Deputy Reinf. Concrete
|
1/30/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
1/30/2019
|
Corrections Issued
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
2/20/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
2/20/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
2/26/2019
|
Partial Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
2/26/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
4/24/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
4/25/2019
|
Partial Inspection
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
4/26/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
5/1/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
5/1/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
5/6/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
5/8/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
5/8/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
5/10/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
5/10/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
5/14/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
5/15/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
5/21/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
6/19/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
6/20/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
6/26/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
7/1/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
7/3/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
7/3/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
7/12/2019
|
Conditional Approval
|
JAMES STEPHENS
|
|
Deputy Drilled-In Anchors
|
7/25/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
7/31/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
8/8/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
8/19/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/21/2019
|
Partial Inspection
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
8/26/2019
|
Partial Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
8/27/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
9/11/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
9/12/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
9/12/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
9/13/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
9/13/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
9/16/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
9/17/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
9/18/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
9/18/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
9/19/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
9/20/2019
|
Conditional Approval
|
JAMES STEPHENS
|
|
Deputy Steel/Welding
|
10/1/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Light Gage Steel Frame
|
10/1/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
10/2/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
10/3/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
10/4/2019
|
Conditional Approval
|
JAMES STEPHENS
|
|
Masonry Wall/Backfill
|
10/15/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Reinf. Masonry
|
10/16/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
10/17/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/21/2019
|
Partial Approval
|
ROBERT COLE
|
|
Green Building Rough
|
10/21/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
10/22/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Wood Construction
|
10/23/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Insulation
|
10/30/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
11/1/2019
|
Conditional Approval
|
JAMES STEPHENS
|
|
Deputy Steel/Welding
|
11/5/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/6/2019
|
Partial Approval
|
ROBERT COLE
|
|
Green Building Rough
|
11/6/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Deputy Wood Construction
|
11/7/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/13/2019
|
Partial Approval
|
ROBERT COLE
|
|
Green Building Rough
|
11/13/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/20/2019
|
Partial Approval
|
ROBERT COLE
|
|
Green Building Rough
|
11/20/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Interior/Exterior Lathing
|
12/11/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
12/12/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Wood Construction
|
12/31/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/31/2019
|
Partial Approval
|
ROBERT COLE
|
|
Green Building Rough
|
12/31/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Deputy Wood Construction
|
1/15/2020
|
Conditional Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/28/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/7/2020
|
Partial Approval
|
JAMES STEPHENS
|
|
Light Gage Steel Frame
|
2/27/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Deputy Steel/Welding
|
2/28/2020
|
Conditional Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
3/18/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Green Building Rough
|
3/18/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Insulation
|
3/18/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Insulation
|
3/31/2020
|
Partial Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
5/8/2020
|
Partial Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
5/8/2020
|
Partial Approval
|
ROBERT COLE
|
|
Green Building Rough
|
5/8/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Interior/Exterior Lathing
|
5/8/2020
|
Partial Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
5/29/2020
|
Partial Approval
|
ROBERT COLE
|
|
Green Building Rough
|
5/29/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Insulation
|
5/29/2020
|
Partial Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
6/19/2020
|
Partial Approval
|
ROBERT COLE
|
|
Green Building Rough
|
6/19/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Drywall Nailing
|
11/17/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
11/17/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
2/10/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
8/23/2022
|
Approved
|
DANIEL VARNUM
|
|
Final
|
8/23/2022
|
Partial Inspection
|
DANIEL VARNUM
|
|
Footing/Foundation/Slab
|
8/23/2022
|
Approved
|
DANIEL VARNUM
|
|
Green Building Final
|
8/23/2022
|
Approved
|
DANIEL VARNUM
|
|
Green Building Rough
|
8/23/2022
|
Approved
|
DANIEL VARNUM
|
|
Reinforced Masonry Frame
|
8/23/2022
|
Partial Approval
|
DANIEL VARNUM
|
|
SGSOV-Seismic Gas S/O Valve
|
8/23/2022
|
SGSOV Approved
|
DANIEL VARNUM
|
|
Smoke Detectors
|
8/23/2022
|
Approved
|
DANIEL VARNUM
|
|
Structural Steel Frame
|
8/23/2022
|
Partial Approval
|
DANIEL VARNUM
|
|
Verify Sprinkler Sign Off
|
8/23/2022
|
Partial Inspection
|
DANIEL VARNUM
|
|
Final
|
6/5/2026
|
Conditional Approval
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
6/5/2026
|
Approved
|
EDWIN GREGORYONA
|
|
Structural Steel Frame
|
6/5/2026
|
Approved
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
6/5/2026
|
Approved
|
EDWIN GREGORYONA
|