17202 W RAYMER ST 91325

Certificate Information: 17202 W RAYMER ST 91325

Application / Permit
18010-20000-02876
Plan Check / Job No.
B18VN10005
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31'-8" X 14'-6", DETACHED, 2-STORY, ACCESSORY DWELLING UNIT (ADU) PER AB 494 AND SB 229.
Permit Issued
Issued on 5/20/2019
Issuing Office
Valley
Current Status
Issued on 5/20/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/12/2018 APPLICANT
Green Plans Picked Up 6/19/2018 APPLICANT
Assigned to Plan Check Engineer 7/3/2018 ALEXANDER SBARDELLATI
Corrections Issued 7/5/2018 ALEXANDER SBARDELLATI
Quality Review Completed 7/5/2018 CHON CHIO KUO
Building Plans Picked Up 7/10/2018 APPLICANT
Applicant returned to address corrections 4/4/2019 ALEXANDER SBARDELLATI
Plan Check Approved 5/20/2019 ALEXANDER SBARDELLATI
Issued 5/20/2019 LADBS

Permit Application Clearance Information

Address approval Cleared 12/19/2018 KAYLA PEJI
CPC Cleared 12/19/2018 TOM HENRY
Tract Map conditions Cleared 12/19/2018 TOM HENRY
Eng Process Fee Ord 176,300 Cleared 1/8/2019 RUDY TERRIQUEZ.
Miscellaneous Cleared 1/8/2019 RUDY TERRIQUEZ.
Permit Cleared 1/8/2019 RUDY TERRIQUEZ.
Sewer availability Cleared 1/8/2019 RUDY TERRIQUEZ.
Low Impact Development Cleared 2/14/2019 MARTIN FRAGOSO
Metro Rail approval Cleared 3/26/2019 ALEXANDER SBARDELLATI
Green Code Cleared 4/1/2019 COLIN LOREDO
Hydrant and Access approval Cleared 5/6/2019 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 5/6/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,
Engineer Eden, Joseph Taki; Lic. No.: C39955 14416 FRIAR ST STE A      VAN NUYS, CA 91401

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/24/2019 Approved MARK JOHNSON
Footing/Foundation/Slab 9/13/2019 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 9/19/2019 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 10/1/2019 No Access for Inspection MARK JOHNSON
Footing/Foundation/Slab 10/3/2019 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 11/15/2019 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 12/3/2019 Partial Inspection MARK JOHNSON
Green Building Rough 12/3/2019 Not Ready for Inspection MARK JOHNSON
Verify Sprinkler Sign Off 12/3/2019 Not Ready for Inspection MARK JOHNSON
Underground Mechanical 1/3/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 1/31/2020 Not Ready for Inspection MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 1/31/2020 Partial Approval MARK JOHNSON
Green Building Rough 1/31/2020 Not Ready for Inspection MARK JOHNSON
Verify Sprinkler Sign Off 1/31/2020 Not Ready for Inspection MARK JOHNSON
Wood Frame 3/4/2020 Partial Approval MARK JOHNSON
Interior/Exterior Lathing 3/10/2020 Approved MARK JOHNSON
Rough-Elec/Plmb/HVAC 3/10/2020 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 3/19/2020 Approved MARK JOHNSON
Green Building Rough 3/19/2020 Approved MARK JOHNSON
Rough-Elec/Plmb/HVAC 3/19/2020 Approved MARK JOHNSON
Insulation 3/25/2020 Approved MARK JOHNSON
Drywall Nailing 4/24/2020 Approved MARK JOHNSON
ELECTRICAL-Final 6/26/2024 Partial Inspection JAVIER RAMOS JR
Final 6/26/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 6/26/2024 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/26/2024 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 6/26/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 6/26/2024 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 9/4/2024 Approved JAVIER RAMOS JR
Final 9/4/2024 Partial Inspection JAVIER RAMOS JR
Green Building Final 9/4/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 9/4/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 9/4/2024 Approved JAVIER RAMOS JR
Smoke Detectors 9/4/2024 Approved JAVIER RAMOS JR