5068 W ROMAINE ST 90029

Certificate Information: 5068 W ROMAINE ST 90029

Application / Permit
18010-20000-02961
Plan Check / Job No.
B18VN10190
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 3-STORY APARTMENT WITH 2 EXTREMELY LOW INCOME DWELLING UNITS PURSUANT TO 12.22.A.31 (TIER 2) AND SUBTERRANEAN PARKING
Permit Issued
Issued on 2/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2018 APPLICANT
Disabled Access Plans Picked Up 7/25/2018 APPLICANT
Green Plans Picked Up 8/8/2018 APPLICANT
Assigned to Plan Check Engineer 8/9/2018 LAWRENCE QUIRANTE
Corrections Issued 8/20/2018 LAWRENCE QUIRANTE
Quality Review Completed 8/24/2018 GARO TELMI
Building Plans Picked Up 8/27/2018 APPLICANT
Applicant returned to address corrections 9/7/2018 LAWRENCE QUIRANTE
Applicant returned to address corrections 11/27/2018 LAWRENCE QUIRANTE
Applicant returned to address corrections 3/19/2019 LAWRENCE QUIRANTE
Applicant returned to address corrections 4/3/2019 LAWRENCE QUIRANTE
Applicant returned to address corrections 4/24/2019 LAWRENCE QUIRANTE
Applicant returned to address corrections 5/9/2019 LAWRENCE QUIRANTE
Plan Check Approved 2/4/2020 LAWRENCE QUIRANTE
Issued 2/6/2020 LADBS
CofO in Progress 2/2/2024 RAFAEL ESPINOZA
Permit Finaled 2/6/2024 ERNESTO CORRAL
CofO Issued 2/6/2024 ERNESTO CORRAL
Permit Finaled 2/6/2024 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/3/2018 EDUARDO PEDROZA
Permit Cleared 10/3/2018 EDUARDO PEDROZA
Work Adjacent to Public Way Cleared 10/3/2018 EDUARDO PEDROZA
Address approval Cleared 11/28/2018 MARKOS PEREZ-BRAN
Sewer availability Cleared 11/28/2018 MARKOS PEREZ-BRAN
Frnt yard landscape/Water mgmt Cleared 1/14/2019 DAISY BENICIA
Opn space landscape/Water mgmt Cleared 1/14/2019 DAISY BENICIA
Hydrant and Access approval Cleared 1/16/2019 GEORGE SUCHAND
Low Impact Development Cleared 2/19/2019 IDA MEISAMI-FARD
DAS Clearance Cleared 2/26/2019 NORLITO MEDRANO
Green Code Cleared 3/15/2019 DAVID MATSON
Fire Marshall Fire Life Safety Cleared 3/29/2019 DOMINIQUE MEDINA
Building over 3-story or 36-ft Cleared 6/12/2019 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 6/17/2019 SAFA JAVANMARDI
Density Bonus 12.22.A.31 Cleared 1/27/2020 MICHAEL ZIRBES

Contact Information

Architect Armen, Kazanchyan; Lic. No.: C34021       ,
Contractor A W I Builders Inc; Lic. No.: 818478-B 1027 SHERLOCK DR      BURBANK, CA 91501
Engineer Haddad, Raymond Mounir; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Sayah,, Daniel Hoshyar; Lic. No.: S6000 15233 VENTURA BLVD 1130      SHERMAN OAKS, CA 91403

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/27/2020 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 5/28/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 6/10/2020 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 6/16/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/17/2020 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 6/23/2020 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 6/24/2020 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 6/25/2020 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/14/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/15/2020 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/27/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/28/2020 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Partial Approval EDWIN GREGORYONA
Green Building Rough 8/13/2020 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/13/2020 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Partial Approval EDWIN GREGORYONA
Green Building Rough 8/31/2020 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/31/2020 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/14/2020 Partial Approval EDWIN GREGORYONA
Green Building Rough 9/14/2020 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 9/14/2020 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/29/2020 Partial Approval EDWIN GREGORYONA
Green Building Rough 9/29/2020 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 9/29/2020 Partial Inspection EDWIN GREGORYONA
Pre-Inspection 12/8/2020 Partial Inspection EDWIN GREGORYONA
Green Building Rough 1/11/2021 Partial Inspection EDWIN GREGORYONA
Insulation 1/11/2021 Partial Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 1/11/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 1/11/2021 Approved EDWIN GREGORYONA
Wood Frame 1/11/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 3/16/2021 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 4/14/2021 Approved EDWIN GREGORYONA
Special/Order Compliance 8/11/2021 Approved EDWIN GREGORYONA
Drywall Nailing 8/12/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 8/26/2021 Partial Approval RUSSELL BONVOULOIR
Pre-Inspection 9/3/2021 Approved RUSSELL BONVOULOIR
Interior/Exterior Lathing 9/17/2021 Approved RUSSELL BONVOULOIR
Light Gage Steel Frame 10/7/2021 Partial Inspection SORIN CIRSTOIU
Light Gage Steel Frame 10/12/2021 Partial Approval SORIN CIRSTOIU
Pre-Inspection 6/3/2022 No Access for Inspection JONATHAN QUACH
Pre-Inspection 6/15/2022 Partial Inspection JONATHAN QUACH
Final 2/8/2023 Corrections Issued RONALD JIMENEZ
Footing/Foundation/Slab 2/8/2023 Approved RONALD JIMENEZ
Green Building Final 2/8/2023 Not Ready for Inspection RONALD JIMENEZ
Green Building Rough 2/8/2023 Approved RONALD JIMENEZ
Pre-Inspection 2/8/2023 Partial Inspection DAVID BURKHEAD
Reinforced Concrete Frame 2/8/2023 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 2/8/2023 Approved RONALD JIMENEZ
Wood Frame 2/8/2023 Approved RONALD JIMENEZ
Green Building Final 10/11/2023 Not Ready for Inspection LARRY ARNICK
Final 10/16/2023 Partial Inspection RICARDO ROBLES
Pre-Inspection 10/16/2023 Partial Inspection RAFAEL ESPINOZA
Final 2/2/2024 OK to Issue CofO RAFAEL ESPINOZA
Green Building Final 2/2/2024 Approved RAFAEL ESPINOZA