2828 W LONDON ST 1-16 90026
Certificate Information: 2828 W LONDON ST 1-16 90026
- Application / Permit
- 18010-20000-02214
- Plan Check / Job No.
- B18VN08251
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- PROPOSED 2 STORY 16 UNIT APT OVER PRIVATE GROUND LEVEL PRIVATE GARAGE, TOTAL OF 3-STORY BLDG.. <SPRINKLERS REQ'D THROUGHOUT NFPA-13>
- Permit Issued
- Issued on 12/30/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 6/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2018 | ABDUL CHEGENI |
| Green Plans Picked Up | 6/28/2018 | APPLICANT |
| Corrections Issued | 7/25/2018 | ABDUL CHEGENI |
| Quality Review Completed | 8/2/2018 | STEVEN KIM |
| Building Plans Picked Up | 8/2/2018 | APPLICANT |
| Applicant returned to address corrections | 6/3/2019 | ABDUL CHEGENI |
| Applicant returned to address corrections | 7/23/2019 | ABDUL CHEGENI |
| Applicant returned to address corrections | 9/16/2019 | ABDUL CHEGENI |
| Plan Check Approved | 12/30/2019 | ABDUL CHEGENI |
| Issued | 12/30/2019 | LADBS |
| CofO in Progress | 4/26/2023 | TED RIES |
| Permit Finaled | 4/26/2023 | TED RIES |
| CofO Issued | 4/26/2023 | TED RIES |
| Permit Finaled | 4/26/2023 | TED RIES |
Permit Application Clearance Information
| Address approval | Cleared | 8/8/2018 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2018 | ADRIAN SANCHEZ |
| Highway dedication | Cleared | 8/8/2018 | ADRIAN SANCHEZ |
| Permit | Cleared | 8/8/2018 | ADRIAN SANCHEZ |
| Fire Marshall Fire Life Safety | Cleared | 9/18/2018 | GEORGE SUCHAND |
| ZI | Cleared | 10/29/2018 | DAISY BENICIA |
| ZI | Cleared | 10/29/2018 | DAISY BENICIA |
| DAS Clearance | Cleared | 11/29/2018 | ABDUL CHEGENI |
| Sewer availability | Cleared | 4/23/2019 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 4/30/2019 | ANDRES COVARRUBIAS |
| Building over 3-story or 36-ft | Cleared | 6/3/2019 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 6/3/2019 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 6/3/2019 | ABDUL CHEGENI |
| Grading Pre-Inspection | Cleared | 6/3/2019 | ABDUL CHEGENI |
| Roof/Waste drainage to street | Cleared | 6/4/2019 | MARKOS PEREZ-BRAN |
| Frnt yard landscape/Water mgmt | Cleared | 7/2/2019 | SHEILA GERSHON |
| Green Code | Cleared | 7/2/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 7/2/2019 | GILBERT URREA |
| Opn space landscape/Water mgmt | Cleared | 7/2/2019 | SHEILA GERSHON |
| Work Adjacent to Public Way | Cleared | 12/9/2019 | BOK GOH |
| Miscellaneous | Cleared | 12/30/2019 | ABDUL CHEGENI |
Contact Information
| Contractor | Ds Builders Group Inc; Lic. No.: 1045516-B | 22647 VENTURA BOULEVARD #534 WOODLAND HILLS, CA 91364 |
| Engineer | Gharai, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
| Engineer | Korganyan,, Karen; Lic. No.: L8510 | 5642 ETIWANDA AVE 9 TARZANA, CA 91356 |
| Engineer | Vidal, Juan Alonso; Lic. No.: GE861 | 15331 DOGWOOD ST WESTMINSTER, CA 92683 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/10/2020 | Partial Approval | DANIEL MC AULIFFE |
| METHANE-Barrier | 11/10/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| METHANE-Subgrade | 11/10/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 11/20/2020 | Partial Approval | DANIEL MC AULIFFE |
| METHANE-Barrier | 11/20/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| METHANE-Subgrade | 11/20/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 11/23/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Insulation | 12/7/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 12/21/2020 | Partial Approval | DANIEL MC AULIFFE |
| Green Building Rough | 12/21/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| METHANE-Barrier | 12/21/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| METHANE-Rough | 12/21/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| METHANE-Subgrade | 12/21/2020 | Partial Approval | DANIEL MC AULIFFE |
| Reinforced Concrete Frame | 12/21/2020 | Partial Approval | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 12/21/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Deputy Shotcrete | 12/28/2020 | Conditional Approval | DANIEL MC AULIFFE |
| METHANE-Subgrade | 2/12/2021 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 3/5/2021 | Approved | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 3/5/2021 | Partial Approval | DANIEL MC AULIFFE |
