22135 W ROSCOE BLVD LOT #5 91304

Certificate Information: 22135 W ROSCOE BLVD LOT #5 91304

Application / Permit
18010-20000-02352
Plan Check / Job No.
B18VN08604
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD W/ ATTACHED GARAGE & ROOFTOP DECK (NFPA-13D FIRE SPRINKLERS THROUGHOUT) [Small lot subdivision pursuant to Tentative Tract Map No. 77107. A certificate of occupancy (temporary or final shall not be issued until after the final map has been recorded]
Permit Issued
Issued on 12/28/2018
Issuing Office
Metro
Current Status
CofO Issued on 11/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2018 APPLICANT
Green Plans Picked Up 6/6/2018 APPLICANT
Assigned to Plan Check Engineer 6/14/2018 NILOOFAR MEHRAIN
Corrections Issued 6/18/2018 NILOOFAR MEHRAIN
Quality Review Completed 6/20/2018 ABDUL CHEGENI
Building Plans Picked Up 6/21/2018 APPLICANT
Applicant returned to address corrections 8/8/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/26/2018 NILOOFAR MEHRAIN
Plan Check Approved 10/11/2018 NILOOFAR MEHRAIN
Issued 12/28/2018 LADBS
TCO Issued (Expire Date: 12-01-2020) 6/4/2020 JEFFREY DURAN
CofO in Progress 11/30/2020 JOSEPH SAGEN
Permit Finaled 11/30/2020 DONALD SUNSERI
CofO Issued 11/30/2020 DONALD SUNSERI
Permit Finaled 11/30/2020 DONALD SUNSERI

Permit Application Clearance Information

Low Impact Development Cleared 6/25/2018 SAM NAVID
Green Code Cleared 8/28/2018 DAVID MATSON
Hydrant and Access approval Cleared 9/21/2018 JOHN DALLAS
"Q" conditions Cleared 9/24/2018 STEVEN WECHSLER
"T" removal Cleared 9/24/2018 STEVEN WECHSLER
Miscellaneous Cleared 9/24/2018 STEVEN WECHSLER
Miscellaneous Cleared 9/24/2018 STEVEN WECHSLER
Miscellaneous Cleared 9/24/2018 STEVEN WECHSLER
Tract Map conditions Cleared 9/24/2018 STEVEN WECHSLER
ZA Case Cleared 9/24/2018 STEVEN WECHSLER
Address approval Cleared 9/25/2018 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 9/25/2018 MARKOS PEREZ-BRAN
Highway dedication Cleared 9/25/2018 MARKOS PEREZ-BRAN
Miscellaneous Cleared 9/25/2018 MARKOS PEREZ-BRAN
Permit Cleared 9/25/2018 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 9/25/2018 MARKOS PEREZ-BRAN
GPI Written Notices Cleared 9/27/2018 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 9/27/2018 NILOOFAR MEHRAIN
Sewer availability Cleared 10/22/2018 LEE GUILBEAUX

Contact Information

Architect Watt, Companies; Lic. No.: C23117 2850 RED HILL AVE   #200    SANTA ANA, CA 92705
Engineer Miller, Karen Lynn; Lic. No.: GE2257 5364 DORIS WY      TORRANCE, CA 90505
Engineer Morris, Kyle Byron; Lic. No.: C72911 54 SANDPIPER      IRVINE, CA 92604

Inspector Information

HENRY KIM, (818) 774-4334 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/2/2019 Partial Approval JOHN KIDWELL
PLUMBING-Rough 1/4/2019 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 1/29/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 2/22/2019 Partial Approval BRUCE ROZAK
Drywall Nailing 2/25/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 2/25/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 3/20/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 3/22/2019 Partial Approval BRUCE ROZAK
Insulation 4/2/2019 Partial Approval JOHN KIDWELL
Drywall Nailing 4/4/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 4/5/2019 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 4/12/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 4/19/2019 Partial Approval JOHN KIDWELL
PLUMBING-Rough 5/1/2019 Not Ready for Inspection DONALD SUNSERI
Gas Test 5/2/2019 Not Ready for Inspection BRUCE ROZAK
Insulation 5/2/2019 Partial Approval BRUCE ROZAK
PLUMBING-Rough 5/2/2019 Corrections Issued BRUCE ROZAK
HVAC-Rough 5/3/2019 Approved BRUCE ROZAK
Insulation 5/3/2019 Partial Approval BRUCE ROZAK
PLUMBING-Rough 5/3/2019 Approved BRUCE ROZAK
ELECTRICAL-Rough 5/6/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 5/9/2019 Approved BRUCE ROZAK
Green Building Rough 5/10/2019 Approved BRUCE ROZAK
BUILDING-Rough-Frame 5/15/2019 Approved BRUCE ROZAK
Verify Sprinkler Sign Off 5/15/2019 Approved BRUCE ROZAK
Insulation 5/17/2019 Approved BRUCE ROZAK
Drywall Nailing 5/22/2019 Approved BRUCE ROZAK
Interior/Exterior Lathing 6/11/2019 Approved BRUCE ROZAK
Shower Pan 6/24/2019 Approved BRUCE ROZAK
Gas Test 7/9/2019 Approved BRUCE ROZAK
HVAC-Final 8/20/2019 Not Ready for Inspection BRUCE ROZAK
PLUMBING-Final 8/20/2019 Not Ready for Inspection BRUCE ROZAK
Service/Power Release 8/20/2019 Not Ready for Inspection BRUCE ROZAK
HVAC-Final 9/12/2019 Approved JOSEPH SAGEN
PLUMBING-Final 9/12/2019 Approved JOSEPH SAGEN
Green Building Final 9/26/2019 Approved BRUCE ROZAK
ELECTRICAL-Final 9/30/2019 Not Ready for Inspection BRUCE ROZAK
ELECTRICAL-Final 10/8/2019 Approved DONALD SUNSERI
Gas Test 10/8/2019 Approved DONALD SUNSERI
Pre-Inspection 10/30/2020 Approved JOSEPH SAGEN
Special/Order Compliance 11/10/2020 Approved JOSEPH SAGEN
Final 11/23/2020 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 11/23/2020 Not Ready for Inspection JOSEPH SAGEN
Service/Power Release 11/23/2020 Not Ready for Inspection JOSEPH SAGEN
Smoke Detectors 11/23/2020 Approved JOSEPH SAGEN
Final 11/25/2020 OK to Issue CofO JOSEPH SAGEN
Green Building Final 11/25/2020 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 11/25/2020 SGSOV Approved JOSEPH SAGEN
Service/Power Release 11/25/2020 Approved JOSEPH SAGEN