11753 W WETHERBY LANE 90077
Certificate Information: 11753 W WETHERBY LANE 90077
- Application / Permit
- 18010-20000-02459
- Plan Check / Job No.
- B18VN08855
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (N) (84'-4" X 71') IRREGULAR SHAPED SFD W/ ATT 3-CAR GARAGE PER ENGINEERING. NFPA 13D SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 4/3/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2018 | RAPHAEL ROSAS |
| Corrections Issued | 6/16/2018 | RAPHAEL ROSAS |
| Quality Review Completed | 6/20/2018 | STEVEN KIM |
| Building Plans Picked Up | 6/21/2018 | APPLICANT |
| Green Plans Picked Up | 6/21/2018 | APPLICANT |
| Applicant returned to address corrections | 10/30/2018 | RAPHAEL ROSAS |
| Plan Check Approved | 4/2/2019 | RAPHAEL ROSAS |
| Issued | 4/3/2019 | LADBS |
| CofO in Progress | 7/22/2021 | CARLOS MATAMOROS |
| CofO Issued | 8/9/2021 | VINCENT COTTON |
| Permit Finaled | 8/9/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2018 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 8/1/2018 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 8/1/2018 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 8/1/2018 | MARKOS PEREZ-BRAN |
| Permit | Cleared | 8/1/2018 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 10/9/2018 | DAVID MATSON |
| Low Impact Development | Cleared | 3/12/2019 | MITESH PATEL |
| Private street | Cleared | 3/12/2019 | RICK TORRES |
| Tract Map conditions | Cleared | 3/12/2019 | RICK TORRES |
| Distance to fire station | Cleared | 3/13/2019 | JOHN DALLAS |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2019 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/13/2019 | JOHN DALLAS |
| Roof/Waste drainage to street | Cleared | 3/13/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/13/2019 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 3/21/2019 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 3/21/2019 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Walter, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
| Engineer | Yuzon, Benigno S Jr; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
| Geologist | Pedram, Rahimikian; Lic. No.: EG2683 | , |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/4/2020 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 2/13/2020 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/13/2020 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 2/14/2020 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2020 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2020 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 5/28/2020 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2020 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 6/15/2020 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 6/15/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 7/6/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/13/2020 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/13/2020 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 7/13/2020 | Partial Approval | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 7/13/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2020 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 7/15/2020 | Approved | CARLOS MATAMOROS |
| Wood Frame | 7/15/2020 | Approved | CARLOS MATAMOROS |
| Insulation | 7/21/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 7/30/2020 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 7/30/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 7/30/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/31/2020 | Approved | CARLOS MATAMOROS |
| Shower Pan | 8/31/2020 | Approved | CARLOS MATAMOROS |
| Gas Test | 3/25/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 6/15/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 6/21/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 6/22/2021 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 6/23/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 7/1/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/22/2021 | Approved | CARLOS MATAMOROS |
| Final | 7/22/2021 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 7/22/2021 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 7/22/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 7/22/2021 | Approved | CARLOS MATAMOROS |