10849 N KEWEN AVE 91331
Certificate Information: 10849 N KEWEN AVE 91331
- Application / Permit
- 18010-20000-02706
- Plan Check / Job No.
- B18VN09542
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25' 5" X 35' 1-STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK DONE PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 6/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2018 | APPLICANT |
| Green Plans Picked Up | 7/9/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2018 | GURUNATH NESARAJAH |
| Corrections Issued | 7/31/2018 | GURUNATH NESARAJAH |
| Quality Review Completed | 8/10/2018 | STEVEN KIM |
| Building Plans Picked Up | 8/22/2018 | APPLICANT |
| Plan Check Approved | 3/5/2020 | GURUNATH NESARAJAH |
| Issued | 6/9/2020 | LADBS |
| CofO in Progress | 4/21/2021 | MICHEL ABAJAN |
| CofO in Progress | 4/21/2021 | MICHEL ABAJAN |
| Permit Finaled | 6/19/2021 | MICHAEL SMITH |
| CofO Issued | 6/19/2021 | MICHAEL SMITH |
| Permit Finaled | 6/19/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 7/24/2018 | PARISA ZAHABI |
| Address approval | Cleared | 6/6/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 6/6/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 6/13/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 2/28/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 3/3/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/27/2020 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 7/27/2020 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 7/27/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/6/2020 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 8/6/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 8/6/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 8/6/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 8/6/2020 | Partial Approval | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 8/6/2020 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2020 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/27/2020 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/27/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 8/27/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 8/27/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/27/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 8/27/2020 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/4/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/4/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/4/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 9/4/2020 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 9/4/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/4/2020 | Approved | MICHEL ABAJAN |
| Insulation | 9/16/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/16/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/25/2020 | Approved | MICHEL ABAJAN |
| Final | 2/4/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 2/4/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Final | 2/4/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/4/2021 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 2/4/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 2/4/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/3/2021 | Approved | MICHEL ABAJAN |
| Final | 3/3/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 3/3/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 3/3/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/3/2021 | Approved | MICHEL ABAJAN |
| Service/Power Release | 3/3/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 4/14/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/14/2021 | Approved | MICHEL ABAJAN |
| Service/Power Release | 4/14/2021 | Approved | MICHEL ABAJAN |
| Final | 4/20/2021 | OK to Issue CofO | MICHEL ABAJAN |