4464 N MATILIJA AVE 91423
Certificate Information: 4464 N MATILIJA AVE 91423
- Application / Permit
- 18010-20000-02642
- Plan Check / Job No.
- B18VN09305
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 48'-0" x 86'-6" irregular shape Two-Story Single Family Dwelling with attached Two-Car Garage, Type VB Construction.
- Permit Issued
- Issued on 11/20/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2018 | APPLICANT |
| Green Plans Picked Up | 7/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2018 | OMID HEDAYAT |
| Corrections Issued | 8/2/2018 | OMID HEDAYAT |
| Quality Review Completed | 8/7/2018 | GUANG MIN TUNG |
| Building Plans Picked Up | 8/8/2018 | APPLICANT |
| Applicant returned to address corrections | 10/29/2018 | OMID HEDAYAT |
| Plan Check Approved | 10/29/2018 | OMID HEDAYAT |
| Issued | 11/20/2019 | LADBS |
| CofO in Progress | 6/8/2023 | ROBERT GOLD |
| No Progress | 6/8/2023 | ROBERT GOLD |
| CofO in Progress | 6/8/2023 | ROBERT GOLD |
| CofO in Progress | 6/13/2023 | ROBERT GOLD |
| Permit Finaled | 6/15/2023 | MICHAEL SMITH |
| CofO Issued | 6/15/2023 | MICHAEL SMITH |
| Permit Finaled | 6/15/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/30/2018 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 9/7/2018 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2018 | JOHN LIN |
| Hydrant and Access approval | Cleared | 9/7/2018 | JOHN DALLAS |
| Permit | Cleared | 9/7/2018 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 9/7/2018 | JOHN LIN |
| Sewer availability | Cleared | 9/7/2018 | JOHN LIN |
| Green Code | Cleared | 9/21/2018 | MICHAEL AYERS |
| ZI | Cleared | 9/21/2018 | TOM HENRY |
| Trees in Parkway | Cleared | 10/26/2018 | LUIS TORRES |
Contact Information
| Architect | Valentine, Janev; Lic. No.: C19379 | , |
| Contractor | Mr Build Solar Electric; Lic. No.: 439166-B | 9238 W PICO BLVD LOS ANGELES, CA 90035 |
| Engineer | Yuzon, Benigno S Jr; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/16/2020 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 12/1/2020 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 12/10/2020 | Not Ready for Inspection | CHARLES POWELL |
| Footing/Foundation/Slab | 12/16/2020 | Approved | CHARLES POWELL |
| Deputy Reinf. Concrete | 12/17/2020 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 5/3/2021 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Rough | 5/3/2021 | Not Ready for Inspection | CHARLES POWELL |
| Verify Sprinkler Sign Off | 5/3/2021 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Rough | 6/15/2021 | Not Ready for Inspection | CHARLES POWELL |
| Pre-Inspection | 6/15/2021 | Partial Approval | CHARLES POWELL |
| Verify Sprinkler Sign Off | 6/15/2021 | Not Ready for Inspection | CHARLES POWELL |
| Deputy Wood Construction | 6/17/2021 | Approved | ALAN MORELOS |
| Underground Mechanical | 7/27/2021 | Partial Approval | CHARLES POWELL |
| Underground Mechanical | 8/4/2021 | Approved | CHARLES POWELL |
| HVAC-Rough | 9/7/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 9/7/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Approved | MICHAEL PELHAM |
| HVAC-Rough | 11/1/2021 | Partial Approval | MICHAEL PELHAM |
| Pre-Inspection | 11/1/2021 | Partial Inspection | MICHAEL PELHAM |
| ELECTRICAL-Rough | 11/5/2021 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/13/2021 | Conditional Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/13/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 12/13/2021 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 12/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 12/13/2021 | Approved | MISAEL ESPARZA |
| Insulation | 12/17/2021 | Corrections Issued | ASHLEY THOMPSON |
| Shower Pan | 12/17/2021 | Partial Inspection | ASHLEY THOMPSON |
| Insulation | 12/20/2021 | Approved | ASHLEY THOMPSON |
| Shower Pan | 12/20/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 12/29/2021 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 1/7/2022 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 1/7/2022 | Approved | MISAEL ESPARZA |
| Shower Pan | 1/7/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 5/3/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 5/13/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | MISAEL ESPARZA |
| Final | 4/11/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 4/11/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 4/11/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/11/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 4/11/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 4/11/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 4/18/2023 | Approved | MISAEL ESPARZA |
| HVAC-Final | 4/18/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 4/18/2023 | Approved | MISAEL ESPARZA |
| Gas Test | 5/5/2023 | Corrections Issued | MISAEL ESPARZA |
| Gas Test | 5/12/2023 | Partial Approval | MICHEL ABAJAN |
| Final | 6/7/2023 | OK to Issue CofO | ROBERT GOLD |
| Green Building Final | 6/7/2023 | Approved | ROBERT GOLD |
| Service/Power Release | 6/7/2023 | Approved | ROBERT GOLD |