22134 W QUINN CIR 91304
Certificate Information: 22134 W QUINN CIR 91304
- Application / Permit
- 18010-20000-02351
- Plan Check / Job No.
- B18VN08604
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT) [Small lot subdivision pursuant to Tentative Tract Map No. 77107. A certificate of occupancy (temporary or final shall not be issued until after the final map has been recorded]
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2018 | APPLICANT |
| Green Plans Picked Up | 6/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2018 | NILOOFAR MEHRAIN |
| Corrections Issued | 6/18/2018 | NILOOFAR MEHRAIN |
| Quality Review Completed | 6/20/2018 | ABDUL CHEGENI |
| Building Plans Picked Up | 6/21/2018 | APPLICANT |
| Applicant returned to address corrections | 8/8/2018 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/26/2018 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/17/2019 | NILOOFAR MEHRAIN |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 4/23/2021 | SEAN WIRCH |
| Permit Finaled | 4/26/2021 | MICHAEL SMITH |
| CofO Issued | 4/26/2021 | MICHAEL SMITH |
| Permit Finaled | 4/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/25/2018 | SAM NAVID |
| Green Code | Cleared | 8/28/2018 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 9/21/2018 | JOHN DALLAS |
| "Q" conditions | Cleared | 9/24/2018 | STEVEN WECHSLER |
| "T" removal | Cleared | 9/24/2018 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 9/24/2018 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 9/24/2018 | STEVEN WECHSLER |
| Tract Map conditions | Cleared | 9/24/2018 | STEVEN WECHSLER |
| ZA Case | Cleared | 9/24/2018 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 9/25/2018 | STEVEN WECHSLER |
| Address approval | Cleared | 9/29/2018 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2018 | MARKOS PEREZ-BRAN |
| Highway dedication | Cleared | 9/29/2018 | MARKOS PEREZ-BRAN |
| Miscellaneous | Cleared | 9/29/2018 | MARKOS PEREZ-BRAN |
| Permit | Cleared | 9/29/2018 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 9/29/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 10/25/2018 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 12/17/2019 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 12/17/2019 | NILOOFAR MEHRAIN |
Contact Information
| Architect | Watt, Companies; Lic. No.: C23117 | 2850 RED HILL AVE #200 SANTA ANA, CA 92705 |
| Engineer | Miller, Karen Lynn; Lic. No.: GE2257 | 5364 DORIS WY TORRANCE, CA 90505 |
| Engineer | Morris, Kyle Byron; Lic. No.: C72911 | 54 SANDPIPER IRVINE, CA 92604 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/8/2020 | Approved | SEAN WIRCH |
| Underground Mechanical | 9/8/2020 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 9/23/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2020 | Partial Approval | SEAN WIRCH |
| Drywall Nailing | 11/4/2020 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2020 | Partial Approval | JOSEPH SAGEN |
| Pre-Inspection | 11/19/2020 | Not Ready for Inspection | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2020 | Partial Approval | JOSEPH SAGEN |
| Deputy Drilled-In Anchors | 12/22/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2021 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 1/11/2021 | Approved | JOSEPH SAGEN |
| Pre-Inspection | 1/11/2021 | Partial Approval | JOSEPH SAGEN |
| HVAC-Rough | 1/13/2021 | Approved | JOSEPH SAGEN |
| PLUMBING-Rough | 1/13/2021 | Approved | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 1/14/2021 | Approved | JOSEPH SAGEN |
| Green Building Rough | 1/14/2021 | Approved | JOSEPH SAGEN |
| Verify Sprinkler Sign Off | 1/14/2021 | Approved | JOSEPH SAGEN |
| Insulation | 1/19/2021 | Approved | JOSEPH SAGEN |
| Drywall Nailing | 1/26/2021 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 1/26/2021 | Partial Approval | SEAN WIRCH |
| Gas Test | 3/12/2021 | Approved | JOSEPH SAGEN |
| SGSOV-Seismic Gas S/O Valve | 3/15/2021 | SGSOV Not Ready | JOSEPH SAGEN |
| Service/Power Release | 3/15/2021 | Approved | JOSEPH SAGEN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2021 | SGSOV Approved | JOSEPH SAGEN |
| ELECTRICAL-Final | 4/1/2021 | Approved | JOSEPH SAGEN |
| HVAC-Final | 4/1/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| HVAC-Final | 4/8/2021 | Approved | JOSEPH SAGEN |
| PLUMBING-Final | 4/12/2021 | Approved | JOSEPH SAGEN |
| Final | 4/23/2021 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 4/23/2021 | Approved | SEAN WIRCH |
| Smoke Detectors | 4/23/2021 | Approved | SEAN WIRCH |