6859 N HAZELTINE AVE 110 91405

Certificate Information: 6859 N HAZELTINE AVE 110 91405

Application / Permit
18010-20000-02837
Plan Check / Job No.
B18VN09888
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 22'-5" x 30'-8" Three Story Single Family Dwelling with attached Two-Car Garage per Small Lot Subdivision pursuant to Vesting Tentative Tract Map No. 73885-SL. Certificate of Occupancy (Temporary or Final) shall not be issued until the final map has been recorded, Nfpa-13d fire spirnklers required throughout, all work per engineering
Permit Issued
Issued on 5/20/2024
Issuing Office
West Los Angeles
Current Status
Issued on 5/20/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/12/2018 APPLICANT
Green Plans Picked Up 7/30/2018 APPLICANT
Assigned to Plan Check Engineer 8/2/2018 OMID HEDAYAT
Corrections Issued 8/8/2018 OMID HEDAYAT
Quality Review Completed 8/10/2018 STEVEN KIM
Building Plans Picked Up 8/13/2018 APPLICANT
Applicant returned to address corrections 8/21/2018 OMID HEDAYAT
Applicant returned to address corrections 3/5/2019 OMID HEDAYAT
Applicant returned to address corrections 11/16/2023 RARES BODEA
Plan Check Approved 2/8/2024 RARES BODEA
Issued 5/20/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/9/2019 ADRIAN SANCHEZ
Low Impact Development Cleared 11/1/2019 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 11/1/2019 THOMAS LANG
Green Code Cleared 12/30/2020 OMID HEDAYAT
Sewer availability Cleared 4/27/2021 GUILLERMO PETRA
Hydrant and Access approval Cleared 7/1/2021 KURT CORRAL
Trees in Parkway Cleared 8/30/2022 RICHARD SANCHEZ
Miscellaneous Cleared 10/16/2022 STEVEN WECHSLER
Address approval Cleared 11/7/2022 COLIN LOREDO
Highway dedication Cleared 11/7/2022 COLIN LOREDO
Miscellaneous Cleared 11/7/2022 COLIN LOREDO
Permit Cleared 11/7/2022 COLIN LOREDO
"Q" conditions Cleared 4/19/2023 STEVEN WECHSLER
"T" removal Cleared 4/19/2023 STEVEN WECHSLER

Contact Information

Contractor S H Z Development Inc; Lic. No.: 899219-B 11030 SANTA MONICA BLVD   SUITE 301    LOS ANGELES, CA 90025
Engineer Jitechian, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504
Engineer Pirbadian, Amir; Lic. No.: C72413 5435 BALBOA BLVD 212      ENCINO, CA 91436

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/18/2024 Approved JEFFREY PARD
Pre-Inspection 8/5/2025 Approved JEFFREY PARD
PLUMBING-Rough 10/6/2025 Partial Approval JEFFREY PARD
PLUMBING-Rough 10/15/2025 Not Ready for Inspection JEFFREY PARD
Footing/Foundation/Slab 10/17/2025 Not Ready for Inspection JEFFREY PARD
Footing/Foundation/Slab 10/27/2025 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 12/4/2025 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Partial Approval HENRY KIM
Interior/Exterior Lathing 12/8/2025 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Partial Approval JEFFREY PARD
Special/Order Compliance 12/10/2025 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Partial Approval JEFFREY PARD
Deputy Wood Construction 12/19/2025 Approved JEFFREY PARD
Deck 1/16/2026 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 1/16/2026 Partial Approval JEFFREY PARD
Interior/Exterior Lathing 1/21/2026 Partial Approval HENRY KIM
Special/Order Compliance 2/4/2026 Partial Approval JEFFREY PARD
Wood Frame 2/4/2026 Partial Approval JEFFREY PARD
Deputy Wood Construction 2/10/2026 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/19/2026 Partial Approval JEFFREY PARD
Wood Frame 2/19/2026 Partial Approval JEFFREY PARD
Interior/Exterior Lathing 2/23/2026 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 3/6/2026 Partial Approval JEFFREY PARD
PLUMBING-Rough 3/17/2026 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 3/19/2026 Partial Approval JEFFREY PARD
Special/Order Compliance 3/25/2026 Approved JEFFREY PARD
Wood Frame 3/25/2026 Approved JEFFREY PARD
Deputy Wood Construction 3/27/2026 Approved JEFFREY PARD
Gas Test 4/2/2026 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 4/2/2026 Partial Approval JEFFREY PARD
PLUMBING-Rough 4/15/2026 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 4/21/2026 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/21/2026 Approved JEFFREY PARD
HVAC-Rough 4/22/2026 Approved JEFFREY PARD
Shower Pan 4/22/2026 Approved JEFFREY PARD
ELECTRICAL-Rough 4/23/2026 Approved JEFFREY PARD
Insulation 4/27/2026 Partial Approval JEFFREY PARD
Interior/Exterior Lathing 4/28/2026 Approved JEFFREY PARD
BUILDING-Rough-Frame 4/30/2026 Approved JEFFREY PARD
Green Building Rough 4/30/2026 Approved JEFFREY PARD
PLUMBING-Rough 4/30/2026 Approved JEFFREY PARD
Verify Sprinkler Sign Off 4/30/2026 Approved JEFFREY PARD
Insulation 5/1/2026 Approved JEFFREY PARD
Drywall Nailing 5/13/2026 Approved JEFFREY PARD
Interior/Exterior Lathing 5/27/2026 Approved JEFFREY PARD
Gas Test 6/3/2026 Partial Approval JEFFREY PARD