/2022 | Conditional Approval | DAVID BURKHEAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Partial Approval | DAVID BURKHEAD |
| Pre-Inspection | 6/27/2022 | Approved | DAVID BURKHEAD |
| Deputy Wood Construction | 9/29/2022 | Approved | DAVID BURKHEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 11/9/2022 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 11/9/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Green Building Rough | 2/1/2023 | Not Ready for Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 2/1/2023 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 2/1/2023 | Partial Inspection | GREGORY POMISH |
| Green Building Rough | 2/15/2023 | Approved | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 2/15/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 2/15/2023 | Partial Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 3/1/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 3/1/2023 | Corrections Issued | DAVID BURKHEAD |
| Interior/Exterior Lathing | 3/20/2023 | Approved | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 3/20/2023 | Approved | EDWIN GREGORYONA |
| Wood Frame | 3/20/2023 | Approved | EDWIN GREGORYONA |
| Insulation | 4/4/2023 | Approved | DAVID BURKHEAD |
| Drywall Nailing | 4/27/2023 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 5/5/2023 | Partial Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 5/15/2023 | Approved | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 9/28/2023 | Approved | DAVID BURKHEAD |
| Reinforced Concrete Frame | 9/28/2023 | Approved | DAVID BURKHEAD |
| Drywall Nailing | 1/10/2024 | Approved | DAVID BURKHEAD |
| Final | 1/10/2024 | Corrections Issued | DAVID BURKHEAD |
| Green Building Final | 1/10/2024 | Not Ready for Inspection | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 1/10/2024 | SGSOV Not Ready | DAVID BURKHEAD |
| Smoke Detectors | 1/10/2024 | Approved | DAVID BURKHEAD |
| Final | 1/31/2024 | Partial Inspection | DAVID BURKHEAD |
| Green Building Final | 1/31/2024 | Approved | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Approved | DAVID BURKHEAD |
| Final | 2/29/2024 | OK to Issue CofO | DAVID BURKHEAD |