PLUMBING-Rough
|
8/19/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Footing/Foundation/Slab
|
8/30/2022
|
Partial Approval
|
JEFFREY PARD
|
|
ELECTRICAL-Rough
|
9/8/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Special/Order Compliance
|
9/22/2022
|
Corrections Issued
|
JEFFREY PARD
|
|
Deputy Steel/Welding
|
10/12/2022
|
Approved
|
JEFFREY PARD
|
|
Deputy Steel/Welding
|
10/13/2022
|
Approved
|
JEFFREY PARD
|
|
Deputy Reinf. Concrete
|
10/14/2022
|
Approved
|
JEFFREY PARD
|
|
Deputy Steel/Welding
|
10/14/2022
|
Approved
|
JEFFREY PARD
|
|
Deputy Steel/Welding
|
10/17/2022
|
Approved
|
JEFFREY PARD
|
|
Deputy Reinf. Concrete
|
10/18/2022
|
Conditional Approval
|
HENRY KIM
|
|
Deputy Reinf. Concrete
|
10/28/2022
|
Approved
|
JEFFREY PARD
|
|
Footing/Foundation/Slab
|
10/28/2022
|
Approved
|
JEFFREY PARD
|
|
Deputy Other (see comments)
|
10/31/2022
|
Conditional Approval
|
JEFFREY PARD
|
|
Deputy Wood Construction
|
11/14/2022
|
Approved
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/14/2022
|
Approved
|
JEFFREY PARD
|
|
Interior/Exterior Lathing
|
11/15/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Interior/Exterior Lathing
|
11/16/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/21/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Deputy Wood Construction
|
12/6/2022
|
Approved
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/6/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Interior/Exterior Lathing
|
12/7/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/8/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Interior/Exterior Lathing
|
12/8/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/20/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/27/2022
|
Approved
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/29/2022
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/30/2022
|
Partial Approval
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/3/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Interior/Exterior Lathing
|
1/3/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Interior/Exterior Lathing
|
1/9/2023
|
Partial Approval
|
JEFFREY PARD
|
|
BUILDING-Rough-Frame
|
1/10/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Green Building Rough
|
1/10/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Verify Sprinkler Sign Off
|
1/10/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
BUILDING-Rough-Frame
|
1/20/2023
|
Partial Approval
|
JEFFREY PARD
|
|
Green Building Rough
|
1/20/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Verify Sprinkler Sign Off
|
1/20/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Insulation
|
1/31/2023
|
Partial Approval
|
JEFFREY PARD
|
|
HVAC-Rough
|
2/9/2023
|
Approved
|
JEFFREY PARD
|
|
ELECTRICAL-Rough
|
2/14/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Deputy Wood Construction
|
2/15/2023
|
Approved
|
JEFFREY PARD
|
|
ELECTRICAL-Rough
|
2/17/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
PLUMBING-Rough
|
2/22/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/23/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
PLUMBING-Rough
|
2/24/2023
|
No Access for Inspection
|
JEFFREY PARD
|
|
ELECTRICAL-Rough
|
2/27/2023
|
Approved
|
JEFFREY PARD
|
|
PLUMBING-Rough
|
2/28/2023
|
Approved
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/1/2023
|
Approved
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/8/2023
|
Approved
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/10/2023
|
Approved
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/14/2023
|
Partial Approval
|
JEFFREY PARD
|
|
Insulation
|
3/15/2023
|
Partial Approval
|
JEFFREY PARD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/20/2023
|
Approved
|
JEFFREY PARD
|
|
Shower Pan
|
3/29/2023
|
Approved
|
JEFFREY PARD
|
|
Interior/Exterior Lathing
|
4/10/2023
|
Partial Approval
|
HENRY KIM
|
|
Deputy Wood Construction
|
4/12/2023
|
Approved
|
HENRY KIM
|
|
BUILDING-Rough-Frame
|
4/26/2023
|
Corrections Issued
|
JEFFREY PARD
|
|
Green Building Rough
|
4/26/2023
|
Approved
|
JEFFREY PARD
|
|
Verify Sprinkler Sign Off
|
4/26/2023
|
Approved
|
JEFFREY PARD
|
|
Pre-Inspection
|
4/27/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
BUILDING-Rough-Frame
|
4/28/2023
|
Approved
|
JEFFREY PARD
|
|
Interior/Exterior Lathing
|
5/1/2023
|
Approved
|
JEFFREY PARD
|
|
Insulation
|
5/3/2023
|
Approved
|
JEFFREY PARD
|
|
Drywall Nailing
|
5/8/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Drywall Nailing
|
5/9/2023
|
Approved
|
JEFFREY PARD
|
|
Interior/Exterior Lathing
|
5/10/2023
|
Approved
|
JEFFREY PARD
|
|
Special/Order Compliance
|
5/18/2023
|
Corrections Issued
|
JEFFREY PARD
|
|
Gas Test
|
5/26/2023
|
Corrections Issued
|
JEFFREY PARD
|
|
Gas Test
|
5/31/2023
|
Approved
|
JEFFREY PARD
|
|
ELECTRICAL-Final
|
6/27/2023
|
Approved
|
JEFFREY PARD
|
|
Underground Mechanical
|
6/27/2023
|
Approved
|
JEFFREY PARD
|
|
Underground Mechanical
|
7/10/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Underground Mechanical
|
7/12/2023
|
Approved
|
HENRY KIM
|
|
Service/Power Release
|
10/31/2023
|
Approved
|
HENRY KIM
|
|
Drywall Nailing
|
11/20/2023
|
Approved
|
JEFFREY PARD
|
|
Final
|
11/20/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Green Building Final
|
11/20/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
SGSOV-Seismic Gas S/O Valve
|
11/20/2023
|
SGSOV Not Ready
|
JEFFREY PARD
|
|
Smoke Detectors
|
11/20/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Structural Steel Frame
|
11/20/2023
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Final
|
12/1/2023
|
Corrections Issued
|
JEFFREY PARD
|
|
Green Building Final
|
12/1/2023
|
Approved
|
JEFFREY PARD
|
|
SGSOV-Seismic Gas S/O Valve
|
12/1/2023
|
SGSOV Approved
|
JEFFREY PARD
|
|
Smoke Detectors
|
12/1/2023
|
Approved
|
JEFFREY PARD
|
|
Structural Steel Frame
|
12/1/2023
|
Approved
|
JEFFREY PARD
|
|
Final
|
12/20/2023
|
OK to Issue CofO
|
JEFFREY PARD
|