8201 W BELLGAVE PL 90069
Certificate Information: 8201 W BELLGAVE PL 90069
- Application / Permit
- 18010-20000-02195
- Plan Check / Job No.
- B18VN08143
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- (N) 1-STORY POOL EQUIPMENT BLDG UNDER (N) POOL ON PILES PER ENG'R DESIGN
- Permit Issued
- Issued on 7/10/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2018 | APPLICANT |
| Green Plans Picked Up | 5/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2018 | NILOOFAR MEHRAIN |
| Corrections Issued | 6/12/2018 | NILOOFAR MEHRAIN |
| Quality Review Completed | 6/13/2018 | ABDUL CHEGENI |
| Building Plans Picked Up | 6/15/2018 | APPLICANT |
| Applicant returned to address corrections | 6/28/2018 | NILOOFAR MEHRAIN |
| Plan Check Approved | 7/10/2018 | NILOOFAR MEHRAIN |
| Issued | 7/10/2018 | LADBS |
| CofO in Progress | 6/16/2022 | RAUL BARAJAS |
| CofO in Progress | 6/17/2022 | RAUL BARAJAS |
| Permit Finaled | 8/11/2022 | DEROLD HAUFF |
| CofO Issued | 8/11/2022 | DEROLD HAUFF |
| Permit Finaled | 8/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/12/2018 | NILOOFAR MEHRAIN |
| Hydrant and Access approval | Cleared | 6/20/2018 | JOHN CONNEALLY |
| Hydrant and Access approval | Cleared | 6/20/2018 | JOHN CONNEALLY |
| Green Code | Cleared | 6/21/2018 | MICHAEL AYERS |
| CPC | Cleared | 6/29/2018 | DANALYNN DOMINGUEZ |
| Miscellaneous | Cleared | 6/29/2018 | DANALYNN DOMINGUEZ |
| Miscellaneous | Cleared | 6/29/2018 | DANALYNN DOMINGUEZ |
| Miscellaneous | Cleared | 6/29/2018 | DANALYNN DOMINGUEZ |
| ZA Case | Cleared | 6/29/2018 | DANALYNN DOMINGUEZ |
| ZA Case | Cleared | 6/29/2018 | DANALYNN DOMINGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 7/6/2018 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/6/2018 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Oh'S Design & Development; Lic. No.: 989612-B | 500 SOUTH SHATTO PLACE #411 LOS ANGELES, CA 90020 |
| Engineer | Daneshfar, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
| Geologist | Feffer, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/18/2022 | Approved | RAUL BARAJAS |
| Final | 4/18/2022 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/18/2022 | Approved | RAUL BARAJAS |
| Green Building Final | 4/18/2022 | Approved | RAUL BARAJAS |
| Green Building Rough | 4/18/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | RAUL BARAJAS |
| Service/Power Release | 4/18/2022 | Approved | RAUL BARAJAS |
| Smoke Detectors | 4/18/2022 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 4/18/2022 | Approved | RAUL BARAJAS |
| Final | 6/16/2022 | OK to Issue CofO | RAUL BARAJAS |