14950 W VOSE ST 91405

Certificate Information: 14950 W VOSE ST 91405

Application / Permit
18010-20000-02804
Plan Check / Job No.
B18VN09852
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW 60'3"X52' 2-STORY SFD W/ ATTACHED 2-CAR GARAGE. SEE COMMENTS (1 OF 3)
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofO Issued on 6/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2018 APPLICANT
Green Plans Picked Up 7/20/2018 APPLICANT
Assigned to Plan Check Engineer 8/2/2018 HAYATO TSUCHIYA
Corrections Issued 8/21/2018 HAYATO TSUCHIYA
Quality Review Completed 8/23/2018 ABDUL CHEGENI
Applicant returned to address corrections 5/14/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 5/15/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 9/1/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 9/3/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/21/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/23/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/27/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 12/22/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 12/23/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 3/10/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 3/12/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 3/18/2021 HAYATO TSUCHIYA
Plan Check Approved 4/9/2021 HAYATO TSUCHIYA
Issued 4/15/2021 APPLICANT
Building Plans Picked Up 4/16/2021 APPLICANT
CofO in Progress 6/9/2023 RYAN SALAZAR
CofO in Progress 6/14/2023 ROBERT GOLD
No Progress 6/14/2023 ROBERT GOLD
CofO in Progress 6/23/2023 RYAN SALAZAR
Permit Finaled 6/27/2023 MICHAEL SMITH
CofO Issued 6/27/2023 MICHAEL SMITH
Permit Finaled 6/27/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/6/2018 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/6/2018 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 1/2/2019 MITESH PATEL
Private street Cleared 5/21/2019 RINA LARA
Tract Map conditions Cleared 5/21/2019 RINA LARA
Address approval Cleared 5/23/2019 APEKSHYA BAJRACHARYA
Highway dedication Cleared 5/23/2019 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 5/23/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 5/23/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 7/9/2019 GEORGE SUCHAND
Green Code Cleared 11/19/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Vidal, Juan Alonso; Lic. No.: GE861 15331 DOGWOOD ST      WESTMINSTER, CA 92683

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/27/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 4/29/2021 Approved JENNIFER RABUCHIN
Structural Steel Frame 4/29/2021 Not Ready for Inspection JENNIFER RABUCHIN
Deputy Steel/Welding 5/14/2021 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 5/27/2021 Partial Approval MARK JOHNSON
Green Building Rough 5/27/2021 Not Ready for Inspection MARK JOHNSON
Verify Sprinkler Sign Off 5/27/2021 Not Ready for Inspection MARK JOHNSON
Structural Steel Frame 6/2/2021 Partial Inspection MICHEL ABAJAN
Wood Frame 7/6/2021 Partial Approval ARTHUR SARGSYAN
Deputy Wood Construction 7/7/2021 Conditional Approval DEANDRE HOFFMAN
ELECTRICAL-Rough 7/8/2021 Approved ARTHUR SARGSYAN
HVAC-Rough 7/8/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 7/8/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 7/22/2021 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 7/22/2021 Not Ready for Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 7/22/2021 Not Ready for Inspection MICHEL ABAJAN
Shower Pan 7/27/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 7/30/2021 Approved JOHN HAYES
BUILDING-Rough-Frame 8/4/2021 Approved JOHN HAYES
Green Building Rough 8/4/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 8/4/2021 Approved JOHN HAYES
Verify Sprinkler Sign Off 8/4/2021 Approved JOHN HAYES
Interior/Exterior Lathing 8/23/2021 Not Ready for Inspection RICHARD DOCKUS
Drywall Nailing 8/25/2021 Corrections Issued RICHARD DOCKUS
Drywall Nailing 8/30/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 9/14/2021 Corrections Issued RICHARD DOCKUS
Interior/Exterior Lathing 9/16/2021 Partial Approval RICHARD DOCKUS
Gas Test 12/16/2021 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 2/23/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 2/23/2022 Approved RICHARD DOCKUS
Underground Mechanical 2/23/2022 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 3/1/2022 Partial Approval RICHARD DOCKUS
Underground Mechanical 3/1/2022 Partial Approval RICHARD DOCKUS
Masonry Wall/Backfill 4/8/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 5/31/2022 Corrections Issued RICHARD DOCKUS
Sewer 9/2/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 10/11/2022 Corrections Issued RICHARD DOCKUS
PLUMBING-Final 10/11/2022 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Final 10/19/2022 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 10/19/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 10/19/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 11/2/2022 Not Ready for Inspection RICHARD DOCKUS
Final 11/2/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 11/2/2022 Not Ready for Inspection RICHARD DOCKUS
HVAC-Final 11/2/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Final 11/2/2022 Not Ready for Inspection RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/2/2022 SGSOV Not Ready RICHARD DOCKUS
Service/Power Release 11/2/2022 Not Ready for Inspection RICHARD DOCKUS
Smoke Detectors 11/2/2022 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Final 11/8/2022 Approved JENNIFER RABUCHIN
Final 11/8/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/8/2022 Approved JENNIFER RABUCHIN
HVAC-Final 11/8/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 11/8/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/9/2022 No Access for Inspection RICHARD DOCKUS
HVAC-Final 11/9/2022 No Access for Inspection RICHARD DOCKUS
PLUMBING-Final 11/9/2022 No Access for Inspection RICHARD DOCKUS
Gas Test 4/3/2023 Approved RYAN SALAZAR
PLUMBING-Final 4/3/2023 Approved RYAN SALAZAR
HVAC-Final 4/13/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 6/8/2023 Approved RYAN SALAZAR
Final 6/8/2023 OK to Issue CofO RYAN SALAZAR
HVAC-Final 6/8/2023 Approved RYAN SALAZAR
PLUMBING-Final 6/8/2023 Approved RYAN SALAZAR
Pool/Spa Cover 6/8/2023 Approved RYAN SALAZAR
Service/Power Release 6/8/2023 Approved RYAN SALAZAR
Smoke Detectors 6/8/2023 Approved RYAN SALAZAR
Final 6/21/2023 OK to Issue CofO RYAN SALAZAR