11044 W MCBROOM ST 91040
Certificate Information: 11044 W MCBROOM ST 91040
- Application / Permit
- 18010-20000-01907
- Plan Check / Job No.
- B18VN07354
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATT GARAGE
- Permit Issued
- Issued on 8/8/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2018 | APPLICANT |
| Green Plans Picked Up | 5/29/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2018 | CHON CHIO KUO |
| Corrections Issued | 6/21/2018 | CHON CHIO KUO |
| Quality Review Completed | 6/22/2018 | STEVEN KIM |
| Building Plans Picked Up | 6/22/2018 | APPLICANT |
| Applicant returned to address corrections | 8/21/2018 | CHON CHIO KUO |
| Applicant returned to address corrections | 2/20/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/25/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/9/2019 | CHON CHIO KUO |
| Plan Check Approved | 8/5/2019 | CHON CHIO KUO |
| Issued | 8/8/2019 | LADBS |
| CofO in Progress | 2/10/2023 | DAVID ANDERSON |
| CofO Issued | 3/4/2023 | MICHAEL SMITH |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/9/2018 | ROBERT DUFF |
| Green Code | Cleared | 2/20/2019 | MICHAEL AYERS |
| ZA Case | Cleared | 5/21/2019 | SHEILA GERSHON |
| Low Impact Development | Cleared | 7/2/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/2/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 7/10/2019 | ERIK BEASLEY |
| Specific Plan | Cleared | 7/24/2019 | RINA LARA |
| BHO/Hillside ordinance | Cleared | 8/2/2019 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 8/2/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2019 | GUILLERMO PETRA |
| GPI Written Notices | Cleared | 8/5/2019 | CHON CHIO KUO |
| BHO/Hillside ordinance | Cleared | 8/8/2019 | GUILLERMO PETRA |
| Permit | Cleared | 8/8/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Villa Nova Developing Inc; Lic. No.: 706070-B | 8209A FOOTHILL BLVD. STE 700 SUNLAND, CA 91040 |
| Engineer | Nelson, David Tarinton Jr; Lic. No.: C76318 | 38171 TRANQUILA AVE MURRIETA, CA 92563 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/12/2019 | Approved | BEAU COLLINS |
| Wood Frame | 4/20/2021 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/14/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/14/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 5/18/2021 | Partial Inspection | MICHEL ABAJAN |
| HVAC-Rough | 5/18/2021 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 5/20/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Structural Steel Frame | 5/25/2021 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 5/27/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 5/27/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 5/27/2021 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 5/27/2021 | Approved | MATTHEW NELSON |
| Insulation | 6/1/2021 | Approved | GABRIEL HERRERA |
| Interior/Exterior Lathing | 6/3/2021 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 6/8/2021 | Approved | MATTHEW NELSON |
| Grounding or Bonding | 8/13/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| ELECTRICAL-Final | 12/20/2021 | Approved | WILLIAM KUEHN |
| Service/Power Release | 12/20/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Final | 5/27/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 5/27/2022 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 5/27/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 10/12/2022 | Approved | DAVID ANDERSON |
| Final | 11/29/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 11/29/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 11/29/2022 | Corrections Issued | DAVID ANDERSON |
| Final | 12/27/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 12/27/2022 | Approved | DAVID ANDERSON |
| Final | 2/10/2023 | OK to Issue CofO | DAVID ANDERSON |