14950 W VOSE ST 91405
Certificate Information: 14950 W VOSE ST 91405
- Application / Permit
- 18010-20000-02804
- Plan Check / Job No.
- B18VN09852
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED NEW 60'3"X52' 2-STORY SFD W/ ATTACHED 2-CAR GARAGE. SEE COMMENTS (1 OF 3)
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Current Status
- CofO Issued on 6/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2018 | APPLICANT |
| Green Plans Picked Up | 7/20/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2018 | HAYATO TSUCHIYA |
| Corrections Issued | 8/21/2018 | HAYATO TSUCHIYA |
| Quality Review Completed | 8/23/2018 | ABDUL CHEGENI |
| Applicant returned to address corrections | 5/14/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 5/15/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/1/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/3/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 10/21/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 10/23/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 10/27/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 12/22/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 12/23/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 3/10/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 3/12/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 3/18/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 4/9/2021 | HAYATO TSUCHIYA |
| Issued | 4/15/2021 | APPLICANT |
| Building Plans Picked Up | 4/16/2021 | APPLICANT |
| CofO in Progress | 6/9/2023 | RYAN SALAZAR |
| CofO in Progress | 6/14/2023 | ROBERT GOLD |
| No Progress | 6/14/2023 | ROBERT GOLD |
| CofO in Progress | 6/23/2023 | RYAN SALAZAR |
| Permit Finaled | 6/27/2023 | MICHAEL SMITH |
| CofO Issued | 6/27/2023 | MICHAEL SMITH |
| Permit Finaled | 6/27/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2018 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 12/6/2018 | APEKSHYA BAJRACHARYA |
| Low Impact Development | Cleared | 1/2/2019 | MITESH PATEL |
| Private street | Cleared | 5/21/2019 | RINA LARA |
| Tract Map conditions | Cleared | 5/21/2019 | RINA LARA |
| Address approval | Cleared | 5/23/2019 | APEKSHYA BAJRACHARYA |
| Highway dedication | Cleared | 5/23/2019 | APEKSHYA BAJRACHARYA |
| Miscellaneous | Cleared | 5/23/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 5/23/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 7/9/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 11/19/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
| Engineer | Vidal, Juan Alonso; Lic. No.: GE861 | 15331 DOGWOOD ST WESTMINSTER, CA 92683 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/27/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 4/29/2021 | Approved | JENNIFER RABUCHIN |
| Structural Steel Frame | 4/29/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Deputy Steel/Welding | 5/14/2021 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 5/27/2021 | Partial Approval | MARK JOHNSON |
| Green Building Rough | 5/27/2021 | Not Ready for Inspection | MARK JOHNSON |
| Verify Sprinkler Sign Off | 5/27/2021 | Not Ready for Inspection | MARK JOHNSON |
| Structural Steel Frame | 6/2/2021 | Partial Inspection | MICHEL ABAJAN |
| Wood Frame | 7/6/2021 | Partial Approval | ARTHUR SARGSYAN |
| Deputy Wood Construction | 7/7/2021 | Conditional Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 7/8/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 7/8/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 7/8/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 7/22/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 7/22/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 7/22/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Shower Pan | 7/27/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Shower Pan | 7/30/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/4/2021 | Approved | JOHN HAYES |
| Green Building Rough | 8/4/2021 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 8/4/2021 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 8/4/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/23/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Drywall Nailing | 8/25/2021 | Corrections Issued | RICHARD DOCKUS |
| Drywall Nailing | 8/30/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 9/14/2021 | Corrections Issued | RICHARD DOCKUS |
| Interior/Exterior Lathing | 9/16/2021 | Partial Approval | RICHARD DOCKUS |
| Gas Test | 12/16/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 2/23/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 2/23/2022 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 2/23/2022 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 3/1/2022 | Partial Approval | RICHARD DOCKUS |
| Underground Mechanical | 3/1/2022 | Partial Approval | RICHARD DOCKUS |
| Masonry Wall/Backfill | 4/8/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 5/31/2022 | Corrections Issued | RICHARD DOCKUS |
| Sewer | 9/2/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 10/11/2022 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Final | 10/11/2022 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Final | 10/19/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 10/19/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 10/19/2022 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 11/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 11/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Final | 11/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 11/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Service/Power Release | 11/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 11/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 11/8/2022 | Approved | JENNIFER RABUCHIN |
| Final | 11/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/8/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/8/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/9/2022 | No Access for Inspection | RICHARD DOCKUS |
| HVAC-Final | 11/9/2022 | No Access for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 11/9/2022 | No Access for Inspection | RICHARD DOCKUS |
| Gas Test | 4/3/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 4/3/2023 | Approved | RYAN SALAZAR |
| HVAC-Final | 4/13/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 6/8/2023 | Approved | RYAN SALAZAR |
| Final | 6/8/2023 | OK to Issue CofO | RYAN SALAZAR |
| HVAC-Final | 6/8/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 6/8/2023 | Approved | RYAN SALAZAR |
| Pool/Spa Cover | 6/8/2023 | Approved | RYAN SALAZAR |
| Service/Power Release | 6/8/2023 | Approved | RYAN SALAZAR |
| Smoke Detectors | 6/8/2023 | Approved | RYAN SALAZAR |
| Final | 6/21/2023 | OK to Issue CofO | RYAN SALAZAR |