965 N STALEY LANE 90042

Certificate Information: 965 N STALEY LANE 90042

Application / Permit
18010-20000-01775
Plan Check / Job No.
B18VN07039
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (N) 37'-6" X 58'-2" 2-STORY SFD PER ENGINEERING. NFPA 13D SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/22/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2018 APPLICANT
Green Plans Picked Up 5/7/2018 APPLICANT
Assigned to Plan Check Engineer 5/17/2018 RAPHAEL ROSAS
Corrections Issued 5/19/2018 RAPHAEL ROSAS
Quality Review Completed 5/25/2018 STEVEN KIM
Building Plans Picked Up 5/30/2018 APPLICANT
Applicant returned to address corrections 9/10/2018 RAPHAEL ROSAS
Applicant returned to address corrections 6/10/2022 RAPHAEL ROSAS
Applicant returned to address corrections 10/11/2022 RAPHAEL ROSAS
Applicant returned to address corrections 3/31/2023 RAPHAEL ROSAS
Applicant returned to address corrections 5/10/2023 RAPHAEL ROSAS
Plan Check Approved 5/12/2023 RAPHAEL ROSAS
Issued 9/22/2023 APPLICANT
CofO in Progress 8/5/2025 DAVID WILLIAMS
Permit Finaled 8/10/2025 DEROLD HAUFF
CofO Issued 8/10/2025 DEROLD HAUFF
Permit Finaled 8/10/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/7/2018 KENNETH PHAM
BHO/Hillside ordinance Cleared 6/7/2018 KENNETH PHAM
BHO/Hillside ordinance Cleared 6/7/2018 KENNETH PHAM
Eng Process Fee Ord 176,300 Cleared 6/7/2018 KENNETH PHAM
Permit Cleared 6/7/2018 KENNETH PHAM
Address approval Cleared 7/19/2018 STEVE MELGAR
Sewer availability Cleared 7/19/2018 STEVE MELGAR
Private street Cleared 9/6/2018 DENNIS CHEW
Tract Map conditions Cleared 9/6/2018 DENNIS CHEW
Tract Map conditions Cleared 9/6/2018 DENNIS CHEW
ZA Case Cleared 9/6/2018 DENNIS CHEW
Distance to fire station Cleared 9/19/2018 ROBERT DUFF
Hydrant and Access approval Cleared 9/19/2018 ROBERT DUFF
Low Impact Development Cleared 9/21/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 9/24/2018 LEE GUILBEAUX
Construction near power lines Cleared 11/2/2019 WALTER RAMIREZ
GPI Written Notices Cleared 10/11/2022 RAPHAEL ROSAS
Disturb/Remove Protected Trees Cleared 4/26/2023 ADALBERTO VERA
Grading Pre-Inspection Cleared 5/10/2023 RAPHAEL ROSAS
Green Code Cleared 5/10/2023 DAVID MATSON

Contact Information

Architect Knitter, M J; Lic. No.: C10524 1401 DOVE STREET SUITE 240      NEWPORT BEACH, CA 92660
Contractor S K L Construction; Lic. No.: 958490-B PO BOX 9559      RANCHO CUCAMONGA, CA 91701
Engineer Nguyen, Huan Ngoc; Lic. No.: C64238 7015 PINNACLE POINTE      ORANGE, CA 92869
Engineer Shahidi, Saeed; Lic. No.: C51711 25422 TRABUCO RD #105      LAKE FOREST, CA 92630
Geologist Hill, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 11/7/2023 No Access for Inspection ROY SPAULDING
Underground Mechanical 8/1/2024 Partial Approval ALIZAH MAYAGOITIA
Sewer 8/2/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 8/2/2024 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 8/6/2024 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/6/2024 Approved ALIZAH MAYAGOITIA
Special/Order Compliance 8/6/2024 Partial Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/3/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 11/15/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/19/2024 Corrections Issued LUIS CASTRO
PLUMBING-Rough 11/19/2024 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 11/21/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/22/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 11/25/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 12/2/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 12/3/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 12/3/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 12/6/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/9/2024 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 12/9/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 12/9/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 12/10/2024 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 12/13/2024 Approved ROY SPAULDING
Shower Pan 12/13/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 12/30/2024 Corrections Issued BRENDAN MORELLI
Green Building Rough 12/30/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 12/30/2024 Partial Approval BRENDAN MORELLI
Special/Order Compliance 12/30/2024 Corrections Issued BRENDAN MORELLI
Verify Sprinkler Sign Off 12/30/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 1/3/2025 Corrections Issued CRAIG DAVIS
Insulation 1/3/2025 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 1/3/2025 Approved CRAIG DAVIS
Insulation 1/8/2025 Conditional Approval ALEX COLIN
Drywall Nailing 1/15/2025 Not Ready for Inspection CRAIG DAVIS
Interior/Exterior Lathing 1/17/2025 Approved CRAIG DAVIS
BUILDING-Rough-Frame 1/22/2025 Approved CRAIG DAVIS
Insulation 1/22/2025 Approved CRAIG DAVIS
Drywall Nailing 1/28/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 1/28/2025 Approved ANTHONY RAMOS
Gas Test 3/27/2025 Not Ready for Inspection DAVID WILLIAMS
Gas Test 4/1/2025 Approved REGINA MENDEZ
PLUMBING-Final 4/14/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 5/2/2025 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Final 5/29/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 5/29/2025 Approved DAVID WILLIAMS
HVAC-Final 6/6/2025 Approved DAVID WILLIAMS
Service/Power Release 6/6/2025 Approved DAVID WILLIAMS
Final 7/31/2025 Corrections Issued DAVID WILLIAMS
Final 8/1/2025 Not Ready for Inspection DAVID WILLIAMS
Green Building Final 8/1/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 8/1/2025 Approved DAVID WILLIAMS
Final 8/5/2025 OK to Issue CofO DAVID WILLIAMS