4422 S MORGAN AVE 90011

Certificate Information: 4422 S MORGAN AVE 90011

Application / Permit
18010-20000-01571
Plan Check / Job No.
B18VN06123
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 27' x 22.5' NFPA13-D fire sprinkler throughout single story dwelling per WFPP
Permit Issued
Issued on 9/21/2018
Issuing Office
Valley
Current Status
CofO Issued on 4/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2018 APPLICANT
Green Plans Picked Up 4/25/2018 APPLICANT
Assigned to Plan Check Engineer 4/26/2018 ALDOUS CHIC
Corrections Issued 4/30/2018 ALDOUS CHIC
Quality Review Completed 5/7/2018 BINH PHAN
Building Plans Picked Up 5/14/2018 APPLICANT
Applicant returned to address corrections 9/11/2018 ALDOUS CHIC
Plan Check Approved 9/21/2018 ALDOUS CHIC
Issued 9/21/2018 LADBS
CofO in Progress 4/9/2026 ALEJANDRO DE ARTOLA
Permit Finaled 4/12/2026 DEROLD HAUFF
CofO Issued 4/12/2026 DEROLD HAUFF
Permit Finaled 4/12/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/10/2018 RUDY TERRIQUEZ.
Eng Process Fee Ord 176,300 Cleared 8/10/2018 RUDY TERRIQUEZ.
Green Code Cleared 8/10/2018 PARISA ZAHABI
Highway dedication Cleared 8/10/2018 RUDY TERRIQUEZ.
Sewer availability Cleared 8/10/2018 RUDY TERRIQUEZ.
Low Impact Development Cleared 8/27/2018 JORGE MEJIA LEMUS
Hydrant and Access approval Cleared 8/29/2018 OSCAR SALGADO JR
Roof/Waste drainage to street Cleared 9/21/2018 RUDY TERRIQUEZ.
Hold Cleared 10/17/2018 LOURDES RAMIRO

Contact Information

Contractor Ochoa Victor Manuel; Lic. No.: 908306-B 13700 FOOTHILL BLVD #920151      SYLMAR, CA 91342

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/22/2018 Corrections Issued ROBERT MCDOWELL
Underground Mechanical 10/22/2018 Conditional Approval ROBERT MCDOWELL
Footing/Foundation/Slab 11/2/2018 Corrections Issued ROBERT MCDOWELL
Footing/Foundation/Slab 11/8/2018 Conditional Approval ROBERT MCDOWELL
BUILDING-Rough-Frame 3/28/2019 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 3/28/2019 Approved ROBERT MCDOWELL
Green Building Rough 3/28/2019 Approved ROBERT MCDOWELL
HVAC-Rough 3/28/2019 Not Ready for Inspection ROBERT MCDOWELL
Verify Sprinkler Sign Off 3/28/2019 Approved ROBERT MCDOWELL
Insulation 4/10/2019 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 5/6/2019 Conditional Approval ALEJANDRO DE ARTOLA
Drywall Nailing 5/31/2019 Approved VICTOR PUKHALSKY
Interior/Exterior Lathing 5/31/2019 Partial Approval VICTOR PUKHALSKY
Final 12/20/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/20/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 12/20/2019 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 12/20/2019 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 12/20/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 12/20/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Final 3/26/2020 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/26/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 3/26/2020 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 3/26/2020 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 3/26/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 3/26/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Special/Order Compliance 3/15/2021 Approved ROBERT MCDOWELL
Special/Order Compliance 4/19/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 1/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 1/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/20/2025 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 8/20/2025 Not Ready for Inspection LUIS CASTRO
Green Building Final 8/20/2025 Not Ready for Inspection LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Not Ready LUIS CASTRO
Service/Power Release 8/20/2025 Not Ready for Inspection LUIS CASTRO
Smoke Detectors 8/20/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 8/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/29/2025 Approved ALEJANDRO DE ARTOLA
Gas Test 8/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 8/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/29/2025 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 8/29/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/15/2025 Not Ready for Inspection JOSH MEISTER
HVAC-Final 10/15/2025 Not Ready for Inspection JOSH MEISTER
PLUMBING-Final 10/15/2025 Not Ready for Inspection JOSH MEISTER
Service/Power Release 10/15/2025 Not Ready for Inspection JOSH MEISTER
ELECTRICAL-Final 10/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/28/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 10/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 10/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 11/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/5/2026 Approved ALEJANDRO DE ARTOLA
Final 3/5/2026 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 3/5/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 3/5/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 3/5/2026 Approved ALEJANDRO DE ARTOLA
Service/Power Release 3/5/2026 Approved ALEJANDRO DE ARTOLA
Gas Test 4/6/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/7/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/8/2026 OK to Issue CofO ALEJANDRO DE ARTOLA
Gas Test 4/8/2026 Approved ALEJANDRO DE ARTOLA