6721 W DREXEL AVE 90048
Certificate Information: 6721 W DREXEL AVE 90048
- Application / Permit
- 18010-20000-02262
- Plan Check / Job No.
- B18VN08403
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2 Story Single Family Dwelling over basement irregular shaped (58'x34'-8")
- Permit Issued
- Issued on 7/2/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2018 | ALYSSA N NARCISO |
| Corrections Issued | 7/11/2018 | ALYSSA N NARCISO |
| Quality Review Completed | 7/12/2018 | STEVEN KIM |
| Building Plans Picked Up | 7/16/2018 | APPLICANT |
| Green Plans Picked Up | 7/16/2018 | APPLICANT |
| Applicant returned to address corrections | 8/31/2018 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 10/10/2018 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 2/28/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 3/12/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 4/16/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 5/1/2019 | ALYSSA N NARCISO |
| Plan Check Approved | 5/13/2019 | ALYSSA N NARCISO |
| Issued | 7/2/2019 | LADBS |
| CofO in Progress | 2/4/2021 | EVAN COOPER |
| Permit Finaled | 3/2/2021 | KENNETH NAGLE |
| CofO Issued | 3/2/2021 | KENNETH NAGLE |
| Permit Finaled | 3/2/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2018 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2018 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 8/28/2018 | JOHN DALLAS |
| Low Impact Development | Cleared | 8/28/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/28/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 8/28/2018 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 9/5/2018 | PARISA ZAHABI |
| ZI | Cleared | 2/21/2019 | RICK TORRES |
| Excavation more than 5-ft deep | Cleared | 5/13/2019 | CALOSHA APPROVED |
Contact Information
| Architect | Jazayeri, Siavash; Lic. No.: C22240 | 20230 WELLS DR WOODLAND HILLS, CA 91364 |
| Contractor | Owner-Builder | , |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
| Engineer | Yuzon, Benigno S Jr; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 7/29/2019 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 9/16/2019 | Corrections Issued | EVAN COOPER |
| Underground Mechanical | 9/16/2019 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 11/7/2019 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 11/7/2019 | Approved | EVAN COOPER |
| METHANE-Subgrade | 11/7/2019 | Approved | EVAN COOPER |
| Deputy Reinf. Concrete | 11/12/2019 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2019 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2019 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 12/31/2019 | No Access for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2020 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 1/13/2020 | Corrections Issued | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 1/15/2020 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2020 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 4/1/2020 | Approved | EVAN COOPER |
| HVAC-Rough | 4/1/2020 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 4/1/2020 | Approved | EVAN COOPER |
| Special/Order Compliance | 4/1/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/7/2020 | Partial Approval | EVAN COOPER |
| Green Building Rough | 4/7/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 4/7/2020 | Partial Approval | EVAN COOPER |
| METHANE-Rough | 4/7/2020 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 4/7/2020 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 4/13/2020 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2020 | Partial Approval | EVAN COOPER |
| Insulation | 4/16/2020 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 4/16/2020 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 4/24/2020 | Approved | KENNETH NAGLE |
| Green Building Rough | 4/24/2020 | Approved | KENNETH NAGLE |
| Insulation | 4/24/2020 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 4/24/2020 | Partial Approval | KENNETH NAGLE |
| METHANE-Rough | 4/24/2020 | Approved | KENNETH NAGLE |
| Verify Sprinkler Sign Off | 4/24/2020 | Approved | KENNETH NAGLE |
| Shower Pan | 4/27/2020 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 5/1/2020 | Approved | EVAN COOPER |
| Shower Pan | 5/1/2020 | Approved | EVAN COOPER |
| Deck | 7/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 9/10/2020 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 9/10/2020 | Approved | EVAN COOPER |
| Green Building Final | 9/10/2020 | Not Ready for Inspection | EVAN COOPER |
| Pre-Inspection | 9/10/2020 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/10/2020 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 9/10/2020 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 9/10/2020 | Approved | EVAN COOPER |
| Final | 9/22/2020 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 9/22/2020 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 9/22/2020 | Not Ready for Inspection | EVAN COOPER |
| Final | 11/23/2020 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 11/23/2020 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 11/23/2020 | Corrections Issued | EVAN COOPER |
| Final | 12/9/2020 | Corrections Issued | EVAN COOPER |
| Green Building Final | 12/9/2020 | Approved | EVAN COOPER |
| Service/Power Release | 12/9/2020 | Approved | EVAN COOPER |
| Final | 12/15/2020 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 1/7/2021 | Approved | KEVIN SARGSYAN |
| Final | 1/7/2021 | Corrections Issued | KEVIN SARGSYAN |
| Service/Power Release | 1/7/2021 | Not Required | KEVIN SARGSYAN |
| Final | 2/1/2021 | Corrections Issued | EVAN COOPER |
| Final | 2/4/2021 | Conditional Approval | EVAN COOPER |
| HVAC-Final | 2/4/2021 | Approved | EVAN COOPER |