517 N ALTA VISTA BLVD 90036
Certificate Information: 517 N ALTA VISTA BLVD 90036
- Application / Permit
- 18010-20000-01650
- Plan Check / Job No.
- B18VN06424
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 94'-5" X 34' NEW 2-STORY DWELLING WITH ATTACHED GARAGE TO BE FULLY SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 8/1/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/7/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2018 | APPLICANT |
| Green Plans Picked Up | 4/25/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2018 | SARAH YOUSSEF |
| Corrections Issued | 5/7/2018 | SARAH YOUSSEF |
| Quality Review Completed | 5/9/2018 | STEVEN KIM |
| Building Plans Picked Up | 5/9/2018 | APPLICANT |
| Applicant returned to address corrections | 6/12/2018 | SARAH YOUSSEF |
| Plan Check Approved | 6/20/2018 | SARAH YOUSSEF |
| Plan Check Approved | 7/26/2018 | SARAH YOUSSEF |
| Issued | 8/1/2018 | LADBS |
| CofO in Progress | 11/20/2019 | JOSEPH MCGARRY |
| No Progress | 2/15/2020 | JOSEPH MCGARRY |
| CofO in Progress | 6/25/2020 | CHRIS CHRISTENSEN |
| No Progress | 6/26/2020 | CHARLES BOGHOSKHAN |
| CofO in Progress | 10/6/2020 | CHRIS CHRISTENSEN |
| Permit Finaled | 10/7/2020 | DEROLD HAUFF |
| CofO Issued | 10/7/2020 | DEROLD HAUFF |
| Permit Finaled | 10/7/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2018 | KAYLA PEJI |
| Hydrant and Access approval | Cleared | 5/7/2018 | JOHN DALLAS |
| Permit | Cleared | 5/7/2018 | KAYLA PEJI |
| Sewer availability | Cleared | 5/7/2018 | KAYLA PEJI |
| Green Code | Cleared | 5/10/2018 | PARISA ZAHABI |
| Address approval | Cleared | 5/17/2018 | RUDY TERRIQUEZ. |
| Low Impact Development | Cleared | 5/17/2018 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 6/22/2018 | RUDY TERRIQUEZ. |
Contact Information
| Contractor | Building Green Construction Services; Lic. No.: 947229-B | 14541 DELANO STREET VAN NUYS, CA 91411 |
| Engineer | Nazari, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/29/2018 | Partial Inspection | DANNY TOLENTINO |
| Footing/Foundation/Slab | 10/10/2018 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 10/17/2018 | Approved | DANNY TOLENTINO |
| METHANE-Barrier | 10/17/2018 | Approved | DANNY TOLENTINO |
| METHANE-Subgrade | 10/17/2018 | Approved | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 10/26/2018 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 10/26/2018 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2018 | Partial Approval | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 11/30/2018 | Not Ready for Inspection | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2018 | Partial Approval | DANNY TOLENTINO |
| METHANE-Rough | 11/30/2018 | Not Ready for Inspection | DANNY TOLENTINO |
| Verify Sprinkler Sign Off | 11/30/2018 | Not Ready for Inspection | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2018 | Conditional Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2019 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Rough | 3/4/2019 | Approved | BRAD BESCOS |
| PLUMBING-Rough | 3/4/2019 | Approved | BRAD BESCOS |
| Pre-Inspection | 3/7/2019 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/19/2019 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/29/2019 | Partial Approval | BRAD BESCOS |
| Interior/Exterior Lathing | 3/29/2019 | Approved | BRAD BESCOS |
| Shower Pan | 3/29/2019 | Approved | BRAD BESCOS |
| BUILDING-Rough-Frame | 4/5/2019 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/5/2019 | Approved | JOSEPH MCGARRY |
| Insulation | 4/9/2019 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/19/2019 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/19/2019 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 4/19/2019 | Approved | JOSEPH MCGARRY |
| Insulation | 4/19/2019 | Approved | JOSEPH MCGARRY |
| METHANE-Rough | 4/19/2019 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 4/19/2019 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 4/25/2019 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 4/25/2019 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 7/9/2019 | Partial Inspection | JOSEPH MCGARRY |
| Gas Test | 10/3/2019 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 10/3/2019 | Partial Approval | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 10/3/2019 | SGSOV Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 10/3/2019 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Final | 10/16/2019 | Partial Inspection | RAUL BARAJAS |
| Green Building Final | 10/16/2019 | Partial Inspection | RAUL BARAJAS |
| HVAC-Final | 10/16/2019 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Final | 10/16/2019 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 10/23/2019 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Final | 10/23/2019 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 10/23/2019 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 11/6/2019 | Approved | JOSEPH MCGARRY |
| Green Building Final | 11/6/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Final | 11/6/2019 | Approved | JOSEPH MCGARRY |
| Final | 11/19/2019 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 11/19/2019 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 11/19/2019 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 11/19/2019 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 1/25/2020 | Corrections Issued | JOSEPH MCGARRY |
| Verify Rec and Parks Fee Memo | 7/16/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Special/Order Compliance | 9/4/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |