11151 W RUNNYMEDE ST 91352
Certificate Information: 11151 W RUNNYMEDE ST 91352
- Application / Permit
- 18010-20000-01939
- Plan Check / Job No.
- B18VN07509
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE (N) TWO STORY ACCESSORY DWELLING UNIT (PER AB494 AND SB 229) ADDITION TO (E) DETACHED GARAGE
- Permit Issued
- Issued on 7/30/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2018 | APPLICANT |
| Green Plans Picked Up | 5/18/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2018 | DAWN MC NULTY |
| Corrections Issued | 5/29/2018 | DAWN MC NULTY |
| Quality Review Completed | 5/30/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 5/30/2018 | APPLICANT |
| Applicant returned to address corrections | 4/22/2019 | DAWN MC NULTY |
| Applicant returned to address corrections | 5/19/2020 | DAWN MC NULTY |
| Applicant returned to address corrections | 4/19/2021 | DAWN MC NULTY |
| Plan Check Approved | 4/21/2021 | DAWN MC NULTY |
| Issued | 7/30/2021 | APPLICANT |
| CofO in Progress | 2/2/2024 | JOHN HAYES |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
| CofO Issued | 3/2/2024 | RUBEN SALAS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/6/2018 | RIDWAN HARDY |
| Address approval | Cleared | 2/15/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2019 | LEE GUILBEAUX |
| Permit | Cleared | 2/15/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/15/2019 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/1/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 3/15/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/15/2019 | JAMES MORALEZ |
| Green Code | Cleared | 4/4/2019 | PARISA ZAHABI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/14/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 2/16/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/23/2022 | Corrections Issued | MATT KELLERMAN |
| Underground Mechanical | 6/16/2022 | Partial Approval | JOHN HAYES |
| Wood Frame | 6/16/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/27/2022 | No Access for Inspection | JOHN HAYES |
| Green Building Rough | 6/27/2022 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 7/6/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/31/2022 | Partial Approval | JOHN HAYES |
| Green Building Rough | 8/31/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 10/24/2022 | Partial Approval | JOHN HAYES |
| Green Building Rough | 10/24/2022 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 11/22/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 11/22/2022 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/2/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 12/2/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/2/2022 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 12/2/2022 | Approved | JOHN HAYES |
| Insulation | 12/13/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 12/13/2022 | Approved | JOHN HAYES |
| Insulation | 1/20/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 1/20/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 1/31/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 12/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 12/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 12/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 12/21/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/21/2023 | Corrections Issued | JOHN HAYES |
| PLUMBING-Final | 12/21/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/22/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 1/22/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/22/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 1/22/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/22/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 2/2/2024 | OK to Issue CofO | JOHN HAYES |
| Footing/Foundation/Slab | 2/2/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/2/2024 | SGSOV Approved | JOHN HAYES |