7813 W JAYSEEL ST 91040

Certificate Information: 7813 W JAYSEEL ST 91040

Application / Permit
18010-20000-01612
Plan Check / Job No.
B18VN06252
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
65'-2" x 21'-6" SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/2/2019
Issuing Office
Valley
Current Status
CofO Issued on 11/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2018 APPLICANT
Assigned to Plan Check Engineer 4/26/2018 SELLA BENYAMIN
Corrections Issued 5/4/2018 SELLA BENYAMIN
Quality Review Completed 5/8/2018 STEVEN KIM
Building Plans Picked Up 5/9/2018 APPLICANT
Plan Check Approved 6/28/2019 SELLA BENYAMIN
Issued 8/2/2019 LADBS
CofO in Progress 11/12/2021 MATTHEW NELSON
Permit Finaled 11/24/2021 MICHAEL SMITH
CofO Issued 11/24/2021 MICHAEL SMITH
Permit Finaled 11/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 3/4/2019 MITESH PATEL
Green Code Cleared 3/7/2019 PARISA ZAHABI
ZI Cleared 6/6/2019 ANNA VIDAL
Hydrant and Access approval Cleared 6/14/2019 GEORGE SUCHAND
Address approval Cleared 6/20/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 6/21/2019 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 6/21/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 6/21/2019 MARKOS PEREZ-BRAN
Grading Pre-Inspection Cleared 6/28/2019 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/8/2019 Approved MATTHEW NELSON
PLUMBING-Rough 8/13/2019 Approved MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 8/16/2019 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/9/2019 Approved MATTHEW NELSON
Wood Frame 12/17/2019 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 12/20/2019 Approved MATTHEW NELSON
Green Building Rough 12/20/2019 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 12/20/2019 Approved MATTHEW NELSON
ELECTRICAL-Rough 1/29/2020 Approved MATTHEW NELSON
PLUMBING-Rough 1/29/2020 Approved MATTHEW NELSON
Underground Mechanical 1/31/2020 Not Ready for Inspection MATTHEW NELSON
Deputy Wood Construction 2/5/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 2/6/2020 Approved MATTHEW NELSON
HVAC-Rough 2/6/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/13/2020 Approved MATTHEW NELSON
Insulation 2/18/2020 Approved MATTHEW NELSON
Drywall Nailing 3/3/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/3/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 1/25/2021 Not Ready for Inspection MATTHEW NELSON
Gas Test 1/25/2021 Approved MATTHEW NELSON
HVAC-Final 1/25/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 3/25/2021 Approved MATTHEW NELSON
Final 3/25/2021 Corrections Issued MATTHEW NELSON
Green Building Final 3/25/2021 Approved MATTHEW NELSON
HVAC-Final 3/25/2021 Corrections Issued MATTHEW NELSON
PLUMBING-Final 3/25/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Approved MATTHEW NELSON
Service/Power Release 3/25/2021 Corrections Issued MATTHEW NELSON
Smoke Detectors 3/25/2021 Approved MATTHEW NELSON
ELECTRICAL-Final 5/14/2021 Not Ready for Inspection MATTHEW NELSON
Final 5/14/2021 Corrections Issued MATTHEW NELSON
HVAC-Final 5/14/2021 Not Ready for Inspection MATTHEW NELSON
Service/Power Release 5/14/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 6/16/2021 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 6/16/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 7/6/2021 Approved MATTHEW NELSON
HVAC-Final 7/6/2021 Partial Approval MATTHEW NELSON
Final 7/23/2021 Corrections Issued MATTHEW NELSON
Service/Power Release 7/23/2021 Not Ready for Inspection MATTHEW NELSON
Final 10/1/2021 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 10/1/2021 Approved MICHEL ABAJAN
Service/Power Release 10/1/2021 Partial Approval MICHEL ABAJAN
Final 10/5/2021 Corrections Issued MATTHEW NELSON
Service/Power Release 10/5/2021 Not Ready for Inspection MATTHEW NELSON
Final 11/10/2021 OK to Issue CofO MATTHEW NELSON
Service/Power Release 11/10/2021 Approved MATTHEW NELSON