| METHANE-Barrier | 3/5/2021 | Approved | DANIEL MC AULIFFE |
| METHANE-Subgrade | 3/5/2021 | Approved | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 4/20/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 4/21/2021 | Partial Inspection | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 4/29/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 5/7/2021 | Approved | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 5/7/2021 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 5/11/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Wood Construction | 6/3/2021 | Conditional Approval | DAVID BURKHEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2021 | Partial Approval | DAVID BURKHEAD |
| Deputy Wood Construction | 7/12/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Partial Approval | DANIEL MC AULIFFE |
| Green Building Rough | 7/14/2021 | Approved | DANIEL MC AULIFFE |
| METHANE-Rough | 7/14/2021 | Approved | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 7/14/2021 | Approved | DANIEL MC AULIFFE |
| Wood Frame | 7/14/2021 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 8/26/2021 | Partial Inspection | DANIEL MC AULIFFE |
| Deputy Wood Construction | 9/9/2021 | Approved | DANIEL MC AULIFFE |
| Wood Frame | 9/9/2021 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 10/4/2021 | Partial Approval | DANIEL MC AULIFFE |
| Wood Frame | 10/12/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Insulation | 10/14/2021 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 10/14/2021 | Approved | RAFAEL ESPINOZA |
| Insulation | 10/25/2021 | Partial Approval | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 12/3/2021 | Approved | DANIEL MC AULIFFE |
| Drywall Nailing | 12/16/2021 | Partial Approval | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 2/23/2022 | Partial Approval | DANIEL MC AULIFFE |
| Light Gage Steel Frame | 2/23/2022 | Partial Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 3/14/2022 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 6/7/2022 | Not Ready for Inspection | TED RIES |
| Final | 6/7/2022 | Not Ready for Inspection | TED RIES |
| Footing/Foundation/Slab | 6/7/2022 | Not Ready for Inspection | TED RIES |
| Green Building Final | 6/7/2022 | Not Ready for Inspection | TED RIES |
| Reinforced Concrete Frame | 6/7/2022 | Not Ready for Inspection | TED RIES |
| Reinforced Masonry Frame | 6/7/2022 | Not Ready for Inspection | TED RIES |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Not Ready | TED RIES |
| Smoke Detectors | 6/7/2022 | Not Ready for Inspection | TED RIES |
| Structural Steel Frame | 6/7/2022 | Not Ready for Inspection | TED RIES |
| Drywall Nailing | 7/28/2022 | Conditional Approval | TED RIES |
| Final | 7/28/2022 | Partial Inspection | TED RIES |
| Footing/Foundation/Slab | 7/28/2022 | Conditional Approval | TED RIES |
| Green Building Final | 7/28/2022 | Approved | TED RIES |
| Reinforced Concrete Frame | 7/28/2022 | Conditional Approval | TED RIES |
| Reinforced Masonry Frame | 7/28/2022 | Conditional Approval | TED RIES |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Not Ready | TED RIES |
| Smoke Detectors | 7/28/2022 | Approved | TED RIES |
| Structural Steel Frame | 7/28/2022 | Conditional Approval | TED RIES |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Not Ready | TED RIES |
| Drywall Nailing | 1/27/2023 | Not Ready for Inspection | TED RIES |
| Final | 1/27/2023 | Not Ready for Inspection | TED RIES |
| Footing/Foundation/Slab | 1/27/2023 | Not Ready for Inspection | TED RIES |
| Reinforced Concrete Frame | 1/27/2023 | Not Ready for Inspection | TED RIES |
| Reinforced Masonry Frame | 1/27/2023 | Not Ready for Inspection | TED RIES |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Not Ready | TED RIES |
| Structural Steel Frame | 1/27/2023 | Not Ready for Inspection | TED RIES |
| Drywall Nailing | 3/31/2023 | Approved | TED RIES |
| Final | 3/31/2023 | Conditional Approval | TED RIES |
| Footing/Foundation/Slab | 3/31/2023 | Approved | TED RIES |
| Reinforced Concrete Frame | 3/31/2023 | Approved | TED RIES |
| Reinforced Masonry Frame | 3/31/2023 | Approved | TED RIES |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | TED RIES |
| Structural Steel Frame | 3/31/2023 | Approved | TED RIES |