13107 W CHASE ST 91331

Certificate Information: 13107 W CHASE ST 91331

Application / Permit
18010-20000-02077
Plan Check / Job No.
B18VN07722
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New irrregular 34'-6''x 38'-0'' 1-story accessory dwelling unit per ab494 and sb229. Work per WFPP.
Permit Issued
Issued on 4/23/2022
Issuing Office
Current Status
CofO Issued on 10/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2018 APPLICANT
Assigned to Plan Check Engineer 6/14/2018 DANNY MORALES
Corrections Issued 6/22/2018 DANNY MORALES
Quality Review Completed 7/3/2018 STEVEN KIM
Building Plans Picked Up 7/9/2018 APPLICANT
Green Plans Picked Up 7/9/2018 APPLICANT
Applicant returned to address corrections 1/24/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/7/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/14/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/28/2022 MOHAMMAD ESMAILI
Plan Check Approved 4/11/2022 MOHAMMAD ESMAILI
Issued 4/23/2022 APPLICANT
CofO in Progress 10/21/2022 MICHEL ABAJAN
CofO Issued 10/25/2022 RONALD MYRICK
Permit Finaled 10/25/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 8/14/2018 EDUARDO PEDROZA
Eng Process Fee Ord 176,300 Cleared 8/14/2018 EDUARDO PEDROZA
Low Impact Development Cleared 8/14/2018 MARTIN FRAGOSO
Sewer availability Cleared 8/14/2018 EDUARDO PEDROZA
Hydrant and Access approval Cleared 8/27/2018 JOHN DALLAS
Green Code Cleared 10/2/2018 PARISA ZAHABI
Construction near power lines Cleared 1/11/2019 RIDWAN HARDY
Roof/Waste drainage to street Cleared 4/11/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/4/2022 Corrections Issued MICHEL ABAJAN
Deputy Reinf. Concrete 5/6/2022 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 5/10/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 5/17/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 5/17/2022 Partial Approval MICHEL ABAJAN
Wood Frame 6/13/2022 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval MICHEL ABAJAN
Wood Frame 6/15/2022 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 6/28/2022 Corrections Issued ROBERT GOLD
HVAC-Rough 6/28/2022 Corrections Issued ROBERT GOLD
PLUMBING-Rough 6/28/2022 Corrections Issued ROBERT GOLD
Wood Frame 6/28/2022 Partial Approval ROBERT GOLD
ELECTRICAL-Rough 7/5/2022 Approved CALEB MEISTER
HVAC-Rough 7/5/2022 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 7/5/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 7/8/2022 Approved MICHEL ABAJAN
Green Building Rough 7/8/2022 Approved MICHEL ABAJAN
HVAC-Rough 7/8/2022 Approved MICHEL ABAJAN
MERV13>=Rough 7/8/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 7/8/2022 Approved MICHEL ABAJAN
Insulation 7/12/2022 Conditional Approval ARAM AVEDISIAN
Interior/Exterior Lathing 7/12/2022 Partial Approval ARAM AVEDISIAN
Drywall Nailing 7/19/2022 Approved MICHEL ABAJAN
Underground Mechanical 8/17/2022 Approved MICHEL ABAJAN
Sewer 9/6/2022 Not Ready for Inspection MICHEL ABAJAN
Sewer 9/8/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/22/2022 Approved MICHEL ABAJAN
HVAC-Final 9/22/2022 Approved MICHEL ABAJAN
PLUMBING-Final 9/22/2022 Approved MICHEL ABAJAN
Final 10/17/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 10/17/2022 Approved MICHEL ABAJAN
MERV13>=Final 10/17/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Approved MICHEL ABAJAN
Service/Power Release 10/17/2022 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 10/17/2022 Approved MICHEL ABAJAN
Final 10/20/2022 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 10/20/2022 Approved MICHEL ABAJAN