13107 W CHASE ST 91331
Certificate Information: 13107 W CHASE ST 91331
- Application / Permit
- 18010-20000-02077
- Plan Check / Job No.
- B18VN07722
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New irrregular 34'-6''x 38'-0'' 1-story accessory dwelling unit per ab494 and sb229. Work per WFPP.
- Permit Issued
- Issued on 4/23/2022
- Issuing Office
- Current Status
- CofO Issued on 10/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2018 | DANNY MORALES |
| Corrections Issued | 6/22/2018 | DANNY MORALES |
| Quality Review Completed | 7/3/2018 | STEVEN KIM |
| Building Plans Picked Up | 7/9/2018 | APPLICANT |
| Green Plans Picked Up | 7/9/2018 | APPLICANT |
| Applicant returned to address corrections | 1/24/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/7/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/14/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/28/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 4/11/2022 | MOHAMMAD ESMAILI |
| Issued | 4/23/2022 | APPLICANT |
| CofO in Progress | 10/21/2022 | MICHEL ABAJAN |
| CofO Issued | 10/25/2022 | RONALD MYRICK |
| Permit Finaled | 10/25/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2018 | EDUARDO PEDROZA |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2018 | EDUARDO PEDROZA |
| Low Impact Development | Cleared | 8/14/2018 | MARTIN FRAGOSO |
| Sewer availability | Cleared | 8/14/2018 | EDUARDO PEDROZA |
| Hydrant and Access approval | Cleared | 8/27/2018 | JOHN DALLAS |
| Green Code | Cleared | 10/2/2018 | PARISA ZAHABI |
| Construction near power lines | Cleared | 1/11/2019 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 4/11/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/4/2022 | Corrections Issued | MICHEL ABAJAN |
| Deputy Reinf. Concrete | 5/6/2022 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 5/10/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/17/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/17/2022 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 6/13/2022 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 6/15/2022 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/28/2022 | Corrections Issued | ROBERT GOLD |
| HVAC-Rough | 6/28/2022 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 6/28/2022 | Corrections Issued | ROBERT GOLD |
| Wood Frame | 6/28/2022 | Partial Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 7/5/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 7/5/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 7/5/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 7/8/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/8/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/8/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 7/8/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 7/8/2022 | Approved | MICHEL ABAJAN |
| Insulation | 7/12/2022 | Conditional Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/12/2022 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 7/19/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 8/17/2022 | Approved | MICHEL ABAJAN |
| Sewer | 9/6/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Sewer | 9/8/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 9/22/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 9/22/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 9/22/2022 | Approved | MICHEL ABAJAN |
| Final | 10/17/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 10/17/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 10/17/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/17/2022 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 10/17/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 10/17/2022 | Approved | MICHEL ABAJAN |
| Final | 10/20/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 10/20/2022 | Approved | MICHEL ABAJAN |