11151 W RUNNYMEDE ST 91352

Certificate Information: 11151 W RUNNYMEDE ST 91352

Application / Permit
18010-20000-01939
Plan Check / Job No.
B18VN07509
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE (N) TWO STORY ACCESSORY DWELLING UNIT (PER AB494 AND SB 229) ADDITION TO (E) DETACHED GARAGE
Permit Issued
Issued on 7/30/2021
Issuing Office
Current Status
CofO Issued on 3/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2018 APPLICANT
Green Plans Picked Up 5/18/2018 APPLICANT
Assigned to Plan Check Engineer 5/24/2018 DAWN MC NULTY
Corrections Issued 5/29/2018 DAWN MC NULTY
Quality Review Completed 5/30/2018 CHON CHIO KUO
Building Plans Picked Up 5/30/2018 APPLICANT
Applicant returned to address corrections 4/22/2019 DAWN MC NULTY
Applicant returned to address corrections 5/19/2020 DAWN MC NULTY
Applicant returned to address corrections 4/19/2021 DAWN MC NULTY
Plan Check Approved 4/21/2021 DAWN MC NULTY
Issued 7/30/2021 APPLICANT
CofO in Progress 2/2/2024 JOHN HAYES
Permit Finaled 3/2/2024 RUBEN SALAS
CofO Issued 3/2/2024 RUBEN SALAS
Permit Finaled 3/2/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 11/6/2018 RIDWAN HARDY
Address approval Cleared 2/15/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/15/2019 LEE GUILBEAUX
Permit Cleared 2/15/2019 LEE GUILBEAUX
Sewer availability Cleared 2/15/2019 LEE GUILBEAUX
Hydrant and Access approval Cleared 3/1/2019 GEORGE SUCHAND
Low Impact Development Cleared 3/15/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/15/2019 JAMES MORALEZ
Green Code Cleared 4/4/2019 PARISA ZAHABI

Contact Information

Contractor Owner-Builder       ,
Engineer Abkarian,, Raffi; Lic. No.: C36027 18763 VINTAGE STREET      NORTHRIDGE, CA 91324

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/14/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 2/16/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 2/23/2022 Corrections Issued MATT KELLERMAN
Underground Mechanical 6/16/2022 Partial Approval JOHN HAYES
Wood Frame 6/16/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/27/2022 No Access for Inspection JOHN HAYES
Green Building Rough 6/27/2022 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/6/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 7/6/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 8/31/2022 Partial Approval JOHN HAYES
Green Building Rough 8/31/2022 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 10/24/2022 Partial Approval JOHN HAYES
Green Building Rough 10/24/2022 Partial Approval JOHN HAYES
Interior/Exterior Lathing 11/22/2022 Not Ready for Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 11/22/2022 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 12/2/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 12/2/2022 Approved JOHN HAYES
Interior/Exterior Lathing 12/2/2022 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 12/2/2022 Approved JOHN HAYES
Insulation 12/13/2022 Not Ready for Inspection JOHN HAYES
Underground Mechanical 12/13/2022 Approved JOHN HAYES
Insulation 1/20/2023 Approved JOHN HAYES
Interior/Exterior Lathing 1/20/2023 Approved JOHN HAYES
Drywall Nailing 1/31/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 12/11/2023 Corrections Issued CHRISTOPHER ROJAS
Final 12/11/2023 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 12/11/2023 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 12/21/2023 Not Ready for Inspection JOHN HAYES
Final 12/21/2023 Corrections Issued JOHN HAYES
PLUMBING-Final 12/21/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/22/2024 Approved CHRISTOPHER ROJAS
Final 1/22/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/22/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 1/22/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/22/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 1/22/2024 Approved CHRISTOPHER ROJAS
Final 2/2/2024 OK to Issue CofO JOHN HAYES
Footing/Foundation/Slab 2/2/2024 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV Approved JOHN HAYES