7235 N CLYBOURN AVE 91352
Certificate Information: 7235 N CLYBOURN AVE 91352
- Application / Permit
- 18010-20000-02063
- Plan Check / Job No.
- B18VN07660
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Photographer
- Work Description
- PHOTOGRAPHY STUDIO WITH ATTACHED GARAGE & PARKING LOT STRIPING.
- Permit Issued
- Issued on 5/14/2019
- Issuing Office
- Valley
- Current Status
- Issued on 5/14/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/7/2018 | APPLICANT |
| Green Plans Picked Up | 5/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2018 | RUDOLF KINAR MELIKOFF |
| Corrections Issued | 5/29/2018 | RUDOLF KINAR MELIKOFF |
| Quality Review Completed | 6/1/2018 | BINH PHAN |
| Building Plans Picked Up | 6/1/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 6/1/2018 | APPLICANT |
| Applicant returned to address corrections | 8/3/2018 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 8/15/2018 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 8/17/2018 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 8/27/2018 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 8/30/2018 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 1/18/2019 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 1/30/2019 | RUDOLF KINAR MELIKOFF |
| Plan Check Approved | 5/3/2019 | RUDOLF KINAR MELIKOFF |
| Issued | 5/14/2019 | LADBS |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/29/2018 | RINA LARA |
| Address approval | Cleared | 6/29/2018 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 6/29/2018 | MARKOS PEREZ-BRAN |
| Work Adjacent to Public Way | Cleared | 6/29/2018 | MARKOS PEREZ-BRAN |
| DAS Clearance | Cleared | 7/13/2018 | OLLIE CARTER |
| Hydrant and Access approval | Cleared | 7/13/2018 | JOHN DALLAS |
| Green Code | Cleared | 7/17/2018 | DAVID MATSON |
| Low Impact Development | Cleared | 8/15/2018 | SAM NAVID |
| Highway dedication | Cleared | 11/7/2018 | LEE GUILBEAUX |
| Permit | Cleared | 2/14/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 2/15/2019 | LEE GUILBEAUX |
| Hold | Cleared | 8/14/2019 | LOURDES RAMIRO |
Contact Information
| Contractor | Westgate Home Improvement; Lic. No.: 1032360-B | 1555 N VERDUGO RD STE 101 GLENDALE, CA 91208 |
| Engineer | Kennedy, Thomas James; Lic. No.: C74144 | 5105 E LOS ANGELES AVE 207 SIMI VALLEY, CA 93063 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/3/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Pre-Inspection | 4/22/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Pre-Inspection | 5/12/2020 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/14/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 5/19/2020 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/22/2020 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 5/22/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/22/2020 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 5/27/2020 | Approved | DAVID BURKHEAD |
| Masonry Wall/Backfill | 5/27/2020 | Partial Approval | DAVID BURKHEAD |
| Reinforced Concrete Frame | 5/29/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Masonry Wall/Backfill | 5/30/2020 | Off-Hour Fees Due | |
| Masonry Wall/Backfill | 5/30/2020 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 6/2/2020 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 6/2/2020 | Approved | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 6/2/2020 | Approved | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 6/2/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 6/4/2020 | Corrections Issued | DANNY RODRIGUEZ |
| Green Building Rough | 6/5/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 6/5/2020 | Partial Approval | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/5/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 6/9/2020 | Partial Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 6/11/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 6/16/2020 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 7/1/2020 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 7/23/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 7/23/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 7/23/2020 | Corrections Issued | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 8/14/2020 | Corrections Issued | DANNY RODRIGUEZ |
| Green Building Rough | 8/24/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/24/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 8/24/2020 | No Access for Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2020 | Corrections Issued | DANNY RODRIGUEZ |
| Green Building Rough | 10/2/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/2/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 10/7/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/7/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 10/7/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 10/21/2020 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 10/21/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 10/21/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 10/21/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/21/2020 | Partial Inspection | DANNY RODRIGUEZ |
| Wood Frame | 10/22/2020 | Not Ready for Inspection | HAMID PISHEHVAR |
| Green Building Rough | 11/21/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 11/21/2020 | Off-Hour Fees Due | |
| Verify Sprinkler Sign Off | 11/21/2020 | Off-Hour Fees Due | |
| Verify Sprinkler Sign Off | 11/21/2020 | Partial Inspection | DANNY RODRIGUEZ |
| Wood Frame | 11/21/2020 | Off-Hour Fees Due | |
| Wood Frame | 11/21/2020 | Partial Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 12/3/2020 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 12/3/2020 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 3/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 3/10/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Final | 3/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 3/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 3/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/10/2021 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 3/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Structural Steel Frame | 3/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 3/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 3/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Pre-Inspection | 11/10/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 4/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 4/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Final | 4/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 4/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 4/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 4/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Structural Steel Frame | 4/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 4/29/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 4/29/2022 | Partial Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 10/19/2022 | No Access for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 1/17/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 10/1/2024 | No Access for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 1/7/2025 | No Access for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 2/19/2026 | No Access for Inspection | JOHN KITCKO |
| Special/Order Compliance | 2/20/2026 | No Access for Inspection | JOHN KITCKO |
| Pre-Inspection | 4/14/2026 | Not Ready for Inspection | JOHN KITCKO |
| Posting Pre-Inspection | 4/15/2026 | Partial Inspection | JOHN KITCKO |