17361 W ROSCOE BLVD 91325
Certificate Information: 17361 W ROSCOE BLVD 91325
- Application / Permit
- 18010-20000-02403
- Plan Check / Job No.
- B18VN08651
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 100'9" x 239'4" (IRR. SHAPE) SENIOR CITIZEN APARTMENT BUILDING WITH ATTACHED PATIO COVER AND OPEN PARKING LOT. 53 UNITS, 3-STORY; PER CPC-2015-3215-CU-ZV-ZAA-SPR
- Permit Issued
- Issued on 11/7/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2018 | JEFFREY TANGONAN |
| Corrections Issued | 7/20/2018 | JEFFREY TANGONAN |
| Disabled Access Plans Picked Up | 7/25/2018 | APPLICANT |
| Green Plans Picked Up | 7/25/2018 | APPLICANT |
| Quality Review Completed | 7/26/2018 | CHON CHIO KUO |
| Applicant returned to address corrections | 1/7/2019 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 3/6/2019 | JEFFREY TANGONAN |
| Plan Check Approved | 7/5/2019 | JEFFREY TANGONAN |
| Issued | 11/7/2019 | LADBS |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| TCO Issued (Expire Date: 02-21-2023) | 8/25/2022 | JEFFREY DURAN |
| TCO Issued (Expire Date: 08-22-2023) | 2/23/2023 | JEFFREY DURAN |
| CofO in Progress | 9/22/2023 | JEFFREY DURAN |
| Permit Finaled | 9/25/2023 | RICKEY JACKSON |
| CofO Issued | 9/25/2023 | RICKEY JACKSON |
| Permit Finaled | 9/25/2023 | RICKEY JACKSON |
Permit Application Clearance Information
| CPC | Cleared | 8/20/2018 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 8/20/2018 | STEVEN WECHSLER |
| Address approval | Cleared | 11/8/2018 | RUDY TERRIQUEZ. |
| Miscellaneous | Cleared | 11/8/2018 | RUDY TERRIQUEZ. |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2018 | KAYLA PEJI |
| Sewer availability | Cleared | 11/9/2018 | KAYLA PEJI |
| Green Code | Cleared | 2/21/2019 | MICHAEL AYERS |
| Fire Marshall Fire Life Safety | Cleared | 3/1/2019 | OSCAR SALGADO JR |
| Driveway location | Cleared | 3/7/2019 | KEN AITCHISON |
| Hydrant and Access approval | Cleared | 3/7/2019 | GILBERT URREA |
| Internal circulation | Cleared | 3/7/2019 | KEN AITCHISON |
| ZA Case | Cleared | 3/7/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 3/7/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 3/7/2019 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 3/11/2019 | ANDRES COVARRUBIAS |
| Highway dedication | Cleared | 3/14/2019 | MARKOS PEREZ-BRAN |
| Permit | Cleared | 4/2/2019 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 4/8/2019 | LEE GUILBEAUX |
| Frnt yard landscape/Water mgmt | Cleared | 4/9/2019 | HERMINIGILDO AGUSTIN |
| DAS Clearance | Cleared | 4/29/2019 | JEFFREY TANGONAN |
| Construction near power lines | Cleared | 5/15/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/15/2019 | RIDWAN HARDY |
| CPC | Cleared | 6/11/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 6/11/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 6/11/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 6/11/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 6/11/2019 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 6/11/2019 | STEVEN WECHSLER |
| Opn space landscape/Water mgmt | Cleared | 6/11/2019 | STEVEN WECHSLER |
| Prkng lot landscape/Water mgmt | Cleared | 6/11/2019 | STEVEN WECHSLER |
| Site Plan review | Cleared | 6/11/2019 | STEVEN WECHSLER |
Contact Information
| Contractor | Aster Construction Services; Lic. No.: 976915-B | 1666 1/2 MCCADDEN PLACE LOS ANGELES, CA 90028 |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
| Engineer | Wahba,, Wahba Faris; Lic. No.: C33667 | 10041 SYLVIA AVE NORTHRIDGE, CA 91324 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/12/2019 | Not Ready for Inspection | ROBERT COLE |
| Pre-Inspection | 11/12/2019 | Partial Inspection | ROBERT COLE |
| Grading Pre-Inspection | 11/22/2019 | Not Ready for Inspection | ROBERT COLE |
| Piling/Pier/Caisson | 4/1/2020 | Partial Inspection | ROBERT COLE |
| Deputy Steel/Welding | 4/30/2020 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 5/8/2020 | Corrections Issued | ROBERT COLE |
| Deputy Reinf. Concrete | 6/2/2020 | Conditional Approval | ROBERT COLE |
| Footing/Foundation/Slab | 6/2/2020 | Partial Approval | ROBERT COLE |
| Reinforced Concrete Frame | 6/2/2020 | Partial Approval | ROBERT COLE |
| Deputy Steel/Welding | 7/2/2020 | Conditional Approval | ROBERT COLE |
| Footing/Foundation/Slab | 7/2/2020 | Partial Approval | ROBERT COLE |
| Deputy Steel/Welding | 7/7/2020 | Conditional Approval | ROBERT COLE |
| Deputy Steel/Welding | 7/28/2020 | No Result Entered | ROBERT COLE |
| Light Gage Steel Frame | 8/28/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Drilled-In Anchors | 9/2/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 9/2/2020 | Conditional Approval | JEFFREY DURAN |
| Light Gage Steel Frame | 9/3/2020 | Not Ready for Inspection | HAMID PISHEHVAR |
| Deputy Steel/Welding | 9/8/2020 | Conditional Approval | RICKEY JACKSON |
| Light Gage Steel Frame | 9/8/2020 | Partial Approval | HAMID PISHEHVAR |
| Pre-Inspection | 9/23/2020 | Corrections Issued | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 10/7/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 10/14/2020 | Partial Approval | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 10/14/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 10/21/2020 | Partial Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 10/21/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 10/28/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 12/3/2020 | Corrections Issued | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 12/7/2020 | Conditional Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 1/11/2021 | Approved | HAMID PISHEHVAR |
| Light Gage Steel Frame | 1/25/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Pre-Inspection | 3/5/2021 | Partial Approval | DANNY RODRIGUEZ |
