7009 N MOONLIGHT LANE 91405

Certificate Information: 7009 N MOONLIGHT LANE 91405

Application / Permit
18010-20000-02806
Plan Check / Job No.
B18VN09852
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW 66'9"X39'7" 2-STORY SFD W/ ATTACHED 2-CAR GARAGE. SEE COMMENTS. (3 OF 3)
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
CofO Issued on 6/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2018 APPLICANT
Green Plans Picked Up 7/20/2018 APPLICANT
Assigned to Plan Check Engineer 8/2/2018 HAYATO TSUCHIYA
Corrections Issued 8/21/2018 HAYATO TSUCHIYA
Quality Review Completed 8/23/2018 ABDUL CHEGENI
Applicant returned to address corrections 5/14/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 5/15/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 9/1/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 9/3/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/21/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/23/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/27/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 12/22/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 12/23/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 3/10/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 3/12/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 3/18/2021 HAYATO TSUCHIYA
Plan Check Approved 4/9/2021 HAYATO TSUCHIYA
Issued 4/12/2021 APPLICANT
Building Plans Picked Up 4/16/2021 APPLICANT
CofO in Progress 6/9/2023 RYAN SALAZAR
Permit Finaled 6/15/2023 MICHAEL SMITH
CofO Issued 6/15/2023 MICHAEL SMITH
Permit Finaled 6/15/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/6/2018 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/6/2018 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 1/2/2019 MITESH PATEL
Private street Cleared 5/21/2019 RINA LARA
Tract Map conditions Cleared 5/21/2019 RINA LARA
Highway dedication Cleared 5/23/2019 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 5/23/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 7/9/2019 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 7/16/2019 CELINA MORENO
Address approval Cleared 10/8/2020 HOWARD COOPER
Green Code Cleared 11/19/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Vidal, Juan Alonso; Lic. No.: GE861 15331 DOGWOOD ST      WESTMINSTER, CA 92683

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/21/2021 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 4/21/2021 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 4/27/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/27/2021 Partial Approval JENNIFER RABUCHIN
Structural Steel Frame 4/27/2021 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 5/6/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/14/2021 Approved MICHEL ABAJAN
Deputy Reinf. Concrete 5/25/2021 Approved KRISTEN CAUSEY
Deputy Steel/Welding 6/10/2021 Conditional Approval MORRIS JACKSON
Structural Steel Frame 6/22/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Partial Approval MICHEL ABAJAN
Wood Frame 7/26/2021 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 8/23/2021 Not Ready for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Partial Approval RICHARD DOCKUS
HVAC-Rough 8/27/2021 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 9/16/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 9/16/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 9/17/2021 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 9/17/2021 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 9/17/2021 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 9/17/2021 Approved RICHARD DOCKUS
ELECTRICAL-Rough 9/22/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 10/1/2021 Not Ready for Inspection MARK JOHNSON
Shower Pan 10/1/2021 Corrections Issued MARK JOHNSON
Shower Pan 10/4/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/25/2021 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 10/25/2021 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 10/25/2021 Not Ready for Inspection RICHARD DOCKUS
Deputy Drilled-In Anchors 10/26/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Approved RICHARD DOCKUS
Wood Frame 10/28/2021 Corrections Issued RICHARD DOCKUS
Insulation 11/1/2021 Approved RICHARD DOCKUS
Wood Frame 11/1/2021 Approved RICHARD DOCKUS
Drywall Nailing 11/5/2021 Approved RICHARD DOCKUS
HVAC-Rough 2/23/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 2/23/2022 Approved RICHARD DOCKUS
Underground Mechanical 2/23/2022 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 2/28/2022 Partial Approval RICHARD DOCKUS
Underground Mechanical 2/28/2022 Partial Approval RICHARD DOCKUS
Sewer 9/2/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 10/19/2022 Corrections Issued ROBERT GOLD
HVAC-Final 10/19/2022 Not Ready for Inspection ROBERT GOLD
PLUMBING-Final 10/19/2022 Corrections Issued ROBERT GOLD
ELECTRICAL-Final 10/26/2022 Approved RICHARD DOCKUS
PLUMBING-Final 10/26/2022 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 11/15/2022 No Access for Inspection RICHARD DOCKUS
ELECTRICAL-Final 11/15/2022 No Access for Inspection RICHARD DOCKUS
Final 11/15/2022 No Access for Inspection RICHARD DOCKUS
Green Building Final 11/15/2022 No Access for Inspection RICHARD DOCKUS
HVAC-Final 11/15/2022 No Access for Inspection RICHARD DOCKUS
PLUMBING-Final 11/15/2022 No Access for Inspection RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Not Ready RICHARD DOCKUS
Service/Power Release 11/15/2022 No Access for Inspection RICHARD DOCKUS
Smoke Detectors 11/15/2022 No Access for Inspection RICHARD DOCKUS
Final 4/3/2023 Corrections Issued RYAN SALAZAR
Gas Test 4/3/2023 Approved RYAN SALAZAR
HVAC-Final 4/14/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 6/8/2023 Approved RYAN SALAZAR
Final 6/8/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 6/8/2023 Approved RYAN SALAZAR
PLUMBING-Final 6/8/2023 Approved RYAN SALAZAR
Pool/Spa Cover 6/8/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/8/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 6/8/2023 Approved RYAN SALAZAR
Smoke Detectors 6/8/2023 Approved RYAN SALAZAR