4464 N MATILIJA AVE 91423

Certificate Information: 4464 N MATILIJA AVE 91423

Application / Permit
18010-20000-02642
Plan Check / Job No.
B18VN09305
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 48'-0" x 86'-6" irregular shape Two-Story Single Family Dwelling with attached Two-Car Garage, Type VB Construction.
Permit Issued
Issued on 11/20/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2018 APPLICANT
Green Plans Picked Up 7/6/2018 APPLICANT
Assigned to Plan Check Engineer 7/26/2018 OMID HEDAYAT
Corrections Issued 8/2/2018 OMID HEDAYAT
Quality Review Completed 8/7/2018 GUANG MIN TUNG
Building Plans Picked Up 8/8/2018 APPLICANT
Applicant returned to address corrections 10/29/2018 OMID HEDAYAT
Plan Check Approved 10/29/2018 OMID HEDAYAT
Issued 11/20/2019 LADBS
CofO in Progress 6/8/2023 ROBERT GOLD
No Progress 6/8/2023 ROBERT GOLD
CofO in Progress 6/8/2023 ROBERT GOLD
CofO in Progress 6/13/2023 ROBERT GOLD
Permit Finaled 6/15/2023 MICHAEL SMITH
CofO Issued 6/15/2023 MICHAEL SMITH
Permit Finaled 6/15/2023 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 8/30/2018 JORGE MEJIA LEMUS
Address approval Cleared 9/7/2018 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 9/7/2018 JOHN LIN
Hydrant and Access approval Cleared 9/7/2018 JOHN DALLAS
Permit Cleared 9/7/2018 JOHN LIN
Roof/Waste drainage to street Cleared 9/7/2018 JOHN LIN
Sewer availability Cleared 9/7/2018 JOHN LIN
Green Code Cleared 9/21/2018 MICHAEL AYERS
ZI Cleared 9/21/2018 TOM HENRY
Trees in Parkway Cleared 10/26/2018 LUIS TORRES

Contact Information

Architect Valentine, Janev; Lic. No.: C19379       ,
Contractor Mr Build Solar Electric; Lic. No.: 439166-B 9238 W PICO BLVD      LOS ANGELES, CA 90035
Engineer Yuzon, Benigno S Jr; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/16/2020 Approved CHARLES POWELL
PLUMBING-Rough 12/1/2020 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 12/10/2020 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 12/16/2020 Approved CHARLES POWELL
Deputy Reinf. Concrete 12/17/2020 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 5/3/2021 Not Ready for Inspection CHARLES POWELL
Green Building Rough 5/3/2021 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 5/3/2021 Not Ready for Inspection CHARLES POWELL
Green Building Rough 6/15/2021 Not Ready for Inspection CHARLES POWELL
Pre-Inspection 6/15/2021 Partial Approval CHARLES POWELL
Verify Sprinkler Sign Off 6/15/2021 Not Ready for Inspection CHARLES POWELL
Deputy Wood Construction 6/17/2021 Approved ALAN MORELOS
Underground Mechanical 7/27/2021 Partial Approval CHARLES POWELL
Underground Mechanical 8/4/2021 Approved CHARLES POWELL
HVAC-Rough 9/7/2021 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 9/7/2021 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 9/9/2021 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 11/1/2021 Approved MICHAEL PELHAM
HVAC-Rough 11/1/2021 Partial Approval MICHAEL PELHAM
Pre-Inspection 11/1/2021 Partial Inspection MICHAEL PELHAM
ELECTRICAL-Rough 11/5/2021 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 12/13/2021 Conditional Approval MISAEL ESPARZA
ELECTRICAL-Rough 12/13/2021 Approved MISAEL ESPARZA
Green Building Rough 12/13/2021 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 12/13/2021 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 12/13/2021 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 12/13/2021 Approved MISAEL ESPARZA
Insulation 12/17/2021 Corrections Issued ASHLEY THOMPSON
Shower Pan 12/17/2021 Partial Inspection ASHLEY THOMPSON
Insulation 12/20/2021 Approved ASHLEY THOMPSON
Shower Pan 12/20/2021 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 12/29/2021 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 1/7/2022 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 1/7/2022 Approved MISAEL ESPARZA
Shower Pan 1/7/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 5/3/2022 Approved MISAEL ESPARZA
Wood Frame 5/13/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/11/2023 Approved MISAEL ESPARZA
Final 4/11/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 4/11/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 4/11/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Approved MISAEL ESPARZA
Service/Power Release 4/11/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 4/11/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/18/2023 Approved MISAEL ESPARZA
HVAC-Final 4/18/2023 Approved MISAEL ESPARZA
PLUMBING-Final 4/18/2023 Approved MISAEL ESPARZA
Gas Test 5/5/2023 Corrections Issued MISAEL ESPARZA
Gas Test 5/12/2023 Partial Approval MICHEL ABAJAN
Final 6/7/2023 OK to Issue CofO ROBERT GOLD
Green Building Final 6/7/2023 Approved ROBERT GOLD
Service/Power Release 6/7/2023 Approved ROBERT GOLD