| Pre-Inspection | 3/10/2021 | No Access for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 3/11/2021 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 3/12/2021 | Conditional Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 3/12/2021 | Partial Approval | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 3/18/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 3/23/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 3/25/2021 | Partial Approval | JOHN KITCKO |
| Pre-Inspection | 3/25/2021 | Partial Approval | JOHN KITCKO |
| Light Gage Steel Frame | 3/31/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2021 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 4/5/2021 | Approved | HAMID PISHEHVAR |
| Pre-Inspection | 4/5/2021 | Approved | HAMID PISHEHVAR |
| Green Building Rough | 4/9/2021 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 4/9/2021 | Off-Hour Fees Due | |
| Green Building Rough | 4/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 4/10/2021 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 4/10/2021 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 4/10/2021 | Partial Approval | DANNY RODRIGUEZ |
| Structural Steel Frame | 4/12/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Insulation | 4/24/2021 | Partial Approval | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 4/28/2021 | Approved | HAMID PISHEHVAR |
| Pre-Inspection | 4/28/2021 | Approved | HAMID PISHEHVAR |
| Drywall Nailing | 5/13/2021 | Approved | HAMID PISHEHVAR |
| Insulation | 5/13/2021 | Approved | HAMID PISHEHVAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 6/11/2021 | Partial Approval | JOE VELASQUEZ |
| Insulation | 7/1/2021 | Partial Approval | KENNETH ROBERTS |
| Verify Sprinkler Sign Off | 7/1/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Wood Frame | 7/1/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Insulation | 7/7/2021 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 7/9/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Interior/Exterior Lathing | 7/13/2021 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 7/22/2021 | Approved | DANIEL VARNUM |
| Drywall Nailing | 7/29/2021 | Partial Approval | DANIEL VARNUM |
| Insulation | 7/29/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 7/29/2021 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 8/4/2021 | No Access for Inspection | DANIEL VARNUM |
| Pre-Inspection | 8/4/2021 | No Access for Inspection | DANIEL VARNUM |
| Insulation | 8/6/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Pre-Inspection | 8/6/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Insulation | 8/10/2021 | Partial Approval | KENNETH ROBERTS |
| Insulation | 8/25/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Insulation | 8/26/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 8/27/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 8/31/2021 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 9/2/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 9/7/2021 | Partial Approval | RICKEY JACKSON |
| Light Gage Steel Frame | 9/13/2021 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 9/15/2021 | No Access for Inspection | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 9/15/2021 | No Access for Inspection | DANIEL VARNUM |
| Wood Frame | 9/15/2021 | No Access for Inspection | DANIEL VARNUM |
| Green Building Rough | 9/17/2021 | Approved | JOHN DODGE |
| Verify Sprinkler Sign Off | 9/17/2021 | Partial Inspection | JOHN DODGE |
| Wood Frame | 9/17/2021 | Partial Approval | JOHN DODGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 9/23/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Wood Frame | 9/23/2021 | Corrections Issued | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 10/4/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 10/6/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 10/13/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 10/15/2021 | Partial Approval | DANNY RODRIGUEZ |
| Special/Order Compliance | 10/20/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| T-Bar Ceiling | 10/20/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 10/22/2021 | Partial Approval | DANNY RODRIGUEZ |
| Special/Order Compliance | 11/2/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/15/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/23/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 12/1/2021 | Approved | JEFF BYTHEWAY |
| Excavation/Setback/Form/Re-Bar | 1/25/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 2/7/2022 | Partial Inspection | DANIEL VARNUM |
| Final | 2/9/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 2/9/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 2/9/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 2/9/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 2/9/2022 | Partial Inspection | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 2/9/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 2/9/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Special/Order Compliance | 5/4/2022 | Partial Inspection | DANIEL VARNUM |
| Special/Order Compliance | 6/23/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 7/27/2022 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 7/27/2022 | Approved | DANIEL VARNUM |
| Green Building Final | 7/27/2022 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 7/27/2022 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 7/27/2022 | Approved | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 7/27/2022 | Approved | DANIEL VARNUM |
| Wood Frame | 7/27/2022 | Approved | DANIEL VARNUM |
| Special/Order Compliance | 1/25/2023 | Partial Inspection | JEFFREY FULTON |
| Final | 7/25/2023 | Corrections Issued | JEFFREY DURAN |
| Special/Order Compliance | 7/25/2023 | Not Ready for Inspection | JEFFREY DURAN |
| Final | 8/22/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 8/29/2023 | Partial Inspection | JEFFREY FULTON |
| Deputy Steel/Welding | 9/22/2023 | No Result Entered | ROBERT COLE |
| Final | 9/22/2023 | OK to Issue CofO | JEFFREY DURAN |